Download:
docx |
pdf
Agreement Seeking Follow-up Questionnaire for an Administrative
Proceeding - Case Lead
OMB Number: 2010-0042, 2434.54
The U.S. Environmental Protection
Agency, Conflict Prevention and Resolution Center (CPRC) requests
your assistance in evaluating this facilitated process. As a part of
this evaluation, we ask the various participants who have been
involved in this project or case to provide us with information about
their experience. The data compiled will be used to improve future
facilitation services provided by the CPRC.
The CPRC will not report information from this evaluation in a way
that respondents or their organizations can be identified. Moreover,
the identity of individual respondents will be kept confidential and
will not be disclosed.
Please indicate the extent to which
agreement was reached.
To answer this question, think about
those issues that were central to the discussions and needed to be
addressed to resolve or advance the matter
THE
TERM "AGREEMENT" APPLIES TO THE WRITTEN OR UNWRITTEN
AGREEMENT(S) YOU REACHED WITH OTHER PARTICIPANTS IN THE PROCESS,
INCLUDING PLANS, PROPOSALS/RECOMMENDATIONS, PROCEDURES, COLLABORATIVE
DECISIONS TO WORK TOGETHER AND SETTLEMENTS. WE USE THE TERM
AGREEMENT
RECOGNIZING THAT THERE MAY HAVE BEEN MORE THAN ONE AGREEMENT.
(CHECK
ONLY ONE)
Agreement
on all key issues
Agreement
on most key issues
Agreement
on some key issues
No
agreement on key issues; progress was made towards addressing the
matter. (To
Q13)
No
agreement, the process ended without us making much progress. (To
Q13)
USE
THE SPACE BELOW IF YOU WOULD LIKE TO ELABORATE ON YOUR RESPONSE:
Rate your level of agreement with the
following statements regarding the agreement.
Scale
0=Not at all, 10=Completely
The agreement reached takes
account of our key interests.
The agreement reached will
effectively resolve the matter.
The agreement reached can be
implemented.
The facilitator’s
involvement was important to efforts to reach agreement
Were there any important issues that
were not addressed by the agreement?
Yes
No
(to
5)
Not
sure (to
5)
Are those important issues from the
previous question satisfactorily addressed or likely to be addressed
by another process that has been agreed to by the parties?
Were you satisfied with the agreement
reached using the facilitated process?
Scale
0=Not at all, 10=Completely
_____
Effects of the
Agreement
In the next
set of questions, you will be asked about the size and the likelihood
of the most important condition that you expect will change as a
result of the agreement reached through the facilitated process.
We recognize
that there can be uncertainty about your answers to these questions.
Without you answering all questions, we cannot produce the needed
estimate of effects from the agreement reached through the
facilitated process.
From your perspective, what condition
has been or will be the most importantly affected or changed as a
result of the agreement made in this facilitated process?
please
select the condition most importantly affected or changed.
Community
/ social
Economic
/ commercial
Historic
/ cultural resource
Natural
resource/ environmental
Public
safety / public health
Recreational
Other
(please comment)
_______________________________________________________
Please
describe the condition you selected above that you expect to change.
For the first [insert number] years
after the agreement (state years) to what extent will the change in
the [pipe
from Q6]
condition be better or worse than existed before the
facilitated process?
Scale
-4 to +4 with -4=significantly worse and +4=significantly better
For the first [insert number] years
after the agreement (state years) how likely is it that the changes
in the [pipe
from Q6] condition will occur?
Scale
0=will not occur, 10=has occurred or definitely will occur.
Please explain your answers about the
amount and likelihood of change in the [pipe from Q6] condition.
Do you anticipate further change in
(pipe
from Q6) effects beyond [insert number] years?
Yes
(describe)
No
Uncertain
Please explain your response.
Were there benefits from the
facilitated process that were not part of the agreement?
Did
the process break an impasse on this matter?
Yes
No
(to
8)
Don’t
know (to
8)
How
important was breaking the impasse to the overall result of the
process?
[0=Not at all, 10=Essential]
To what extent was there change over
the course of the process in the ability of participants to work
together on this matter and in your level of trust in each other?
-
|
Much improved
|
Somewhat improved
|
About the same
|
Somewhat worse
|
Much worse
|
Change
in our ability to work together cooperatively.
|
|
|
|
|
|
Change
in our trust of each other.
|
|
|
|
|
|
Please use this
space if you wish to elaborate on changes in the levels of
cooperation and trust.
_________________________________________________________________
Did you participate in developing the
approach for the facilitated process (e.g., agenda setting, meeting
frequency and location, ground rules)?
I/we
participated and my participation was appropriate
I/we
participated and my participation was unnecessary
I/we
participated and my participation was insufficient
I/we
declined to participate
I
was/we were unable to participate
My/our
participation was unnecessary
Other
(please describe)
What is your estimate of the total
time period in weeks for the facilitated process, from the time your
organization started working with the facilitator to the conclusion
of the facilitated process? This is the elapsed time from beginning
to end, including any inactive time
A
ROUGH ESTIMATE IS FINE. INCLUDE ACTIVITIES PREPARING FOR AND
PARTICIPATING IN NEGOTIATION, TRAVEL, MEETINGS WITH THE FACILITATOR
AND OTHER PARTIES, AND OTHER ACTIVITIES RELATED TO THE FACILITATED
PROCESS. YOU MAY ENTER "DK" IF YOU CAN NOT PROVIDE AN
ESTIMATE.
Total
number of weeks (or DK) ___________
Please
consider a typical week during the time your organization was
negotiating with the assistance of the facilitator.
How many staff members (including you, but excluding any
employees serving as facilitators) were involved directly in the
facilitated process as a regular part of the case team?
INCLUDE
ACTIVITIES PREPARING FOR AND PARTICIPATING IN NEGOTIATION, TRAVEL,
MEETINGS WITH THE FACILITATOR AND OTHER PARTIES, AND OTHER ACTIVITIES
RELATED TO THE FACILITATED PROCESS.
Radio
buttons 1 (only myself) through 10 or more with Don’t Know
Page
Header
The next two
questions help us to calculate the amount of time the case lead (you
or someone else) spent actively working with the facilitator or other
parties in the facilitated process.
You
will be asked about:
the number
of weeks the case lead
was actively involved in the facilitated process (excluding inactive
periods); and
the number of hours
in a typical week the case
lead was actively involved in the facilitated process.
We will multiply these two numbers together to generate a rough
estimate of the amount of time your organization’s case lead
spent on the process.
We recognize that there can be
considerable uncertainty about these values. Without you
providing both numbers we cannot produce the needed
estimate of time spent during the facilitated process for your
organization.
Please make every effort to provide estimates of
weeks and hours in the following two questions.
For how many weeks was your
organization’s staff lead (you or someone
else) actively involved in working with the facilitator or
other parties during the facilitated process (excluding any less
intensive periods)?
YOU
MAY ENTER "DK" IF YOU CAN NOT PROVIDE AN ESTIMATE.
Total
number of weeks the facilitated process was active (or DK)
______________
How many hours did your
organization’s
staff lead (you or someone else) spend
on the facilitated process over the course of a typical week in
which you were actively working with the facilitator or
other parties (excluding less intensive periods)?
If
you don't think you had a typical week, please do your best to
provide a rough estimate of your average weekly time commitment when
you were actively involved in the facilitated process.
INCLUDE
ACTIVITIES PREPARING FOR AND PARTICIPATING IN NEGOTIATION, TRAVEL,
MEETINGS WITH THE FACILITATOR AND OTHER PARTIES, AND OTHER ACTIVITIES
RELATED TO THE FACILITATED PROCESS.
Hours
spent in a typical active week by YOU during the facilitated process
1-5
hours 6-10 hours 11-15 hours 16-20 hours 21-25 hours 26-30
hours 31-35 hours 36-40 hours 41-50 hours Over 50 hours Don't Know
Were there important costs in addition
to staff time to your organization associated with the facilitated
process?
Yes
No
(GO
TO 43)
Not
certain (GO
TO 43)
What were these additional costs
for? PLEASE USE THE LIST BELOW TO IDENTIFY THE IMPORTANT
SOURCES OF THESE COSTS.
Largest
cost
|
|
Next
largest cost
|
|
Third
largest cost
|
|
Fourth
largest cost
|
|
Fifth
largest cost
|
|
Please
estimate the total of these additional costs you identified above.
Under
$10,000
$10,001-$25,000
$25,001-$50,000
$50,001-$75,000
$75,001-$100,000
$100,001-$250,000
Over
$250,000
If you and the other party(ies) had
not used a facilitated process what is the alternative decision
making process that would most likely have been used to reach
an agreement or decision the matter? In responding to this
question, please choose the most likely alternative forum/entity to
the facilitated process that would have produced a decision or
agreement on the same matter, regardless of whether that agreement
or decision might be later appealed in other forums.
We
would have reached a negotiated agreement/settlement with other
party(ies) without the assistance of a facilitator.
The
administrative tribunal would have issued a ruling to decide the
matter before any other appeals occurred.
The
case would have been withdrawn from the administrative tribunal
before a ruling was issued.
Other
(please describe)
We
would like you to now consider the amount of time that would likely
have been required if the decision had been made by [Q24] instead of
by the parties using the facilitated process.
If the decision or agreement had been
made in the alternative process you selected (i.e., [Q24])
what is your estimate of the total time period in
weeks for the facilitated process? This is the elapsed time from
beginning to end, including any inactive time
A
ROUGH ESTIMATE IS FINE. INCLUDE ACTIVITIES PREPARING FOR TRAVEL AND
MEETINGS, AND OTHER ACTIVITIES RELATED TO THE PROCESS. YOU MAY ENTER
“DK” IF YOU CAN NOT PROVIDE AN ESTIMATE.
Please
estimate the total number of weeks (or don’t know)
___________
If the decision or agreement had been made in the alternative
process you selected (i.e., [Q24])
please consider a typical week during the time your organization
would have been actively involved in the process.
Please estimate how many staff
members (including you, but excluding any employees serving as
facilitators) would have been involved directly in the alternative
process you selected as a regular part of the case team?
INCLUDE
ACTIVITIES PREPARING FOR TRAVEL AND MEETINGS, AND OTHER ACTIVITIES
RELATED TO THE PROCESS. YOU MAY ENTER "DK" IF YOU CAN NOT
PROVIDE AN ESTIMATE.
Radio
buttons 1 (only myself) through 10 or more with DK
Please estimate how many weeks you
would have (you or someone else) have been actively involved
in the alternative process you selected (i.e., [Q24])
(excluding any less intensive periods)?
YOU
MAY ENTER "DK" IF YOU CAN NOT PROVIDE AN ESTIMATE.
Total
number of weeks the [Q24]
process was active (or DK) ______________
How many hours would your
organization’s staff lead (you or someone else) have spent
over the course of a typical week in which you were actively working
on the alternative process you selected (i.e., [Q24]),
excluding less intensive periods?
If
you don't think you had a typical week, please do your best to
provide a rough estimate of your average weekly time commitment when
you were actively involved in the process.
INCLUDE
ACTIVITIES PREPARING FOR TRAVEL AND MEETINGS, AND OTHER ACTIVITIES
RELATED TO THE PROCESS. YOU MAY ENTER "DK" IF YOU CAN NOT
PROVIDE AN ESTIMATE.
Hours
spent in a typical active week by YOU during the process
1-5
hours 6-10 hours 11-15 hours 16-20 hours 21-25 hours 26-30
hours 31-35 hours 36-40 hours 41-50 hours Over 50 hours Don't Know
If the alternative process you
selected (i.e., [Q24])
had been used instead of the facilitated process for this case what
is your estimate of the total costs using that process other than
the cost of staff time?
Under
$10,000
$10,001-$25,000
$25,001-$50,000
$50,001-$75,000
$75,001-$100,000
$100,001-$250,000
Over
$250,000
Imagine the [pipe
selected response from Q6] condition that would have occurred
during the first
[insert number] years after a decision or agreement from the
alternative process you identified above (i.e., [pipe Q24]).
Would the [pipe selected
response from Q6] condition
be better or worse than existed before you began the
facilitated process?
Please
indicate the extent to which the decision or agreement from the
alternative process would have produced a better or worse [pipe
selected response from Q16] condition than what existed before the
facilitated process
began.
Scale -4 to +4 with
-4=significantly worse and +4=significantly better
How likely would the result you
indicated in Q30 be for the [pipe
from Q6] condition be during the first [insert number] years
after a decision or agreement from the alternative process?
Scale 0=would not occur, 10=would
have already occurred or definitely would occur.
Please explain your answers about the
amount and likelihood of change in the [pipe from Q6] condition
following the alternative process (i.e., [pipe Q24]) and
agreement/decision.
Would you anticipate further change in
(pipe
from Q6) effects beyond [insert number] years
following the alternative process?
Yes
(describe)
No
Uncertain
Please explain your response.
The next several questions
ask for your views about how the facilitated process and the
alternative you selected above (i.e.,
[Q24])
would compare.
Please
consider how the total costs (time and expenses) of the facilitated
process compare with the potential costs of the alternative that you
identified in Q24 [i.e., pipe
from Q24].
The facilitated process was likely CHECK ONE:
Significantly
more costly than the alternative
Somewhat
more costly that the alternative
Costs
were about the same
Somewhat
less costly that the alternative
Significantly
less costly than the alternative
Don’t
know
How do you think the facilitated
process would compare with the alternative that you selected
(i.e.,[Q24])?
[0=Not
at all, 10=Completely]
The
facilitated process better served the interests of my/our
organization.
The
facilitated process resulted in more timely decisions and
implementation
The
participants are more likely to be able to work together in the
future on matters related to this case.
The
agreement we reached through the facilitated process is less likely
to be challenged.
The
agreement we reached through the facilitated process is better for
us.
In your view, what is the greatest
advantage and disadvantage that the agreement from the facilitated
process provided compared to what would have been possible with the
alternative process you selected (i.e.,
[Q24])?
Greatest advantage
Greatest disadvantage
What is your top suggestion on how the
facilitated process could have been improved?
PLEASE WRITE
"NONE" IF YOU FEEL THIS PROCESS COULD NOT HAVE BEEN
IMPROVED.
Please use the space below for any
additional comments you would like to make.
Thank you for taking
the time to complete this questionnaire.
PERSONS WITH
DISABILITIES WHO REQUIRE ALTERNATIVE MEANS FOR COMMUNICATION OF
PROGRAM EVALUATION INFORMATION SHOULD CONTACT THE CPRC OFFICE.
CONFLICT
PREVENTION AND RESOLUTION CENTER
U.S. Environmental Protection Agency
(MC: 2388A)
1200 Pennsylvania Avenue, NW,
Washington, DC 20460
Telephone: 202.564.0214, Fax:
202.501.1715
Website: www.epa.gov/adr
Email: adr@epa.gov
File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document |
Author | Eric |
File Modified | 0000-00-00 |
File Created | 2021-01-23 |