NSPS for Phosphate Rock Plants (40 CFR part 60, subpart NN) (Renewal)

ICR 201312-2060-003

OMB: 2060-0111

Federal Form Document

Forms and Documents
Document
Name
Status
Supporting Statement A
2013-11-22
IC Document Collections
ICR Details
2060-0111 201312-2060-003
Historical Active 201012-2060-003
EPA/OAR 1078.10
NSPS for Phosphate Rock Plants (40 CFR part 60, subpart NN) (Renewal)
Extension without change of a currently approved collection   No
Regular
Approved without change 01/02/2014
Retrieve Notice of Action (NOA) 12/02/2013
  Inventory as of this Action Requested Previously Approved
01/31/2017 36 Months From Approved 03/31/2014
31 0 29
1,724 0 1,602
132,582 0 124,182

The affected entities are subject to the General Provisions of the NSPS at 40 CFR part 60, subpart A, and any changes, or additions to the Provisions specified at 40 CFR part 60, subpart NN. Owners or operators of the affected facilities must submit a onetime- only report of any physical or operational changes, initial performance tests, and periodic reports and results. Owners or operators are also required to maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. Reports are required semiannually at a minimum.

None
None

Not associated with rulemaking

  78 FR 33409 06/04/2013
78 FR 72078 12/02/2013
No

1
IC Title Form No. Form Name
NSPS for Phosphate Rock Plants (40 CFR Part 60, Subpart NN) (Renewal)

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 31 29 0 0 2 0
Annual Time Burden (Hours) 1,724 1,602 0 0 122 0
Annual Cost Burden (Dollars) 132,582 124,182 0 0 8,400 0
No
No
The increase in burden from the most recently approved ICR is due to an increase in the number of new or modified sources and an increase in labor costs. This ICR uses updated labor rates from the Bureau of Labor Statistics to calculate burden costs.

$6,707
No
No
No
No
No
Uncollected
Learia Williams 202 564-4113 williams.learia@epa.gov

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
12/02/2013


© 2024 OMB.report | Privacy Policy