Labor Rates | ||||
Professional/Technical Level | Labor Rate ($/hr) | Overhead Multiplier | Loaded Labor Rate ($/hr) | Comment |
Junior Technician (TEC1) | $12.00 | 1.90 | $22.80 | |
Senior Technician (TEC2) | $13.20 | 1.83 | $24.20 | |
Junior Professional (PRO1) | $14.40 | 1.75 | $25.22 | |
Mid-level Professional (PRO2) | $16.80 | 1.64 | $27.57 | |
Staff Professional (PRO3) | $20.00 | 1.57 | $31.31 | |
Senior Professional (PRO4) | $26.40 | 1.43 | $37.83 | |
Contractor | $25.00 | 1.00 | $25.00 | |
Labor rates based on year | 1993 |
ESTIMATED | |||||||||||||||||||||||||||||||||||||||||||
Inflation Adjustment for | 1992 | 1993 | 1994 | 1995 | 1996 | 1997 | 1998 | 1999 | 2000 | 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 | 2008 | 2009 | 2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 2033 | Comment |
Annual CPI | 140.3 | 144.5 | 148.2 | 152.4 | 156.9 | 160.5 | 163 | 166.6 | 172.2 | 177.1 | 179.9 | 184 | 188.9 | 195.3 | 201.6 | 207.3 | 215.3 | 214.5 | 218.1 | 224.9 | 229.6 | 233 | 236.7 | 237 | 240 | 245.1 | 251.1 | 255.7 | 258.8 | 271 | 294.4 | 309.12 | 321.4848 | 327.914496 | |||||||||
CPI values from https://www.minneapolisfed.org/about-us/monetary-policy/inflation-calculator/consumer-price-index-1913- |
Monitoring | ||||||||||||||||||||||||||||||||||||||||||||||||
Equipment | ||||||||||||||||||||||||||||||||||||||||||||||||
Costs | Routine Visits | Maintenance | Special Items | |||||||||||||||||||||||||||||||||||||||||||||
Pollutant | Analyzer | Year | Supplies | Year | SpareParts/ Supplies |
Year | Filters | Year | Item 1 | Cost | Year | Item 2 | Cost | Year | Item 3 | Cost | Year | Item 4 | Cost | Year | Year | Item 5 | Cost | Year | Item 6 | Cost | Year | Item 7 | Cost | Year | Item 8 | Cost | Year | Item 9 | Cost | Year | Item 10 | Cost | Year | Item 11 | Cost | Year | Item 12 | Cost | Year | Item 13 | Cost | Year |
CO | $10,000 | 2019 | $800 | 2019 | $1,000 | 2019 | ||||||||||||||||||||||||||||||||||||||||||
Generic Network | Multigas calibrator | $14,000 | 2019 | Zero air supply | $5,980 | 2019 | Ambient air intake manifold assembly | $1,500 | 2019 | Shelter (large, temp controlled) | $30,000 | 2019 | 2019 | Shelter delivery charges | $1,500 | 2019 | Other shelter equipment/accessories | $5,000 | 2019 | Site preparation | $4,500 | 2019 | Power drop | $800 | 2019 | Land/Lease | $4,000 | 2019 | Rent | $284 | 2019 | Miscellaneous equipment | $2,500 | 2019 | Utilities | $1,500 | 2019 | Vehicle | $75,000 | 2019 | ||||||||
NATTS | Analysis (grant to RO) | $129,385 | 2019 | |||||||||||||||||||||||||||||||||||||||||||||
NO2 | $11,700 | 2019 | $800 | 2019 | $1,000 | 2019 | ||||||||||||||||||||||||||||||||||||||||||
O3 | $11,000 | 2019 | $800 | 2019 | $1,000 | 2019 | ||||||||||||||||||||||||||||||||||||||||||
PAMSVOC | $100,000 | 2019 | $16,000 | 2019 | $3,000 | 2019 | Gas cleaning system | 5667 | 2019 | |||||||||||||||||||||||||||||||||||||||
PAMSNMOC | $11,426 | 2019 | $800 | 2019 | $1,000 | 2019 | ||||||||||||||||||||||||||||||||||||||||||
PAMSNOx | $20,500 | 2019 | $800 | 2019 | $1,000 | 2019 | ||||||||||||||||||||||||||||||||||||||||||
PAMSSurfMet | $17,285 | 2019 | $750 | 2019 | $2,000 | 2019 | ||||||||||||||||||||||||||||||||||||||||||
PAMSUpperAir | 2019 | $1,000 | 2019 | $2,000 | 2019 | Cielometer | $26,500 | 2019 | Radar profiler | $125,000 | 2019 | Rawindsondes | $45,000 | 2019 | SODAR | $65,000 | 2019 | 2019 | Computer hardware & software | $8,000 | 2019 | |||||||||||||||||||||||||||
PAMSCarbD | $16,000 | 2019 | $250 | 2019 | $3,400 | 2019 | Carbonyl sample cartridges | $2,900 | 2019 | HPLC/UV with autosampler | $59,000 | 2019 | Equipment (auxiliary) | $1,000 | 2019 | Supplies/reagents | $1,200 | 2019 | 2019 | Calibration Stds | $1,500 | 2019 | ||||||||||||||||||||||||||
PAMSCarbE | $16,000 | 2019 | $750 | 2019 | $10,200 | 2019 | Carbonyl sample cartridges | $8,500 | 2019 | HPLC/UV with autosampler | $59,000 | 2019 | Equipment (auxiliary) | $1,000 | 2019 | Supplies/reagents | $2,400 | 2019 | 2019 | Calibration Stds | $4,500 | 2019 | ||||||||||||||||||||||||||
PAMSHalfD | $16,000 | 2019 | $125 | 2019 | $1,700 | 2019 | Carbonyl sample cartridges | $1,450 | 2019 | HPLC/UV with autosampler | $59,000 | 2019 | Equipment (auxiliary) | $1,000 | 2019 | Supplies/reagents | $600 | 2019 | 2019 | Calibration Stds | $1,500 | 2019 | ||||||||||||||||||||||||||
Pb | $4,000 | 2019 | $150 | 2019 | $300 | 2019 | $150 | 2019 | Audit Cal Kit | $125 | 2019 | Lab Services | $1,610 | 2019 | ||||||||||||||||||||||||||||||||||
PM10 | $5,500 | 2019 | $950 | 2019 | 2019 | Continuous Sampler | $17,600 | 2019 | Sampling Platform | $2,000 | 2019 | Filters | $1,033 | 2019 | Filter Tape | $500 | 2019 | 2019 | Audit/Calibration Kits (Filter Based) | $125 | 2019 | Audit/Calibration Kits (Continuous) | $360 | 2019 | Spare Parts - Continuous | $555 | 2019 | |||||||||||||||||||||
PM25 | $7,000 | 2019 | $950 | 2019 | $400 | 2019 | Sequential Sampler | $11,000 | 2019 | Continuous Sampler | $18,300 | 2019 | Speciation Sampler | $12,000 | 2019 | Data acquisition (laptop/PDA) | $400 | 2019 | 2019 | Speciation sampling national contract | $3,455,984 | 2019 | Microbalance | $3,000 | 2019 | Clean Room for Weighing | $75,000 | 2019 | Filter-based calibration kit | $120 | 2019 | Continuous calibration kit | $75 | 2019 | ||||||||||||||
SENSORS | $1,000 | 2023 | ||||||||||||||||||||||||||||||||||||||||||||||
SO2 | $10,000 | 2019 | $800 | 2019 | $1,000 | 2019 |
Data Entry for | SO2 | Updated on | November 8, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | 83 | ||||||||||||||||||
5.00% | Report Org | Sites | 406 | Report Org | Sites | 406 | Report Org | Sites | 406 | Sites | 406 | |||||||||
Overall Comment | 83 | Spares | 20 | 83 | Spares | 20 | 83 | Spares | 20 | Spares | 20 | |||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 7 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 10 | 10 | 10 | 30 | NA | 2490 | 356 | NA | 2,490 | 356 | NA | 2,490 | 356 | 356 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 276 | 313 | 378 | $967 | $2,069 | $171,697 | $24,528 | $2,151 | $178,565 | $25,509 | $2,194 | $182,137 | $26,020 | $25,352 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 0 | 0 | 4 | 4 | 0 | 8 | NA | 664 | 95 | NA | 664 | 95 | NA | 664 | 95 | 95 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 110 | 125 | 0 | $235 | $503 | $41,726 | $5,961 | $523 | $43,395 | $6,199 | $533 | $44,263 | $6,323 | $6,161 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 3,154 | 451 | NA | 3154 | 451 | NA | 3,154 | 451 | 451 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $213,423 | $30,489 | $2,674 | $221,960 | $31,709 | $2,728 | $226,399 | $32,343 | $31,513 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 7 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $10,000 | 2019 | $12,089 | $4,908,202 | $701,172 | $12,573 | $5,104,530 | $729,219 | $12,824 | $5,206,620 | $743,803 | NA | NA | $724,731 | ||||||
Spare Analyzers | $245,410 | $35,059 | $255,226 | $36,461 | $260,331 | $37,190 | NA | NA | $36,237 | |||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 4 | 0 | 0 | 4 | NA | 1,705 | 244 | NA | 1,705 | 244 | NA | 1,705 | 244 | 244 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 0 | 0 | $110 | $235 | $100,315 | $14,331 | $245 | $99,360 | $14,194 | $250 | $101,347 | $14,478 | $14,334 | NA | NA | |
Installation Hours per site | 0 | 8 | 8 | 0 | 0 | 0 | 16 | NA | 6496 | 928 | NA | 6,496 | 928 | NA | 6,496 | 928 | 928 | NA | NA | |
Cost per site | 0 | 194 | 202 | 0 | 0 | 0 | $396 | $847 | $343,938 | $49,134 | $881 | $357,696 | $51,099 | $899 | $364,850 | $52,121 | $50,785 | NA | NA | |
Sub Total - Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 8,201 | 1,172 | NA | 8,201 | 1,172 | NA | 8,201 | 1,172 | 1,172 | NA | NA | |
Sub Total - Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $799,695 | $1,126 | $830,973 | $1,148 | $847,593 | $65,119 | NA | $760,968 | ||||
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$800 | 2019 | $967 | $392,656 | $392,656 | $1,006 | $408,362 | $408,362 | $1,026 | $416,530 | $416,530 | NA | $405,849 | NA | |||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 48,720 | 48,720 | NA | 48,720 | 48,720 | NA | 48,720 | 48,720 | 48,720 | NA | NA | |
Cost per site | 0 | 1452 | 1513 | 0 | 0 | 0 | $2,965 | $6,343 | $2,575,194 | $2,575,194 | $6,597 | $2,678,202 | $2,678,202 | $6,728 | $2,731,766 | $2,731,766 | $2,661,721 | NA | NA | |
Sub Total - Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 48,720 | 48,720 | NA | 48,720 | 48,720 | NA | 48,720 | 48,720 | 48,720 | NA | NA | |
Sub Total - Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $2,967,850 | $2,967,850 | $7,602 | $3,086,564 | $3,086,564 | $7,754 | $3,148,296 | $3,148,296 | $3,067,570 | $405,849 | NA | |
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$1,000 | 2019 | $1,209 | $490,820 | $490,820 | $1,257 | $510,453 | $510,453 | $1,282 | $520,662 | $520,662 | NA | $507,312 | NA | |||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 6 | 3 | 3 | 0 | 0 | 12 | NA | 4,872 | 4,872 | NA | 4,872 | 4,872 | NA | 4,872 | 4,872 | 4,872 | NA | NA | |
Cost per site | 0 | 145 | 76 | 83 | 0 | 0 | $304 | $650 | $264,033 | $264,033 | $676 | $274,595 | $274,595 | $690 | $280,087 | $280,087 | $272,905 | NA | NA | |
Routine Maint. Hours per site | 0 | 16 | 8 | 32 | 0 | 0 | 56 | NA | 22,736 | 22,736 | NA | 22,736 | 22,736 | NA | 22,736 | 22,736 | 22,736 | NA | NA | |
Cost per site | 0 | 387 | 202 | 882 | 0 | 0 | $1,471 | $3,147 | $1,277,609 | $1,277,609 | $3,273 | $1,328,713 | $1,328,713 | $3,338 | $1,355,288 | $1,355,288 | $1,320,537 | NA | NA | |
Sub Total - Hours | 0 | 22 | 11 | 35 | 0 | 0 | 68 | NA | 27,608 | 27,608 | NA | 27,608 | 27,608 | NA | 27,608 | 27,608 | 27,608 | NA | NA | |
Sub Total - Costs | $0 | $532 | $278 | $965 | $0 | $0 | $2,775 | $5,006 | $2,032,463 | $2,032,463 | $5,206 | $2,113,761 | $2,113,761 | $5,310 | $2,156,036 | $2,156,036 | $1,593,442 | $507,312 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 6 | 3 | 3 | 2 | 0 | 14 | NA | 5,684 | 5,684 | NA | 5,684 | 5,684 | NA | 5,684 | 5,684 | 5,684 | NA | NA | |
Cost per site | 0 | 145 | 76 | 83 | 63 | 0 | $367 | $785 | $318,751 | $318,751 | $817 | $331,501 | $331,501 | $833 | $338,131 | $338,131 | $329,461 | NA | NA | |
Data reporting Hours per site | 0 | 1 | 2 | 4 | 2 | 0 | 9 | NA | 3,654 | 3,654 | NA | 3,654 | 3,654 | NA | 3,654 | 3,654 | 3,654 | NA | NA | |
Cost per site | 0 | 24 | 50 | 110 | 63 | 0 | $247 | $528 | $214,527 | $214,527 | $550 | $223,108 | $223,108 | $561 | $227,570 | $227,570 | $221,735 | NA | NA | |
Data validation Hours per site | 0 | 0 | 4 | 8 | 0 | 0 | 12 | NA | 4,872 | 4,872 | NA | 4,872 | 4,872 | NA | 4,872 | 4,872 | 4,872 | NA | NA | |
Cost per site | 0 | 0 | 101 | 221 | 0 | 0 | $322 | $689 | $279,667 | $279,667 | $716 | $290,854 | $290,854 | $731 | $296,671 | $296,671 | $289,064 | NA | NA | |
Data distribution Hours per site | 0 | 1 | 1 | 2 | 0 | 0 | 4 | NA | 1,624 | 1,624 | NA | 1,624 | 1,624 | NA | 1,624 | 1,624 | 1,624 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 0 | 0 | $104 | $222 | $90,327 | $90,327 | $231 | $93,940 | $93,940 | $236 | $95,819 | $95,819 | $93,362 | NA | NA | |
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | NA | 102 | 102 | NA | 102 | 102 | NA | 102 | 102 | 102 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $5,211 | $5,211 | $13 | $5,420 | $5,420 | $14 | $5,528 | $5,528 | $5,386 | NA | NA | |
Sub Total - Hours | 0 | 8.25 | 10 | 17 | 4 | 0 | 39.25 | NA | 15,936 | 15,936 | NA | 15,936 | 15,936 | NA | 15,936 | 15,936 | 15,936 | NA | NA | |
Sub Total - Costs | $0 | $199 | $252 | $469 | $126 | $0 | $1,046 | $2,238 | $908,483 | $908,483 | $2,327 | $944,823 | $944,823 | $2,374 | $963,719 | $963,719 | $939,008 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 20 | 16 | 0 | 36 | NA | 14,616 | 14,616 | NA | 14,616 | 14,616 | NA | 14,616 | 14,616 | 14,616 | NA | NA | |
Cost per site | 0 | 0 | 0 | 551 | 501 | 0 | $1,052 | $2,250 | $913,695 | $913,695 | $2,340 | $950,242 | $950,242 | $2,387 | $969,247 | $969,247 | $944,395 | NA | NA | |
Routine Calibrations Hours per site | 0 | 26 | 0 | 0 | 0 | 0 | 26 | NA | 10,556 | 10,556 | NA | 10,556 | 10,556 | NA | 10,556 | 10,556 | 10,556 | NA | NA | |
Cost per site | 0 | 629 | 0 | 0 | 0 | 0 | $629 | $1,346 | $546,306 | $546,306 | $1,399 | $568,158 | $568,158 | $1,427 | $579,521 | $579,521 | $564,662 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 2 | 2 | 0 | 4 | NA | 1,624 | 1,624 | NA | 1,624 | 1,624 | NA | 1,624 | 1,624 | 1,624 | NA | NA | |
Cost per site | 0 | 0 | 0 | 55 | 63 | 0 | $118 | $252 | $102,487 | $102,487 | $263 | $106,586 | $106,586 | $268 | $108,718 | $108,718 | $105,930 | NA | NA | |
Training Hours per site | 0 | 1 | 1 | 2 | 1 | 0 | 5 | NA | 2,030 | 2,030 | NA | 2,030 | 2,030 | NA | 2,030 | 2,030 | 2,030 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 31 | 0 | $135 | $289 | $117,252 | $117,252 | $300 | $121,942 | $121,942 | $306 | $124,381 | $124,381 | $121,191 | NA | NA | |
Reporting Hours per site | 0 | 0 | 0 | 3 | 3 | 0 | 6 | NA | 2,436 | 2,436 | NA | 2,436 | 2,436 | NA | 2,436 | 2,436 | 2,436 | NA | NA | |
Cost per site | 0 | 0 | 0 | 83 | 94 | 0 | $177 | $379 | $153,730 | $153,730 | $394 | $159,879 | $159,879 | $402 | $163,077 | $163,077 | $158,895 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0.2 | 0.3 | 0 | 0 | 0.5 | NA | 42 | 42 | NA | 42 | 42 | NA | 42 | 42 | 42 | NA | NA | |
Cost | 0 | 0 | 5 | 8 | 0 | 0 | $13 | $28 | $2,308 | $2,308 | $29 | $2,401 | $2,401 | $30 | $2,449 | $2,449 | $2,386 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 0 | 5 | 5 | 5 | 15 | NA | 1245 | 249 | NA | 1245 | 249 | NA | 1245 | 249 | 249 | NA | NA | |
Cost per RO | 0 | 0 | 0 | 138 | 157 | 189 | $484 | $1,035 | $85,937 | $17,187 | $1,077 | $89,375 | $17,875 | $1,098 | $91,162 | $18,232 | $17,765 | NA | NA | |
Sub Total - Hours | 0 | 27 | 1 | 32 | 27 | 5 | 93 | NA | NA | 31,553 | NA | NA | 31,553 | NA | NA | 31,553 | 31,553 | |||
Sub Total - Costs | $0 | $653 | $30 | $890 | $846 | $189 | $2,608 | $5,579 | NA | $1,852,965 | $5,802 | NA | $1,927,083 | $5,918 | NA | $1,965,625 | $1,915,224 | |||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 8 | 4 | 12 | NA | 4,872 | 4,872 | NA | 4,872 | 4872 | NA | 4,872 | 4,872 | 4,872 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 250 | 151 | $401 | $858 | $348,281 | $348,281 | $892 | $362,212 | $362,212 | $910 | $369,456 | $369,456 | $359,983 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 16 | 8 | 4 | 2 | 30 | NA | 12,180 | 12,180 | NA | 12,180 | 12,180 | NA | 12,180 | 12,180 | 12,180 | NA | NA | |
Cost per site | 0 | 0 | 404 | 221 | 125 | 76 | $826 | $1,767 | $717,407 | $717,407 | $1,838 | $746,103 | $746,103 | $1,874 | $761,025 | $761,025 | $741,511 | NA | NA | |
Sub Total - Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 17052 | 17052 | NA | 17052 | 17052 | NA | 17052 | 17,052 | 17,052 | NA | NA | |
Sub Total - Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $1,065,687 | $1,065,687 | $2,730 | $1,108,315 | $1,108,315 | $2,784 | $1,130,481 | $1,130,481 | $1,101,495 | NA | NA | |
Summary by Element | SO2 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 3,154 | 451 | NA | 3,154 | 451 | NA | 3,154 | 451 | 451 | |||
Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $213,423 | $30,489 | $2,674 | $221,960 | $31,709 | $2,728 | $226,399 | $32,343 | $31,513 | NA | NA | |
2 - Site Installation Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 8,201 | 1,172 | NA | 8,201 | 1,172 | NA | 8,201 | 1,172 | 1,172 | |||
Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $0 | $799,695 | $1,126 | $0 | $830,973 | $1,148 | $0 | $847,593 | $65,119 | NA | $760,968 | |
3 - Supplies & site visits Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 48720 | 48720 | NA | 48720 | 48720 | NA | 48720 | 48720 | 48720 | NA | NA | |
Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $2,967,850 | $2,967,850 | $7,602 | $3,086,564 | $3,086,564 | $7,754 | $3,148,296 | $3,148,296 | $3,067,570 | $405,849 | NA | |
4 - Maintenance Hours | 0 | 22 | 11 | 35 | 0 | 0 | 68 | NA | 27608 | 27608 | NA | 27608 | 27608 | NA | 27608 | 27608 | 27608 | |||
Costs | $0 | $532 | $278 | $965 | $0 | $0 | $2,775 | $5,006 | $2,032,463 | $2,032,463 | $5,206 | $2,113,761 | $2,113,761 | $5,310 | $2,156,036 | $2,156,036 | $1,593,442 | $507,312 | NA | |
5 - Data Managment Hours | 0 | 8.25 | 10 | 17 | 4 | 0 | 39.25 | NA | 15935.5 | 15935.5 | NA | 15935.5 | 15935.5 | NA | 15935.5 | 15935.5 | 15935.5 | NA | NA | |
Costs | $0 | $199 | $252 | $469 | $126 | $0 | $1,046 | $2,238 | $908,483 | $908,483 | $2,327 | $944,823 | $944,823 | $2,374 | $963,719 | $963,719 | $939,008 | NA | NA | |
6 - Quality Assurance Hours | 0 | 27 | 1 | 32 | 27 | 5 | 93 | NA | NA | 31553 | NA | NA | 31553 | NA | NA | 31553 | 31553 | NA | NA | |
Costs | $0 | $653 | $30 | $890 | $846 | $189 | $2,608 | $5,579 | NA | $1,852,965 | $5,802 | NA | $1,927,083 | $5,918 | NA | $1,965,625 | $1,915,224 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 17052 | 17052 | NA | 17052 | 17052 | NA | 17052 | 17052 | 17052 | NA | NA | |
Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $1,065,687 | $1,065,687 | $2,730 | $1,108,315 | $1,108,315 | $2,784 | $1,130,481 | $1,130,481 | $1,101,495 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 125 | 106 | 110 | 57 | 21 | 420 | NA | 120,671 | 142,490 | NA | 120,671 | 142,490 | NA | 120,671 | 142,490 | 142,490 | NA | ||
Costs | $0 | $1,638 | $1,226 | $3,041 | $1,785 | $794 | $13,129 | $26,411 | 7,187,907 | $9,657,632 | $27,468 | 7,475,423 | $10,043,228 | $28,017 | 7,624,932 | $10,244,093 | $8,713,372 | $913,161 | $760,968 |
Data Entry for | CO | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | 71 | ||||||||||||||||||
5.00% | Report Org | Sites | 241 | Report Org | Sites | 241 | Report Org | Sites | 241 | Sites | 241 | |||||||||
Overall Comment | 71 | Spares | 12 | 71 | Spares | 12 | 71 | Spares | 12 | Spares | 12 | |||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 7 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 10 | 10 | 10 | 30 | NA | 2130 | 304 | NA | 2,130 | 304 | NA | 2,130 | 304 | 304 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 276 | 313 | 378 | $967 | $2,069 | $146,874 | $20,982 | $2,151 | $152,749 | $21,821 | $2,194 | $155,804 | $22,258 | $21,687 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 0 | 0 | 4 | 4 | 0 | 8 | NA | 568 | 81 | NA | 568 | 81 | NA | 568 | 81 | 81 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 110 | 125 | 0 | $235 | $503 | $35,693 | $5,099 | $523 | $37,121 | $5,303 | $533 | $37,863 | $5,409 | $5,270 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 2,698 | 385 | NA | 2698 | 385 | NA | 2,698 | 385 | 385 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $182,567 | $26,081 | $2,674 | $189,870 | $27,124 | $2,728 | $193,667 | $27,667 | $26,957 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 7 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $10,000 | 2019 | $12,089 | $2,913,489 | $416,213 | $12,573 | $3,030,029 | $432,861 | $12,824 | $3,090,629 | $441,518 | NA | NA | $430,197 | ||||||
Spare Analyzers | $145,674 | $20,811 | $151,501 | $21,643 | $154,531 | $22,076 | NA | NA | $21,510 | |||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 4 | 0 | 0 | 4 | NA | 1,012 | 145 | NA | 1,012 | 145 | NA | 1,012 | 145 | 145 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 0 | 0 | $110 | $235 | $59,547 | $8,507 | $245 | $58,980 | $8,426 | $250 | $60,159 | $8,594 | $8,509 | NA | NA | |
Installation Hours per site | 0 | 8 | 8 | 0 | 0 | 0 | 16 | NA | 3856 | 551 | NA | 3,856 | 551 | NA | 3,856 | 551 | 551 | NA | NA | |
Cost per site | 0 | 194 | 202 | 0 | 0 | 0 | $396 | $847 | $204,160 | $29,166 | $881 | $212,327 | $30,332 | $899 | $216,573 | $30,939 | $30,146 | NA | NA | |
Sub Total - Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 4,868 | 695 | NA | 4,868 | 695 | NA | 4,868 | 695 | 695 | NA | NA | |
Sub Total - Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $474,696 | $1,126 | $493,262 | $1,148 | $503,128 | $38,655 | NA | $451,707 | ||||
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$800 | 2019 | $967 | $233,079 | $233,079 | $1,006 | $242,402 | $242,402 | $1,026 | $247,250 | $247,250 | NA | $240,911 | NA | |||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 28,920 | 28,920 | NA | 28,920 | 28,920 | NA | 28,920 | 28,920 | 28,920 | NA | NA | |
Cost per site | 0 | 1452 | 1513 | 0 | 0 | 0 | $2,965 | $6,343 | $1,528,625 | $1,528,625 | $6,597 | $1,589,770 | $1,589,770 | $6,728 | $1,621,566 | $1,621,566 | $1,579,987 | NA | NA | |
Sub Total - Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 28,920 | 28,920 | NA | 28,920 | 28,920 | NA | 28,920 | 28,920 | 28,920 | NA | NA | |
Sub Total - Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $1,761,704 | $1,761,704 | $7,602 | $1,832,172 | $1,832,172 | $7,754 | $1,868,816 | $1,868,816 | $1,820,898 | $240,911 | NA | |
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$1,000 | 2019 | $1,209 | $291,349 | $291,349 | $1,257 | $303,003 | $303,003 | $1,282 | $309,063 | $309,063 | NA | $301,138 | NA | |||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 6 | 3 | 3 | 0 | 0 | 12 | NA | 2,892 | 2,892 | NA | 2,892 | 2,892 | NA | 2,892 | 2,892 | 2,892 | NA | NA | |
Cost per site | 0 | 145 | 76 | 83 | 0 | 0 | $304 | $650 | $156,729 | $156,729 | $676 | $162,998 | $162,998 | $690 | $166,258 | $166,258 | $161,995 | NA | NA | |
Routine Maint. Hours per site | 0 | 16 | 8 | 32 | 0 | 0 | 56 | NA | 13,496 | 13,496 | NA | 13,496 | 13,496 | NA | 13,496 | 13,496 | 13,496 | NA | NA | |
Cost per site | 0 | 387 | 202 | 882 | 0 | 0 | $1,471 | $3,147 | $758,384 | $758,384 | $3,273 | $788,719 | $788,719 | $3,338 | $804,493 | $804,493 | $783,865 | NA | NA | |
Sub Total - Hours | 0 | 22 | 11 | 35 | 0 | 0 | 68 | NA | 16,388 | 16,388 | NA | 16,388 | 16,388 | NA | 16,388 | 16,388 | 16,388 | NA | NA | |
Sub Total - Costs | $0 | $532 | $278 | $965 | $0 | $0 | $2,775 | $5,006 | $1,206,462 | $1,206,462 | $5,206 | $1,254,720 | $1,254,720 | $5,310 | $1,279,815 | $1,279,815 | $945,861 | $301,138 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 6 | 3 | 3 | 2 | 0 | 14 | NA | 3,374 | 3,374 | NA | 3,374 | 3,374 | NA | 3,374 | 3,374 | 3,374 | NA | NA | |
Cost per site | 0 | 145 | 76 | 83 | 63 | 0 | $367 | $785 | $189,209 | $189,209 | $817 | $196,778 | $196,778 | $833 | $200,713 | $200,713 | $195,567 | NA | NA | |
Data reporting Hours per site | 0 | 1 | 2 | 4 | 2 | 0 | 9 | NA | 2,169 | 2,169 | NA | 2,169 | 2,169 | NA | 2,169 | 2,169 | 2,169 | NA | NA | |
Cost per site | 0 | 24 | 50 | 110 | 63 | 0 | $247 | $528 | $127,342 | $127,342 | $550 | $132,436 | $132,436 | $561 | $135,085 | $135,085 | $131,621 | NA | NA | |
Data validation Hours per site | 0 | 0 | 4 | 8 | 0 | 0 | 12 | NA | 2,892 | 2,892 | NA | 2,892 | 2,892 | NA | 2,892 | 2,892 | 2,892 | NA | NA | |
Cost per site | 0 | 0 | 101 | 221 | 0 | 0 | $322 | $689 | $166,009 | $166,009 | $716 | $172,650 | $172,650 | $731 | $176,103 | $176,103 | $171,587 | NA | NA | |
Data distribution Hours per site | 0 | 1 | 1 | 2 | 0 | 0 | 4 | NA | 964 | 964 | NA | 964 | 964 | NA | 964 | 964 | 964 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 0 | 0 | $104 | $222 | $53,618 | $53,618 | $231 | $55,763 | $55,763 | $236 | $56,878 | $56,878 | $55,419 | NA | NA | |
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | NA | 60 | 60 | NA | 60 | 60 | NA | 60 | 60 | 60 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $3,093 | $3,093 | $13 | $3,217 | $3,217 | $14 | $3,281 | $3,281 | $3,197 | NA | NA | |
Sub Total - Hours | 0 | 8.25 | 10 | 17 | 4 | 0 | 39.25 | NA | 9,459 | 9,459 | NA | 9,459 | 9,459 | NA | 9,459 | 9,459 | 9,459 | NA | NA | |
Sub Total - Costs | $0 | $199 | $252 | $469 | $126 | $0 | $1,046 | $2,238 | $539,272 | $539,272 | $2,327 | $560,843 | $560,843 | $2,374 | $572,060 | $572,060 | $557,392 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 20 | 16 | 0 | 36 | NA | 8,676 | 8,676 | NA | 8,676 | 8,676 | NA | 8,676 | 8,676 | 8,676 | NA | NA | |
Cost per site | 0 | 0 | 0 | 551 | 501 | 0 | $1,052 | $2,250 | $542,365 | $542,365 | $2,340 | $564,060 | $564,060 | $2,387 | $575,341 | $575,341 | $560,589 | NA | NA | |
Routine Calibrations Hours per site | 0 | 26 | 0 | 0 | 0 | 0 | 26 | NA | 6,266 | 6,266 | NA | 6,266 | 6,266 | NA | 6,266 | 6,266 | 6,266 | NA | NA | |
Cost per site | 0 | 629 | 0 | 0 | 0 | 0 | $629 | $1,346 | $324,285 | $324,285 | $1,399 | $337,256 | $337,256 | $1,427 | $344,002 | $344,002 | $335,181 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 2 | 2 | 0 | 4 | NA | 964 | 964 | NA | 964 | 964 | NA | 964 | 964 | 964 | NA | NA | |
Cost per site | 0 | 0 | 0 | 55 | 63 | 0 | $118 | $252 | $60,836 | $60,836 | $263 | $63,269 | $63,269 | $268 | $64,534 | $64,534 | $62,880 | NA | NA | |
Training Hours per site | 0 | 1 | 1 | 2 | 1 | 0 | 5 | NA | 1,205 | 1,205 | NA | 1,205 | 1,205 | NA | 1,205 | 1,205 | 1,205 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 31 | 0 | $135 | $289 | $69,600 | $69,600 | $300 | $72,384 | $72,384 | $306 | $73,832 | $73,832 | $71,939 | NA | NA | |
Reporting Hours per site | 0 | 0 | 0 | 3 | 3 | 0 | 6 | NA | 1,446 | 1,446 | NA | 1,446 | 1,446 | NA | 1,446 | 1,446 | 1,446 | NA | NA | |
Cost per site | 0 | 0 | 0 | 83 | 94 | 0 | $177 | $379 | $91,254 | $91,254 | $394 | $94,904 | $94,904 | $402 | $96,802 | $96,802 | $94,320 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0.2 | 0.3 | 0 | 0 | 0.5 | NA | 36 | 36 | NA | 36 | 36 | NA | 36 | 36 | 36 | NA | NA | |
Cost | 0 | 0 | 5 | 8 | 0 | 0 | $13 | $28 | $1,975 | $1,975 | $29 | $2,053 | $2,053 | $30 | $2,095 | $2,095 | $2,041 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 0 | 5 | 5 | 5 | 15 | NA | 1065 | 213 | NA | 1065 | 213 | NA | 1065 | 213 | 213 | NA | NA | |
Cost per RO | 0 | 0 | 0 | 138 | 157 | 189 | $484 | $1,035 | $73,513 | $14,703 | $1,077 | $76,453 | $15,291 | $1,098 | $77,982 | $15,596 | $15,197 | NA | NA | |
Sub Total - Hours | 0 | 27 | 1 | 32 | 27 | 5 | 93 | NA | NA | 18,806 | NA | NA | 18,806 | NA | NA | 18,806 | 18,806 | |||
Sub Total - Costs | $0 | $653 | $30 | $890 | $846 | $189 | $2,608 | $5,579 | NA | $1,105,017 | $5,802 | NA | $1,149,218 | $5,918 | NA | $1,172,202 | $1,142,146 | |||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 8 | 4 | 12 | NA | 2,892 | 2,892 | NA | 2,892 | 2892 | NA | 2,892 | 2,892 | 2,892 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 250 | 151 | $401 | $858 | $206,738 | $206,738 | $892 | $215,008 | $215,008 | $910 | $219,308 | $219,308 | $213,685 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 16 | 8 | 4 | 2 | 30 | NA | 7,230 | 7,230 | NA | 7,230 | 7,230 | NA | 7,230 | 7,230 | 7,230 | NA | NA | |
Cost per site | 0 | 0 | 404 | 221 | 125 | 76 | $826 | $1,767 | $425,850 | $425,850 | $1,838 | $442,884 | $442,884 | $1,874 | $451,741 | $451,741 | $440,158 | NA | NA | |
Sub Total - Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 10122 | 10122 | NA | 10122 | 10122 | NA | 10122 | 10,122 | 10,122 | NA | NA | |
Sub Total - Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $632,588 | $632,588 | $2,730 | $657,891 | $657,891 | $2,784 | $671,049 | $671,049 | $653,843 | NA | NA | |
Summary by Element | CO | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 2,698 | 385 | NA | 2,698 | 385 | NA | 2,698 | 385 | 385 | |||
Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $182,567 | $26,081 | $2,674 | $189,870 | $27,124 | $2,728 | $193,667 | $27,667 | $26,957 | NA | NA | |
2 - Site Installation Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 4,868 | 695 | NA | 4,868 | 695 | NA | 4,868 | 695 | 695 | |||
Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $0 | $474,696 | $1,126 | $0 | $493,262 | $1,148 | $0 | $503,128 | $38,655 | NA | $451,707 | |
3 - Supplies & site visits Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 28920 | 28920 | NA | 28920 | 28920 | NA | 28920 | 28920 | 28920 | NA | NA | |
Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $1,761,704 | $1,761,704 | $7,602 | $1,832,172 | $1,832,172 | $7,754 | $1,868,816 | $1,868,816 | $1,820,898 | $240,911 | NA | |
4 - Maintenance Hours | 0 | 22 | 11 | 35 | 0 | 0 | 68 | NA | 16388 | 16388 | NA | 16388 | 16388 | NA | 16388 | 16388 | 16388 | |||
Costs | $0 | $532 | $278 | $965 | $0 | $0 | $2,775 | $5,006 | $1,206,462 | $1,206,462 | $5,206 | $1,254,720 | $1,254,720 | $5,310 | $1,279,815 | $1,279,815 | $945,861 | $301,138 | NA | |
5 - Data Managment Hours | 0 | 8.25 | 10 | 17 | 4 | 0 | 39.25 | NA | 9459.25 | 9459.25 | NA | 9459.25 | 9459.25 | NA | 9459.25 | 9459.25 | 9459.25 | NA | NA | |
Costs | $0 | $199 | $252 | $469 | $126 | $0 | $1,046 | $2,238 | $539,272 | $539,272 | $2,327 | $560,843 | $560,843 | $2,374 | $572,060 | $572,060 | $557,392 | NA | NA | |
6 - Quality Assurance Hours | 0 | 27 | 1 | 32 | 27 | 5 | 93 | NA | NA | 18806 | NA | NA | 18806 | NA | NA | 18806 | 18806 | NA | NA | |
Costs | $0 | $653 | $30 | $890 | $846 | $189 | $2,608 | $5,579 | NA | $1,105,017 | $5,802 | NA | $1,149,218 | $5,918 | NA | $1,172,202 | $1,142,146 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 10122 | 10122 | NA | 10122 | 10122 | NA | 10122 | 10122 | 10122 | NA | NA | |
Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $632,588 | $632,588 | $2,730 | $657,891 | $657,891 | $2,784 | $671,049 | $671,049 | $653,843 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 125 | 106 | 110 | 57 | 21 | 420 | NA | 72,455 | 84,776 | NA | 72,455 | 84,776 | NA | 72,455 | 84,776 | 84,776 | NA | ||
Costs | $0 | $1,638 | $1,226 | $3,041 | $1,785 | $794 | $13,129 | $26,411 | 4,322,593 | $5,745,820 | $27,468 | 4,495,497 | $5,975,231 | $28,017 | 4,585,407 | $6,094,736 | $5,185,750 | $542,049 | $451,707 |
Data Entry for | NO2 | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | 80 | ||||||||||||||||||
5.00% | Report Org | Sites | 437 | Report Org | Sites | 437 | Report Org | Sites | 437 | Sites | 437 | |||||||||
Overall Comment | 80 | Spares | 22 | 80 | Spares | 22 | 80 | Spares | 22 | Spares | 22 | |||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 7 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 10 | 10 | 10 | 30 | NA | 2400 | 343 | NA | 2,400 | 343 | NA | 2,400 | 343 | 343 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 276 | 313 | 378 | $967 | $2,069 | $165,492 | $23,642 | $2,151 | $172,111 | $24,587 | $2,194 | $175,553 | $25,079 | $24,436 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 0 | 0 | 4 | 4 | 0 | 8 | NA | 640 | 91 | NA | 640 | 91 | NA | 640 | 91 | 91 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 110 | 125 | 0 | $235 | $503 | $40,218 | $5,745 | $523 | $41,826 | $5,975 | $533 | $42,663 | $6,095 | $5,938 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 3,040 | 434 | NA | 3040 | 434 | NA | 3,040 | 434 | 434 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $205,709 | $29,387 | $2,674 | $213,938 | $30,563 | $2,728 | $218,216 | $31,174 | $30,374 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 7 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $11,700 | 2019 | $14,144 | $6,181,070 | $883,010 | $14,710 | $6,428,313 | $918,330 | $15,004 | $6,556,879 | $936,697 | NA | NA | $912,679 | ||||||
Spare Analyzers | $309,054 | $44,151 | $321,416 | $45,917 | $327,844 | $46,835 | NA | NA | $45,634 | |||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 4 | 0 | 0 | 4 | NA | 1,835 | 262 | NA | 1,835 | 262 | NA | 1,835 | 262 | 262 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 0 | 0 | $110 | $235 | $107,975 | $15,425 | $245 | $112,294 | $16,042 | $250 | $114,540 | $16,363 | $15,943 | NA | NA | |
Installation Hours per site | 0 | 8 | 8 | 0 | 0 | 0 | 16 | NA | 6992 | 999 | NA | 6,992 | 999 | NA | 6,992 | 999 | 999 | NA | NA | |
Cost per site | 0 | 194 | 202 | 0 | 0 | 0 | $396 | $847 | $370,200 | $52,886 | $881 | $385,008 | $55,001 | $899 | $392,708 | $56,101 | $54,663 | NA | NA | |
Sub Total - Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 8,827 | 1,261 | NA | 8,827 | 1,261 | NA | 8,827 | 1,261 | 1,261 | NA | NA | |
Sub Total - Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $995,471 | $1,126 | $1,035,290 | $1,148 | $1,055,996 | $70,606 | NA | $958,313 | ||||
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$800 | 2019 | $967 | $422,637 | $422,637 | $1,006 | $439,543 | $439,543 | $1,026 | $448,334 | $448,334 | NA | $436,838 | NA | |||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 52,440 | 52,440 | NA | 52,440 | 52,440 | NA | 52,440 | 52,440 | 52,440 | NA | NA | |
Cost per site | 0 | 1452 | 1513 | 0 | 0 | 0 | $2,965 | $6,343 | $2,771,822 | $2,771,822 | $6,597 | $2,882,695 | $2,882,695 | $6,728 | $2,940,349 | $2,940,349 | $2,864,956 | NA | NA | |
Sub Total - Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 52,440 | 52,440 | NA | 52,440 | 52,440 | NA | 52,440 | 52,440 | 52,440 | NA | NA | |
Sub Total - Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $3,194,460 | $3,194,460 | $7,602 | $3,322,238 | $3,322,238 | $7,754 | $3,388,683 | $3,388,683 | $3,301,793 | $436,838 | NA | |
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$1,000 | 2019 | $1,209 | $528,297 | $528,297 | $1,257 | $549,428 | $549,428 | $1,282 | $560,417 | $560,417 | NA | $546,047 | NA | |||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 8 | 8 | 0 | 0 | 16 | NA | 6,992 | 6,992 | NA | 6,992 | 6,992 | NA | 6,992 | 6,992 | 6,992 | NA | NA | |
Cost per site | 0 | 0 | 202 | 221 | 0 | 0 | $423 | $905 | $395,440 | $395,440 | $941 | $411,258 | $411,258 | $960 | $419,483 | $419,483 | $408,727 | NA | NA | |
Routine Maint. Hours per site | 0 | 0 | 30 | 40 | 0 | 0 | 70 | NA | 30,590 | 30,590 | NA | 30,590 | 30,590 | NA | 30,590 | 30,590 | 30,590 | NA | NA | |
Cost per site | 0 | 0 | 757 | 1103 | 0 | 0 | $1,860 | $3,979 | $1,738,816 | $1,738,816 | $4,138 | $1,808,369 | $1,808,369 | $4,221 | $1,844,536 | $1,844,536 | $1,797,240 | NA | NA | |
Sub Total - Hours | 0 | 0 | 38 | 48 | 0 | 0 | 86 | NA | 37,582 | 37,582 | NA | 37,582 | 37,582 | NA | 37,582 | 37,582 | 37,582 | NA | NA | |
Sub Total - Costs | $0 | $0 | $959 | $1,324 | $0 | $0 | $3,283 | $6,093 | $2,662,553 | $2,662,553 | $6,337 | $2,769,055 | $2,769,055 | $6,463 | $2,824,436 | $2,824,436 | $2,205,967 | $546,047 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 8 | 8 | 4 | 0 | 20 | NA | 8,740 | 8,740 | NA | 8,740 | 8,740 | NA | 8,740 | 8,740 | 8,740 | NA | NA | |
Cost per site | 0 | 0 | 202 | 221 | 125 | 0 | $548 | $1,172 | $512,296 | $512,296 | $1,219 | $532,788 | $532,788 | $1,244 | $543,444 | $543,444 | $529,509 | NA | NA | |
Data reporting Hours per site | 0 | 0 | 3 | 4 | 3 | 0 | 10 | NA | 4,370 | 4,370 | NA | 4,370 | 4,370 | NA | 4,370 | 4,370 | 4,370 | NA | NA | |
Cost per site | 0 | 0 | 76 | 110 | 94 | 0 | $280 | $599 | $261,757 | $261,757 | $623 | $272,228 | $272,228 | $635 | $277,672 | $277,672 | $270,552 | NA | NA | |
Data validation Hours per site | 0 | 0 | 5 | 10 | 0 | 0 | 15 | NA | 6,555 | 6,555 | NA | 6,555 | 6,555 | NA | 6,555 | 6,555 | 6,555 | NA | NA | |
Cost per site | 0 | 0 | 126 | 276 | 0 | 0 | $402 | $860 | $375,809 | $375,809 | $894 | $390,841 | $390,841 | $912 | $398,658 | $398,658 | $388,436 | NA | NA | |
Data distribution Hours per site | 0 | 0 | 2 | 3 | 0 | 0 | 5 | NA | 2,185 | 2,185 | NA | 2,185 | 2,185 | NA | 2,185 | 2,185 | 2,185 | NA | NA | |
Cost per site | 0 | 0 | 50 | 83 | 0 | 0 | $133 | $285 | $124,335 | $124,335 | $296 | $129,308 | $129,308 | $302 | $131,894 | $131,894 | $128,512 | NA | NA | |
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | NA | 109 | 109 | NA | 109 | 109 | NA | 109 | 109 | 109 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $5,609 | $5,609 | $13 | $5,833 | $5,833 | $14 | $5,950 | $5,950 | $5,798 | NA | NA | |
Sub Total - Hours | 0 | 0.25 | 18 | 25 | 7 | 0 | 50.25 | NA | 21,959 | 21,959 | NA | 21,959 | 21,959 | NA | 21,959 | 21,959 | 21,959 | NA | NA | |
Sub Total - Costs | $0 | $6 | $454 | $690 | $219 | $0 | $1,369 | $2,929 | $1,279,812 | $1,279,806 | $3,046 | $1,330,998 | $1,330,998 | $3,113 | $1,357,631 | $1,363,227 | $1,324,677 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 36 | 36 | 0 | 72 | NA | 31,464 | 31,464 | NA | 31,464 | 31,464 | NA | 31,464 | 31,464 | 31,464 | NA | NA | |
Cost per site | 0 | 0 | 0 | 992 | 1127 | 0 | $2,119 | $4,533 | $1,980,942 | $1,980,942 | $4,714 | $2,060,179 | $2,060,179 | $4,809 | $2,101,383 | $2,101,383 | $2,047,501 | NA | NA | |
Routine Calibrations Hours per site | 0 | 24 | 24 | 0 | 0 | 0 | 48 | NA | 20,976 | 20,976 | NA | 20,976 | 20,976 | NA | 20,976 | 20,976 | 20,976 | NA | NA | |
Cost per site | 0 | 581 | 605 | 0 | 0 | 0 | $1,186 | $2,537 | $1,108,729 | $1,108,729 | $2,639 | $1,153,078 | $1,153,078 | $2,691 | $1,176,140 | $1,176,140 | $1,145,982 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 2 | 2 | 0 | 4 | NA | 1,748 | 1,748 | NA | 1,748 | 1,748 | NA | 1,748 | 1,748 | 1,748 | NA | NA | |
Cost per site | 0 | 0 | 0 | 55 | 63 | 0 | $118 | $252 | $110,312 | $110,312 | $263 | $114,724 | $114,724 | $268 | $117,019 | $117,019 | $114,018 | NA | NA | |
Training Hours per site | 0 | 1 | 1 | 2 | 1 | 0 | 5 | NA | 2,185 | 2,185 | NA | 2,185 | 2,185 | NA | 2,185 | 2,185 | 2,185 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 31 | 0 | $135 | $289 | $126,204 | $126,204 | $300 | $131,253 | $131,253 | $306 | $133,878 | $133,878 | $130,445 | NA | NA | |
Reporting Hours per site | 0 | 0 | 0 | 3 | 3 | 0 | 6 | NA | 2,622 | 2,622 | NA | 2,622 | 2,622 | NA | 2,622 | 2,622 | 2,622 | NA | NA | |
Cost per site | 0 | 0 | 0 | 83 | 94 | 0 | $177 | $379 | $165,468 | $165,468 | $394 | $172,087 | $172,087 | $402 | $175,528 | $175,528 | $171,028 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0.2 | 0.3 | 0 | 0 | 0.5 | NA | 40 | 40 | NA | 40 | 40 | NA | 40 | 40 | 40 | NA | NA | |
Cost | 0 | 0 | 5 | 8 | 0 | 0 | $13 | $28 | $2,225 | $2,225 | $29 | $2,314 | $2,314 | $30 | $2,360 | $2,360 | $2,300 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 0 | 5 | 5 | 5 | 15 | NA | 1200 | 240 | NA | 1200 | 240 | NA | 1200 | 240 | 240 | NA | NA | |
Cost per RO | 0 | 0 | 0 | 138 | 157 | 189 | $484 | $1,035 | $82,831 | $16,566 | $1,077 | $86,145 | $17,229 | $1,098 | $87,867 | $17,573 | $17,123 | NA | NA | |
Sub Total - Hours | 0 | 25 | 25 | 48 | 47 | 5 | 151 | NA | NA | 59,275 | NA | NA | 59,275 | NA | NA | 59,275 | 59,275 | |||
Sub Total - Costs | $0 | $605 | $635 | $1,331 | $1,472 | $189 | $4,232 | $9,053 | NA | $3,510,446 | $9,415 | NA | $3,650,864 | $9,604 | NA | $3,723,881 | $3,628,397 | |||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 8 | 4 | 12 | NA | 5,244 | 5,244 | NA | 5,244 | 5244 | NA | 5,244 | 5,244 | 5,244 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 250 | 151 | $401 | $858 | $374,874 | $374,874 | $892 | $389,869 | $389,869 | $910 | $397,666 | $397,666 | $387,470 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 16 | 8 | 4 | 2 | 30 | NA | 13,110 | 13,110 | NA | 13,110 | 13,110 | NA | 13,110 | 13,110 | 13,110 | NA | NA | |
Cost per site | 0 | 0 | 404 | 221 | 125 | 76 | $826 | $1,767 | $772,184 | $772,184 | $1,838 | $803,071 | $803,071 | $1,874 | $819,133 | $819,133 | $798,129 | NA | NA | |
Sub Total - Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 18354 | 18354 | NA | 18354 | 18354 | NA | 18354 | 18,354 | 18,354 | NA | NA | |
Sub Total - Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $1,147,058 | $1,147,058 | $2,730 | $1,192,940 | $1,192,940 | $2,784 | $1,216,799 | $1,216,799 | $1,185,599 | NA | NA | |
Summary by Element | NO2 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 3,040 | 434 | NA | 3,040 | 434 | NA | 3,040 | 434 | 434 | |||
Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $205,709 | $29,387 | $2,674 | $213,938 | $30,563 | $2,728 | $218,216 | $31,174 | $30,374 | NA | NA | |
2 - Site Installation Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 8,827 | 1,261 | NA | 8,827 | 1,261 | NA | 8,827 | 1,261 | 1,261 | |||
Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $0 | $995,471 | $1,126 | $0 | $1,035,290 | $1,148 | $0 | $1,055,996 | $70,606 | NA | $958,313 | |
3 - Supplies & site visits Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 52440 | 52440 | NA | 52440 | 52440 | NA | 52440 | 52440 | 52,440 | NA | NA | |
Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $3,194,460 | $3,194,460 | $7,602 | $3,322,238 | $3,322,238 | $7,754 | $3,388,683 | $3,388,683 | $3,301,793 | $436,838 | NA | |
4 - Maintenance Hours | 0 | 0 | 38 | 48 | 0 | 0 | 86 | NA | 37582 | 37582 | NA | 37582 | 37582 | NA | 37582 | 37582 | 37,582 | |||
Costs | $0 | $0 | $959 | $1,324 | $0 | $0 | $3,283 | $6,093 | $2,662,553 | $2,662,553 | $6,337 | $2,769,055 | $2,769,055 | $6,463 | $2,824,436 | $2,824,436 | $2,205,967 | $546,047 | NA | |
5 - Data Managment Hours | 0 | 0.25 | 18 | 25 | 7 | 0 | 50.25 | NA | 21959.25 | 21959.25 | NA | 21959.25 | 21959.25 | NA | 21959.25 | 21959.25 | 21,959 | NA | NA | |
Costs | $0 | $6 | $454 | $690 | $219 | $0 | $1,369 | $2,929 | $1,279,812 | $1,279,806 | $3,046 | $1,330,998 | $1,330,998 | $3,113 | $1,357,631 | $1,363,227 | $1,324,677 | NA | NA | |
6 - Quality Assurance Hours | 0 | 25 | 25 | 48 | 47 | 5 | 151 | NA | NA | 59275 | NA | NA | 59275 | NA | NA | 59275 | 59,275 | NA | NA | |
Costs | $0 | $605 | $635 | $1,331 | $1,472 | $189 | $4,232 | $9,053 | NA | $3,510,446 | $9,415 | NA | $3,650,864 | $9,604 | NA | $3,723,881 | $3,628,397 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 18354 | 18354 | NA | 18354 | 18354 | NA | 18354 | 18354 | 18,354 | NA | NA | |
Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $1,147,058 | $1,147,058 | $2,730 | $1,192,940 | $1,192,940 | $2,784 | $1,216,799 | $1,216,799 | $1,185,599 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 93 | 165 | 147 | 80 | 21 | 507 | NA | 142,203 | 191,306 | NA | 142,203 | 191,306 | NA | 142,203 | 191,306 | 191,306 | NA | ||
Costs | $0 | $865 | $2,714 | $4,062 | $2,504 | $794 | $15,584 | $31,663 | 8,489,592 | $12,819,180 | $32,930 | 8,829,169 | $13,331,948 | $33,594 | 9,005,765 | $13,604,196 | $11,747,414 | $982,885 | $958,313 |
Data Entry for | O3 | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | Sites | Report Org | Sites | Report Org | Sites | Sites | |||||||||||||
20.00% | 103 | 4 month | 9 | 103 | 4 month | 9 | 103 | 4 month | 9 | 4 month | 9 | |||||||||
Overall Comment | 5 month | 71 | 5 month | 71 | 5 month | 71 | 5 month | 71 | ||||||||||||
6 month | 109 | 6 month | 109 | 6 month | 109 | 6 month | 109 | |||||||||||||
7 month | 352 | 7 month | 352 | 7 month | 352 | 7 month | 352 | |||||||||||||
8 month | 165 | 8 month | 165 | 8 month | 165 | 8 month | 165 | |||||||||||||
9 month | 33 | 9 month | 33 | 9 month | 33 | 9 month | 33 | |||||||||||||
12 month | 372 | 12 month | 372 | 12 month | 372 | 12 month | 372 | |||||||||||||
Total Sites | 1111 | Total Sites | 1111 | Total Sites | 1111 | Total Sites | 1111 | |||||||||||||
Avg Percent Sampled | 71.9% | Avg Percent Sampled | 71.9% | Avg Percent Sampled | 71.9% | |||||||||||||||
Spares | 222 | Spares | 222 | Spares | 222 | Report Org | 103 | |||||||||||||
General Costs | Labor | Non Labor O & M | ||||||||||||||||||
Element 1 - Network design | Years Amoritized | 7 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 10 | 10 | 10 | 30 | NA | 3090 | 441 | NA | 3,090 | 441 | NA | 3,090 | 441 | 441 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 276 | 313 | 378 | $967 | $2,069 | $213,070 | $30,439 | $2,151 | $221,593 | $31,656 | $2,194 | $226,025 | $32,289 | $31,461 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 0 | 0 | 4 | 4 | 0 | 8 | NA | 824 | 118 | NA | 824 | 118 | NA | 824 | 118 | 118 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 110 | 125 | 0 | $235 | $503 | $51,780 | $7,397 | $523 | $53,851 | $7,693 | $533 | $54,929 | $7,847 | $7,646 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 3,914 | 559 | NA | 3914 | 559 | NA | 3,914 | 559 | 559 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $264,851 | $37,836 | $2,674 | $275,445 | $39,349 | $2,728 | $280,954 | $40,136 | $39,107 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 7 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $11,000 | 2019 | $13,298 | $14,774,171 | $2,110,596 | $13,830 | $15,365,138 | $2,195,020 | $14,107 | $15,672,441 | $2,238,920 | NA | NA | $2,181,512 | ||||||
Spare Analyzers | $2,954,834 | $422,119 | $3,073,028 | $439,004 | $3,134,488 | $447,784 | NA | NA | $436,302 | |||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 4 | 0 | 0 | 4 | NA | 5,333 | 762 | NA | 5,333 | 762 | NA | 5,333 | 762 | 762 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 0 | 0 | $110 | $235 | $313,724 | $44,818 | $245 | $271,894 | $38,842 | $250 | $277,332 | $39,619 | $41,093 | NA | NA | |
Installation Hours per site | 0 | 8 | 8 | 0 | 0 | 0 | 16 | NA | 17776 | 2539 | NA | 17,776 | 2539 | NA | 17,776 | 2539 | 2,539 | NA | NA | |
Cost per site | 0 | 194 | 202 | 0 | 0 | 0 | $396 | $847 | $941,171 | $134,453 | $881 | $978,818 | $139,831 | $899 | $998,394 | $142,628 | $138,971 | NA | NA | |
Sub Total - Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 23,109 | 3,301 | NA | 23,109 | 3,301 | NA | 23,109 | 3,301 | 3,301 | NA | NA | |
Sub Total - Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $2,711,986 | $1,126 | $2,812,697 | $1,148 | $2,868,951 | $180,063 | NA | $2,617,814 | ||||
Element 3 - Supplies and Site Visits (1) | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$800 | 2019 | $967 | $1,074,485 | $1,074,485 | $1,006 | $1,117,465 | $1,117,465 | $1,026 | $1,139,814 | $1,139,814 | NA | $1,110,588 | NA | |||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | ||||||||||||||
Routine visits Hours per site | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 95,900 | 95,900 | NA | 95,900 | 95,900 | NA | 95,900 | 95,900 | 95,900 | NA | NA | |
Cost per site | 0 | 1452 | 1513 | 0 | 0 | 0 | $2,965 | $6,343 | $7,046,898 | $7,046,898 | $6,597 | $7,328,774 | $7,328,774 | $6,728 | $7,475,350 | $7,475,350 | $7,283,674 | NA | NA | |
Sub Total - Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 95,900 | 95,900 | NA | 95,900 | 95,900 | NA | 95,900 | 95,900 | 95,900 | NA | NA | |
Sub Total - Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $8,121,384 | $8,121,384 | $7,602 | $8,446,239 | $8,446,239 | $7,754 | $8,615,164 | $8,615,164 | $7,283,674 | $1,110,588 | NA | |
Element 4 - Maintenance (1) | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$1,000 | 2019 | $1,209 | $1,343,106 | $1,343,106 | $1,257 | $1,396,831 | $1,396,831 | $1,282 | $1,424,767 | $1,424,767 | NA | $1,388,235 | NA | |||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | ||||||||||||||
Remedial Repairs Hours per site | 0 | 6 | 3 | 3 | 0 | 0 | 12 | NA | 9,590 | 9,590 | NA | 9,590 | 9,590 | NA | 9,590 | 9,590 | 9,590 | NA | NA | |
Cost per site | 0 | 145 | 76 | 83 | 0 | 0 | $304 | $650 | $722,515 | $722,515 | $676 | $751,416 | $751,416 | $690 | $766,444 | $766,444 | $746,792 | NA | NA | |
Routine Maintenance Hours per site | 0 | 16 | 8 | 32 | 0 | 0 | 56 | NA | 44,753 | 44,753 | NA | 44,753 | 44,753 | NA | 44,753 | 44,753 | 44,753 | NA | NA | |
Cost per site | 0 | 387 | 202 | 882 | 0 | 0 | $1,471 | $3,147 | $3,496,117 | $3,496,117 | $3,273 | $3,635,962 | $3,635,962 | $3,338 | $3,708,681 | $3,708,681 | $3,613,587 | NA | NA | |
Sub Total - Hours | 0 | 22 | 11 | 35 | 0 | 0 | 68 | NA | 54,343 | 54,343 | NA | 54,343 | 54,343 | NA | 54,343 | 54,343 | 54,343 | NA | NA | |
Sub Total - Costs | $0 | $532 | $278 | $965 | $0 | $0 | $2,775 | $5,006 | $5,561,739 | $5,561,739 | $5,206 | $5,784,208 | $5,784,208 | $5,310 | $5,899,892 | $5,899,892 | $4,360,378 | $1,388,235 | NA | |
Element 5 - Data Management (1) | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 6 | 3 | 3 | 2 | 0 | 14 | NA | 11,188 | 11,188 | NA | 11,188 | 11,188 | NA | 11,188 | 11,188 | 11,188 | NA | NA | |
Cost per site | 0 | 145 | 76 | 83 | 63 | 0 | $367 | $785 | $872,247 | $872,247 | $817 | $907,137 | $907,137 | $833 | $925,279 | $925,279 | $901,554 | NA | NA | |
Data reporting Hours per site | 0 | 1 | 2 | 4 | 2 | 0 | 9 | NA | 7,193 | 7,193 | NA | 7,193 | 7,193 | NA | 7,193 | 7,193 | 7,193 | NA | NA | |
Cost per site | 0 | 24 | 50 | 110 | 63 | 0 | $247 | $528 | $587,043 | $587,043 | $550 | $610,525 | $610,525 | $561 | $622,736 | $622,736 | $606,768 | NA | NA | |
Data validation Hours per site | 0 | 0 | 4 | 8 | 0 | 0 | 12 | NA | 9,590 | 9,590 | NA | 9,590 | 9,590 | NA | 9,590 | 9,590 | 9,590 | NA | NA | |
Cost per site | 0 | 0 | 101 | 221 | 0 | 0 | $322 | $689 | $765,296 | $765,296 | $716 | $795,907 | $795,907 | $731 | $811,826 | $811,826 | $791,009 | NA | NA | |
Data distribution Hours per site | 0 | 1 | 1 | 2 | 0 | 0 | 4 | NA | 3,197 | 3,197 | NA | 3,197 | 3,197 | NA | 3,197 | 3,197 | 3,197 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 0 | 0 | $104 | $222 | $247,176 | $247,176 | $231 | $257,063 | $257,063 | $236 | $262,205 | $262,205 | $255,481 | NA | NA | |
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | NA | 278 | 278 | NA | 278 | 278 | NA | 278 | 278 | 278 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $14,260 | $14,260 | $13 | $14,831 | $14,831 | $14 | $15,127 | $15,127 | $14,739 | NA | NA | |
Sub Total - Hours | 0 | 8 | 10 | 17 | 4 | 0 | 39 | NA | 31,445 | 31,445 | NA | 31,445 | 31,445 | NA | 31,445 | 31,445 | 31,445 | NA | NA | |
Sub Total - Costs | $0 | $193 | $252 | $469 | $126 | $0 | $1,040 | $2,238 | $2,486,022 | $2,486,022 | $2,327 | $2,585,463 | $2,585,463 | $2,374 | $2,637,172 | $2,637,172 | $2,569,553 | NA | NA | |
Element 6 - Quality Assurance (1) | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 20 | 16 | 0 | 36 | NA | 28,770 | 28,770 | NA | 28,770 | 28,770 | NA | 28,770 | 28,770 | 28,770 | NA | NA | |
Cost per site | 0 | 0 | 0 | 551 | 501 | 0 | $1,052 | $2,250 | $2,500,282 | $2,500,282 | $2,340 | $2,600,294 | $2,600,294 | $2,387 | $2,652,300 | $2,652,300 | $2,584,292 | NA | NA | |
Routine Calibrations Hours per site | 0 | 26 | 0 | 0 | 0 | 0 | 26 | NA | 20,778 | 20,778 | NA | 20,778 | 20,778 | NA | 20,778 | 20,778 | 20,778 | NA | NA | |
Cost per site | 0 | 629 | 0 | 0 | 0 | 0 | $629 | $1,346 | $1,494,941 | $1,494,941 | $1,399 | $1,554,738 | $1,554,738 | $1,427 | $1,585,833 | $1,585,833 | $1,545,171 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 2 | 2 | 0 | 4 | NA | 3,197 | 3,197 | NA | 3,197 | 3,197 | NA | 3,197 | 3,197 | 3,197 | NA | NA | |
Cost per site | 0 | 0 | 0 | 55 | 63 | 0 | $118 | $252 | $280,450 | $280,450 | $263 | $291,668 | $291,668 | $268 | $297,501 | $297,501 | $289,873 | NA | NA | |
Training Hours per site | 0 | 1 | 1 | 2 | 1 | 0 | 5 | NA | 5,555 | 5,555 | NA | 5,555 | 5,555 | NA | 5,555 | 5,555 | 5,555 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 31 | 0 | $135 | $289 | $320,854 | $320,854 | $300 | $333,688 | $333,688 | $306 | $340,362 | $340,362 | $331,634 | NA | NA | |
Reporting Hours per site | 0 | 0 | 0 | 3 | 2 | 0 | 5 | NA | 3,996 | 3,996 | NA | 3,996 | 3,996 | NA | 3,996 | 3,996 | 3,996 | NA | NA | |
Cost per site | 0 | 0 | 0 | 83 | 63 | 0 | $146 | $312 | $346,997 | $346,997 | $325 | $360,877 | $360,877 | $331 | $368,095 | $368,095 | $358,656 | NA | NA | |
Per RO | ||||||||||||||||||||
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor | |||||||||||||
Hours per reporting organization | 0 | 0 | 0.2 | 0.3 | 0 | 0 | 0.5 | NA | 52 | 52 | NA | 52 | 52 | NA | 52 | 52 | 52 | NA | NA | |
Cost per reporting organization | 0 | 0 | 5 | 8 | 0 | 0 | $13 | $28 | $2,864 | $2,864 | $29 | $2,979 | $2,979 | $30 | $3,039 | $3,039 | $2,961 | NA | NA | |
Years Amoritized | 5 | Per RO | ||||||||||||||||||
QA Plan preparation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor | |||||||||||||
Hours per reporting organization | 0 | 0 | 0 | 5 | 5 | 5 | 15 | NA | 1545 | 309 | NA | 1545 | 309 | NA | 1545 | 309 | 309 | NA | NA | |
Cost per reporting organization | 0 | 0 | 0 | 138 | 157 | 189 | $484 | $1,035 | $106,645 | $21,329 | $1,077 | $110,911 | $110,911 | $1,098 | $113,129 | $113,129 | $81,790 | NA | NA | |
Sub Total - Hours | 0 | 27 | 1 | 32 | 26 | 5 | 92 | NA | NA | 62,656 | NA | NA | 62,656 | NA | NA | 62,656 | 62,656 | |||
Sub Total - Costs | $0 | $653 | $30 | $890 | $815 | $189 | $2,577 | $5,513 | $5,053,034 | $4,967,718 | $5,733 | $5,255,155 | $5,255,155 | $5,848 | $5,360,258 | $5,360,258 | $5,194,377 | |||
Element 7 - Supervision (1) | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Planning/coordination Hours per site | 0 | 0 | 0 | 0 | 8 | 4 | 12 | NA | 9,590 | 9,590 | NA | 9,590 | 9,590 | NA | 9,590 | 9,590 | 9,590 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 250 | 151 | $401 | $858 | $953,054 | $953,054 | $892 | $991,177 | $991,177 | $910 | $1,011,000 | $1,011,000 | $985,077 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 16 | 8 | 4 | 2 | 30 | NA | 23,975 | 23,975 | NA | 23,975 | 23,975 | NA | 23,975 | 23,975 | 23,975 | NA | NA | |
Cost per site | 0 | 0 | 404 | 221 | 125 | 76 | $826 | $1,767 | $1,963,149 | $1,963,149 | $1,838 | $2,041,675 | $2,041,675 | $1,874 | $2,082,509 | $2,082,509 | $2,029,111 | NA | NA | |
Sub Total - Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 33,565 | 33,565 | NA | 33,565 | 33,565 | NA | 33,565 | 33565 | 33,565 | NA | NA | |
Sub Total - Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $2,916,204 | $2,916,204 | $2,730 | $3,032,852 | $3,032,852 | $2,784 | $3,093,509 | $3,093,509 | $3,014,188 | NA | NA | |
Summary by Element | O3 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 14 | 14 | 10 | 38 | NA | 3,914 | 559 | NA | 3,914 | 559 | NA | 3,914 | 559 | 559 | |||
Costs | $0 | $0 | $0 | $386 | $438 | $378 | $1,202 | $2,571 | $264,851 | $37,836 | $2,674 | $275,445 | $39,349 | $2,728 | $280,954 | $40,136 | $39,107 | NA | NA | |
2 - Site Installation Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 23,109 | 3,301 | NA | 23,109 | 3,301 | NA | 23,109 | 3,301 | 3,301 | |||
Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $0 | $2,711,986 | $1,126 | $0 | $2,812,697 | $1,148 | $0 | $2,868,951 | $180,063 | NA | $2,617,814 | |
3 - Supplies and Site Visits Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 95900 | 95900 | NA | 95900 | 95900 | NA | 95900 | 95900 | 95900 | NA | NA | |
Costs | $0 | $60 | $60 | $0 | $0 | $0 | $3,765 | $7,310 | $8,121,384 | $8,121,384 | $7,602 | $8,446,239 | $8,446,239 | $7,754 | $8,615,164 | $8,615,164 | $7,283,674 | $1,110,588 | NA | |
4 - Maintenance Hours | 0 | 22 | 11 | 35 | 0 | 0 | 68 | NA | 54343.3333333333 | 54343.3333333333 | NA | 54343.3333333333 | 54343.3333333333 | NA | 54343.3333333333 | 54343.3333333333 | 54343.3333333333 | |||
Costs | $0 | $532 | $278 | $965 | $0 | $0 | $2,775 | $5,006 | $5,561,739 | $5,561,739 | $5,206 | $5,784,208 | $5,784,208 | $5,310 | $5,899,892 | $5,899,892 | $4,360,378 | $1,388,235 | NA | |
5 - Data Management Hours | 0 | 8 | 10 | 17 | 4 | 0 | 39 | NA | 31445.25 | 31445.25 | NA | 31445.25 | 31445.25 | NA | 31445.25 | 31445.25 | 31445.25 | NA | NA | |
Costs | $0 | $193 | $252 | $469 | $126 | $0 | $1,040 | $2,238 | $2,486,022 | $2,486,022 | $2,327 | $2,585,463 | $2,585,463 | $2,374 | $2,637,172 | $2,637,172 | $2,569,553 | NA | NA | |
6 - Quality Assurance Hours | 0 | 27 | 1 | 32 | 26 | 5 | 92 | NA | NA | 62656 | NA | NA | 62656 | NA | NA | 62656 | 62656 | NA | NA | |
Costs | $0 | $653 | $30 | $890 | $815 | $189 | $2,577 | $5,513 | $5,053,034 | $4,967,718 | $5,733 | $5,255,155 | $5,255,155 | $5,848 | $5,360,258 | $5,360,258 | $5,194,377 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 33565 | 33565 | NA | 33565 | 33565 | NA | 33565 | 33565 | 33565 | NA | NA | |
Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $2,916,204 | $2,916,204 | $2,730 | $3,032,852 | $3,032,852 | $2,784 | $3,093,509 | $3,093,509 | $3,014,188 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 125 | 106 | 110 | 56 | 21 | 419 | NA | 242,276 | 281,770 | NA | 242,276 | 281,770 | NA | 242,276 | 281,770 | 281,770 | NA | ||
Costs | $0 | $1,632 | $1,226 | $3,041 | $1,754 | $794 | $13,092 | $26,345 | 19,350,199 | $26,802,887 | $27,399 | 20,124,207 | $27,955,963 | $27,947 | 20,526,691 | $28,515,083 | $22,641,341 | $2,498,823 | $2,617,814 | |
1) Per site operating costs are weighted by the average percent sampling. For example, the operating expenses for a site operated for 6 months per year are assummed to be half that of a site operated for 12 months per year. |
Data Entry for | PM10 | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Analyzer Spare Factor | Filter-Based | 1/1 (daily) | 39 | Filter-Based | 1/1 (daily) | 39 | Filter-Based | 1/1 (daily) | 39 | |||||||||||
3.50% | Sites | 1/2 | 0 | Sites | 1/2 | 0 | Sites | 1/2 | 0 | |||||||||||
Overall Comment | 1/3 | 30 | 1/3 | 30 | 1/3 | 30 | ||||||||||||||
Report Org | 1/6 | 126 | Report Org | 1/6 | 126 | Report Org | 1/6 | 126 | ||||||||||||
113 | collocated | 20 | 113 | collocated | 20 | 113 | collocated | 20 | ||||||||||||
Total | 215 | Total | 215 | Total | 215 | Total | 215 | |||||||||||||
Samplers | 362 | Samplers | 362 | Samplers | 362 | Samplers | 362 | |||||||||||||
Spares | 13 | Spares | 13 | Spares | 13 | Spares | 13 | |||||||||||||
Avg Percent Sampled | 33% | Avg Percent Sampled | 33% | Avg Percent Sampled | 33% | |||||||||||||||
Continuous Sites | 465 | Continuous Sites | 465 | Continuous Sites | 465 | Cont Samplers | 465 | |||||||||||||
Spares | 16 | Spares | 16 | Spares | 16 | Spares | 16 | |||||||||||||
Platforms | 680 | Platforms | 680 | Platforms | 680 | Platforms | 680 | |||||||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 7 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 10 | 10 | 10 | 30 | NA | 3,390 | 484 | NA | 3,390 | 484 | NA | 0 | 0 | 323 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 276 | 313 | 378 | $967 | $2,069 | $233,757 | $33,394 | $2,151 | $243,107 | $34,730 | $2,194 | $247,969 | $35,424 | $34,516 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 6 | 2 | 2 | 0 | 0 | 10 | NA | 1,130 | 161 | NA | 1,130 | 161 | NA | 1,130 | 161 | 161 | NA | NA | |
Costs per RO | 0 | 145 | 50 | 55 | 0 | 0 | $250 | $535 | $60,433 | $8,633 | $556 | $62,851 | $8,979 | $567 | $64,108 | $9,158 | $8,923 | NA | NA | |
Sub Total - Hours | 0 | 6 | 2 | 12 | 10 | 10 | 40 | NA | 4,520 | 646 | NA | 4,520 | 646 | NA | 1,130 | 161 | 484 | NA | NA | |
Sub Total - Costs | $0 | $145 | $50 | $331 | $313 | $378 | $1,217 | $2,603 | $294,190 | $42,027 | $2,708 | $305,958 | $43,708 | $2,762 | $312,077 | $44,582 | $43,439 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 7 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $5,500 | 2019 | $6,649 | $1,429,544 | $204,221 | $6,915 | $1,486,726 | $212,389 | $7,053 | $1,516,460 | $216,637 | NA | NA | $211,082 | ||||||
Spare Analyzers | $84,243 | $12,035 | $87,613 | $12,516 | $89,365 | $12,766 | NA | NA | $12,439 | |||||||||||
Continuous Analyzers | $17,600 | 2019 | $21,277 | $9,893,774 | $1,413,396 | $22,128 | $10,289,525 | $1,469,932 | $22,571 | $10,495,316 | $1,499,331 | NA | NA | $1,460,886 | ||||||
Continuous Spare Analyzers | $346,282 | $49,469 | $360,133 | $51,448 | $367,336 | $52,477 | NA | NA | $51,131 | |||||||||||
Sampling Platform | $2,000 | 2019 | $2,418 | $1,644,127 | $234,875 | $2,515 | $1,644,127 | $234,875 | $2,565 | $1,644,127 | $234,875 | NA | NA | $234,875 | ||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 4 | 0 | 0 | 0 | 4 | NA | 2,836 | 405 | NA | 2,836 | 405 | NA | 2,836 | 405 | 405 | NA | NA | |
Cost per site | 0 | 0 | 101 | 0 | 0 | 0 | $101 | $216 | $153,177 | $21,882 | $225 | $159,304 | $22,758 | $229 | $162,490 | $23,213 | $22,618 | NA | NA | |
Installation | ||||||||||||||||||||
a) Sampler Hours per site | 0 | 4 | 0 | 0 | 0 | 0 | 4 | NA | 860 | 123 | NA | 860 | 123 | NA | 860 | 123 | 123 | NA | NA | |
Cost per site | 0 | 97 | 0 | 0 | 0 | 0 | $97 | $208 | $44,614 | $6,373 | $216 | $46,398 | $6,628 | $220 | $47,326 | $6,761 | $6,588 | NA | NA | |
b) Cont Sampler Hours per site | 0 | 0 | 0 | 10 | 0 | 0 | 10 | NA | 4650 | 664 | NA | 4650 | 664 | NA | 4650 | 664 | 664 | NA | NA | |
Cost per site | 0 | 0 | 0 | 276 | 0 | 0 | $276 | $590 | $274,550 | $39,221 | $614 | $285,532 | $40,790 | $626 | $291,243 | $41,606 | $40,539 | NA | NA | |
Sub Total - Hours | 0 | 4 | 4 | 0 | 0 | 0 | 8 | NA | 3,696 | 1,192 | NA | 3,696 | 1,192 | NA | 3,696 | 1,192 | 1,192 | NA | NA | |
Sub Total - Costs | $0 | $97 | $101 | $0 | $0 | $0 | $198 | $31,358 | $13,439,786 | $1,981,473 | $32,612 | $13,911,612 | $2,051,337 | $33,264 | $14,156,962 | $2,087,666 | $69,744 | NA | $1,970,414 | |
Element 3 - Sampling and Analysis | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
Filters | $1,033 | 2019 | $1,249 | $452,157 | $452,157 | $1,299 | $470,243 | $470,243 | $1,325 | $479,648 | $479,648 | NA | $467,350 | NA | ||||||
Filter Tape | $500 | 2019 | $604 | $281,073 | $281,073 | $629 | $292,316 | $292,316 | $641 | $298,162 | $298,162 | NA | $290,517 | NA | ||||||
Laboratory Service | $86 | 2019 | $104 | $37,511 | $37,511 | $108 | $39,011 | $39,011 | $110 | $39,792 | $39,792 | NA | NA | $38,771 | ||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
1/1 and 1/2 sites Hours per site | 0 | 45 | 50 | 25 | 0 | 0 | 120 | NA | 4,680 | 4,680 | NA | 4,680 | 4,680 | NA | 4,680 | 4,680 | 4,680 | NA | NA | |
Cost per site | 0 | 1089 | 1261 | 689 | 0 | 0 | $3,039 | $6,501 | $253,545 | $253,545 | $6,761 | $263,687 | $263,687 | $6,896 | $268,960 | $268,960 | $262,064 | NA | NA | |
1/3 and 1/6 sites Hours per site | 0 | 15 | 65 | 100 | 0 | 0 | 180 | NA | 31,680 | 31,680 | NA | 31,680 | 31,680 | NA | 31,680 | 31,680 | 31,680 | NA | NA | |
Cost per site | 0 | 363 | 1639 | 2757 | 0 | 0 | $4,759 | $10,181 | $1,791,792 | $1,791,792 | $10,588 | $1,863,464 | $1,863,464 | $10,800 | $1,900,733 | $1,900,733 | $1,851,996 | NA | NA | |
Continuous sites Hours per site | 0 | 0 | 30 | 2 | 0 | 0 | 32 | NA | 14,880 | 14,880 | NA | 6,880 | 6,880 | NA | 6,880 | 6,880 | 9,547 | NA | NA | |
Cost per site | 0 | 0 | 757 | 55 | 0 | 0 | $812 | $1,737 | $807,734 | $807,734 | $1,807 | $388,407 | $388,407 | $1,843 | $396,175 | $396,175 | $530,772 | NA | NA | |
Laboratory Hours per site | 0 | 24 | 24 | 0 | 0 | 0 | 48 | 15.6 | 5,657 | 5,657 | 15.6 | 5,657 | 5,657 | 15.6 | 5,657 | 5,657 | 5,657 | NA | NA | |
Cost per site | 0 | 581 | 605 | 0 | 0 | 0 | $1,186 | $2,537 | $918,444 | $918,444 | $2,639 | $955,181 | $955,181 | $2,691 | $974,285 | $974,285 | $949,303 | NA | NA | |
Sub Total - Hours | 0 | 84 | 169 | 127 | 0 | 0 | 380 | NA | 56,897 | 56,897 | NA | 48,897 | 48,897 | NA | 48,897 | 48,897 | 9,547 | NA | NA | |
Sub Total - Costs | $0 | $2,033 | $4,262 | $3,501 | $0 | $0 | $9,796 | $20,956 | $3,771,514 | $3,771,514 | $21,794 | $3,470,739 | $3,470,739 | $22,230 | $3,540,154 | $3,540,154 | $3,594,136 | $757,867 | $38,771 | |
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
Filter Based | $950 | 2019 | $1,148 | $246,921 | $246,921 | $1,194 | $256,798 | $256,798 | $1,218 | $261,934 | $261,934 | NA | $255,218 | NA | ||||||
Spare Parts - Continuous | $555 | 2019 | $671 | $311,991 | $311,991 | $698 | $324,471 | $324,471 | $712 | $330,960 | $330,960 | NA | $322,474 | NA | ||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Filter Hours per site | 0 | 85 | 0 | 0 | 0 | 0 | 85 | 28 | 5,950 | 5,950 | 28 | 5,950 | 5,950 | 28 | 5,950 | 5,950 | 5,950 | NA | NA | |
Cost per site | $0 | $2,057 | $0 | $0 | $0 | $0 | $2,057 | $4,400 | $946,089 | $946,089 | $4,576 | $983,933 | $983,933 | $4,668 | $1,003,611 | $1,003,611 | $977,878 | NA | NA | |
Continuous Hours per site | 0 | 0 | 6 | 1 | 0.5 | 0 | 8 | 7.5 | 3,488 | 3,488 | 7.5 | 3,488 | 3,488 | 7.5 | 3,488 | 3,488 | 3,488 | NA | NA | |
Cost per site | $0 | $0 | $151 | $28 | $16 | $0 | $195 | $417 | $193,975 | $193,975 | $434 | $201,734 | $201,734 | $443 | $205,769 | $205,769 | $200,493 | NA | NA | |
Routine Maint. Filter Hours per site | 0 | 0 | 50 | 25 | 0 | 0 | 75 | 24 | 5,250 | 5,250 | 24 | 5,250 | 5,250 | 24 | 5,250 | 5,250 | 5,250 | NA | NA | |
Cost per site | $0 | $0 | $1,261 | $689 | $0 | $0 | $1,950 | $4,172 | $896,876 | $896,876 | $4,338 | $932,751 | $932,751 | $4,425 | $951,406 | $951,406 | $927,011 | NA | NA | |
Continuous Hours per site | 0 | 5 | 5 | 4 | 0 | 0 | 14 | 14 | 6,510 | 6,510 | 14 | 6,510 | 6,510 | 14 | 6,510 | 6,510 | 6,510 | NA | NA | |
Cost per site | $0 | $121 | $126 | $110 | $0 | $0 | $357 | $764 | $355,124 | $355,124 | $794 | $369,329 | $369,329 | $810 | $376,716 | $376,716 | $367,057 | NA | NA | |
Sub Total - Hours | 0 | 85 | 50 | 25 | 0 | 0 | 160 | NA | 11,200 | 11,200 | NA | 11,200 | 11,200 | NA | 11,200 | 11,200 | 11,200 | NA | NA | |
Sub Total - Costs | $0 | $2,057 | $1,261 | $689 | $0 | $0 | $4,957 | $9,720 | $2,089,886 | $2,089,886 | $10,109 | $2,173,482 | $2,173,482 | $10,311 | $2,216,951 | $2,216,951 | $1,904,889 | $577,692 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Filter - based Hours per site | 0 | 0 | 96 | 0 | 0 | 0 | 96 | 31 | 11,315 | 11,315 | 31 | 20,640 | 20,640 | 31 | 20,640 | 20,640 | 17,532 | NA | NA | |
Cost per site | $0 | $0 | $2,421 | $0 | $0 | $0 | $2,421 | $5,179 | $1,874,833 | $1,874,833 | $5,386 | $1,158,046 | $1,158,046 | $5,494 | $1,181,207 | $1,181,207 | $1,404,695 | NA | NA | |
Continuous Hours per site | 0 | 0 | 6 | 6 | 0 | 0 | 12 | 12 | 5,580 | 5,580 | 12 | 5,580 | 5,580 | 12 | 5,580 | 5,580 | 5,580 | NA | NA | |
Cost per site | $0 | $0 | $151 | $165 | $0 | $0 | $316 | $676 | $314,340 | $314,340 | $703 | $326,913 | $326,913 | $717 | $333,452 | $333,452 | $324,902 | NA | NA | |
Data reporting Filter Hours per site | 0 | 0 | 0 | 38 | 0 | 0 | 38 | 12 | 2,660 | 2,660 | 12 | 2,660 | 2,660 | 12 | 2,660 | 2,660 | 2,660 | NA | NA | |
Cost per site | $0 | $0 | $0 | $1,048 | $0 | $0 | $1,048 | $2,242 | $482,013 | $482,013 | $2,332 | $501,294 | $501,294 | $2,378 | $511,320 | $511,320 | $498,209 | NA | NA | |
Continuous Hours per site | 0 | 0 | 6 | 12 | 0 | 0 | 18 | 18 | 8,370 | 8,370 | 18 | 8,370 | 8,370 | 18 | 8,370 | 8,370 | 8,370 | NA | NA | |
Cost per site | $0 | $0 | $151 | $331 | $0 | $0 | $482 | $1,031 | $479,468 | $479,468 | $1,072 | $498,646 | $498,646 | $1,094 | $508,619 | $508,619 | $495,578 | NA | NA | |
Data validation Filter Hours per site | 0 | 0 | 24 | 72 | 48 | 0 | 144 | 47 | 10,080 | 10,080 | 47 | 10,080 | 10,080 | 47 | 10,080 | 10,080 | 10,080 | NA | NA | |
Cost per site | $0 | $0 | $605 | $1,985 | $1,503 | $0 | $4,093 | $8,756 | $1,882,519 | $1,882,519 | $9,106 | $1,957,820 | $1,957,820 | $9,288 | $1,996,977 | $1,996,977 | $1,945,772 | NA | NA | |
Continuous Hours per site | 0 | 0 | 6 | 14 | 0 | 0 | 20 | 20 | 9,300 | 9,300 | 20 | 9,300 | 9,300 | 20 | 9,300 | 9,300 | 9,300 | NA | NA | |
Cost per site | $0 | $0 | $151 | $386 | $0 | $0 | $537 | $1,149 | $534,179 | $534,179 | $1,195 | $555,546 | $555,546 | $1,219 | $566,657 | $566,657 | $552,127 | NA | NA | |
Data distribution Hours per site | 0 | 0 | 6 | 7 | 0 | 0 | 13 | 13 | 2,795 | 2,795 | 13 | 2,795 | 2,795 | 13 | 2,795 | 2,795 | 2,795 | NA | NA | |
Cost per site | $0 | $0 | $151 | $193 | $0 | $0 | $344 | $736 | $158,218 | $158,218 | $765 | $164,547 | $164,547 | $781 | $167,838 | $167,838 | $163,534 | NA | NA | |
Continuous Hours per site | 0 | 0 | 2 | 2 | 2 | 0 | 6 | 6 | 2,790 | 2,790 | 6 | 2,790 | 2,790 | 6 | 2,790 | 2,790 | 2,790 | NA | NA | |
Cost per site | $0 | $0 | $50 | $55 | $63 | $0 | $168 | $359 | $167,117 | $167,117 | $374 | $173,802 | $173,802 | $381 | $177,278 | $177,278 | $172,732 | NA | NA | |
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | 0.25 | 54 | 54 | 0.25 | 54 | 54 | 0.25 | 54 | 54 | 54 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $2,760 | $2,760 | $13 | $2,870 | $2,870 | $14 | $2,927 | $2,927 | $2,852 | NA | NA | |
Continuous Hours per site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | 0.25 | 116 | 116 | 0.25 | 116 | 116 | 0.25 | 116 | 116 | 116 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $5,968 | $5,968 | $13 | $6,207 | $6,207 | $14 | $6,331 | $6,331 | $6,169 | NA | NA | |
Sub Total - Hours | 0 | 1 | 146 | 151 | 50 | 0 | 348 | 160 | 53,060 | 53,060 | 160 | 62,385 | 62,385 | 160 | 62,385 | 62,385 | 59,277 | NA | NA | |
Sub Total - Costs | $0 | $12 | $3,680 | $4,163 | $1,566 | $0 | $9,421 | $20,154 | $5,901,427 | $5,901,415 | $20,960 | $5,345,692 | $5,345,692 | $21,391 | $5,452,631 | $5,461,333 | $5,569,480 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Years Amoritized | 7 | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||||
Audit/Calibration Kits (Filter Based) | $125 | 2019 | $151 | $29,467 | $842 | $157 | $30,646 | $876 | $160 | $31,259 | $893 | NA | $870 | NA | ||||||
Audit/Calibration Kits (Continuous) | $360 | 2019 | $435 | $202,373 | $5,782 | $453 | $210,468 | $6,013 | $462 | $214,677 | $6,134 | NA | $5,976 | NA | ||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits - Filter based Hours per site | 0 | 0 | 0 | 35 | 34 | 0 | 69 | 22.5 | 4,830 | 4,830 | 22.5 | 4,830 | 4,830 | 22.5 | 4,830 | 4,830 | 4,830 | NA | NA | |
Cost per site | 0 | 0 | 0 | 965 | 1065 | 0 | $2,030 | $4,343 | $933,671 | $933,671 | $4,516 | $971,018 | $971,018 | $4,607 | $990,438 | $990,438 | $965,042 | NA | NA | |
Audits - Continuous Hours per site | 0 | 0 | 12 | 0 | 0 | 0 | 12 | NA | 5,580 | 5,580 | NA | 5,580 | 5,580 | NA | 5,580 | 5,580 | 5,580 | NA | NA | |
Cost per site | 0 | 0 | 303 | 0 | 0 | 0 | $303 | $648 | $301,408 | $301,408 | $674 | $313,464 | $313,464 | $688 | $319,734 | $319,734 | $311,535 | NA | NA | |
Training - Filter Hours per site | 0 | 0 | 0 | 4 | 0 | 0 | 4 | NA | 780 | 780 | NA | 860 | 860 | NA | 860 | 860 | 833 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 0 | 0 | $110 | $235 | $45,887 | $45,887 | $245 | $47,722 | $47,722 | $250 | $48,677 | $48,677 | $47,428 | NA | NA | |
Training - Continuous Hours per site | 0 | 0 | 2 | 2 | 1 | 0 | 5 | NA | 2,325 | 2,325 | NA | 2,325 | 2,325 | NA | 2,325 | 2,325 | 2,325 | NA | NA | |
Cost per site | 0 | 0 | 50 | 55 | 31 | 0 | $136 | $291 | $135,285 | $135,285 | $303 | $140,697 | $140,697 | $309 | $143,511 | $143,511 | $139,831 | NA | NA | |
Reporting - Filter Hours per site | 0 | 0 | 0 | 6 | 6 | 0 | 12 | NA | 2,580 | 2,580 | NA | 2,580 | 2,580 | NA | 2,580 | 2,580 | 2,580 | NA | NA | |
Cost per site | 0 | 0 | 0 | 165 | 188 | 0 | $353 | $755 | $162,358 | $162,358 | $785 | $168,852 | $168,852 | $801 | $172,229 | $172,229 | $167,813 | NA | NA | |
Reporting - Cont Hours per site | 0 | 0 | 2 | 2 | 1 | 0 | 5 | NA | 2,325 | 2,325 | NA | 1,075 | 1,075 | NA | 1,075 | 1,075 | 1,492 | NA | NA | |
Cost per site | 0 | 0 | 50 | 55 | 31 | 0 | $136 | $291 | $135,285 | $135,285 | $303 | $140,697 | $140,697 | $309 | $143,511 | $143,511 | $139,831 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0.2 | 0.3 | 0 | 0 | 0.5 | NA | 57 | 57 | NA | 0 | 0 | NA | 0 | 0 | 19 | NA | NA | |
Cost | 0 | 0 | 5 | 8 | 0 | 0 | $13 | $28 | $3,143 | $3,143 | $29 | $0 | $0 | $30 | $0 | $0 | $1,048 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 6 | 5 | 5 | 0 | 16 | NA | 1808 | 362 | NA | 0 | 0 | NA | 0 | 0 | 121 | NA | NA | |
Cost per RO | 0 | 0 | 151 | 138 | 157 | 0 | $446 | $954 | $107,813 | $21,563 | $992 | $0 | $0 | $1,012 | $0 | $0 | $7,188 | NA | NA | |
Sub Total - Hours | 0 | 0 | 22 | 54 | 47 | 0 | 124 | NA | 20,285 | 18,838 | NA | 17,250 | 17,250 | NA | 17,250 | 17,250 | 17,779 | |||
Sub Total - Costs | $0 | $0 | $559 | $1,496 | $1,472 | $0 | $3,527 | $7,545 | $1,824,850 | $1,738,599 | $7,847 | $1,782,450 | $1,782,450 | $8,004 | $1,818,099 | $1,818,099 | $1,779,716 | $6,847 | NA | |
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Filter Based Hours per site | 0 | 0 | 0 | 2 | 2 | 0 | 4 | NA | 780 | 780 | NA | 780 | 780 | NA | 780 | 780 | 780 | NA | NA | |
Cost per site | 0 | 0 | 0 | 55 | 63 | 0 | $118 | $252 | 49,224 | $49,224 | $263 | 51,193 | $51,193 | $268 | 52,217 | $52,217 | $50,878 | NA | NA | |
Continuous Hours per site | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 6 | 12 | 0 | 18 | NA | 8,370 | 8,370 | NA | 8,370 | 8,370 | NA | 8,370 | 8,370 | 8,370 | NA | NA | |
Cost per site | 0 | 0 | 0 | 165 | 376 | 0 | $541 | $1,157 | $538,158 | $538,158 | $1,204 | $559,684 | $559,684 | $1,228 | $570,878 | $570,878 | $556,240 | NA | NA | |
Supervision/review | ||||||||||||||||||||
Filter Based Hours per site | 0 | 0 | 0 | 0 | 3 | 3 | 6 | NA | 1,170 | 1,170 | NA | 1,170 | 1,170 | NA | 1,170 | 1,170 | 1,170 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 94 | 113 | $207 | $443 | $86,350 | $86,350 | $461 | $89,804 | $89,804 | $470 | $91,600 | $91,600 | $89,252 | NA | NA | |
Continuous Hours per site | 0 | 0 | 0 | 3 | 3 | 0 | 6 | NA | 2,790 | 2,790 | NA | 2,790 | 2,790 | NA | 2,790 | 2,790 | 2,790 | NA | NA | |
Cost per site | 0 | 0 | 0 | 83 | 94 | 0 | $177 | $379 | $176,070 | $176,070 | $394 | $183,113 | $183,113 | $402 | $186,775 | $186,775 | $181,986 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 11 | 20 | 3 | 34 | NA | 13,110 | 13110 | NA | 13110 | 13110 | NA | 13110 | 13110 | 13,110 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $303 | $627 | $113 | $1,043 | NA | $849,802 | $849,802 | NA | $883,794 | $883,794 | NA | $901,470 | $901,470 | $878,355 | NA | NA | |
Summary by Element | PM10 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 6 | 2 | 12 | 10 | 10 | 40 | NA | 4,520 | 646 | NA | 4,520 | 646 | NA | 1,130 | 161 | 484 | |||
Costs | $0 | $145 | $50 | $331 | $313 | $378 | $1,217 | $2,603 | $294,190 | $42,027 | $2,708 | $305,958 | $43,708 | $2,762 | $312,077 | $44,582 | $43,439 | NA | NA | |
2 - Site Installation Hours | 0 | 4 | 4 | 0 | 0 | 0 | 8 | NA | 3,696 | 1,192 | NA | 3,696 | 1,192 | NA | 3,696 | 1,192 | 1,192 | |||
Costs | $0 | $97 | $101 | $0 | $0 | $0 | $198 | $31,358 | $13,439,786 | $1,981,473 | $32,612 | $13,911,612 | $2,051,337 | $33,264 | $14,156,962 | $2,087,666 | $69,744 | NA | $1,970,414 | |
3 - Supplies & site visits Hours | 0 | 84 | 169 | 127 | 0 | 0 | 380 | NA | 56,897 | 56,897 | NA | 48,897 | 48,897 | NA | 48,897 | 48,897 | 9,547 | NA | NA | |
Costs | $0 | $2,033 | $4,262 | $3,501 | $0 | $0 | $9,796 | $20,956 | $3,771,514 | $3,771,514 | $21,794 | $3,470,739 | $3,470,739 | $22,230 | $3,540,154 | $3,540,154 | $3,594,136 | $757,867 | NA | |
4 - Maintenance Hours | 0 | 85 | 50 | 25 | 0 | 0 | 160 | NA | 11,200 | 11,200 | NA | 11,200 | 11,200 | NA | 11,200 | 11,200 | 11,200 | |||
Costs | $0 | $2,057 | $1,261 | $689 | $0 | $0 | $4,957 | $9,720 | $2,089,886 | $2,089,886 | $10,109 | $2,173,482 | $2,173,482 | $10,311 | $2,216,951 | $2,216,951 | $1,904,889 | $577,692 | NA | |
5 - Data Managment Hours | 0 | 0.5 | 146 | 151 | 50 | 0 | 347.5 | 160 | 53,060 | 53,060 | 160 | 62,385 | 62,385 | 160 | 62,385 | 62,385 | 59,277 | NA | NA | |
Costs | $0 | $12 | $3,680 | $4,163 | $1,566 | $0 | $9,421 | $20,154 | $5,901,427 | $5,901,415 | $20,960 | $5,345,692 | $5,345,692 | $21,391 | $5,452,631 | $5,461,333 | $5,569,480 | NA | NA | |
6 - Quality Assurance Hours | 0 | 0 | 22 | 54 | 47 | 0 | 124 | NA | 20285 | 18838 | NA | 17250 | 17250 | NA | 17250 | 17250 | 17779 | NA | NA | |
Costs | $0 | $0 | $559 | $1,496 | $1,472 | $0 | $3,527 | $7,545 | $1,824,850 | $1,738,599 | $7,847 | $1,782,450 | $1,782,450 | $8,004 | $1,818,099 | $1,818,099 | $1,779,716 | $6,847 | NA | |
7 - Supervision Hours | 0 | 0 | 0 | 11 | 20 | 3 | 34 | NA | 13110 | 13110 | NA | 13110 | 13110 | NA | 13110 | 13110 | 13110 | NA | NA | |
Costs | $0 | $0 | $0 | $303 | $627 | $113 | $1,043 | NA | $849,802 | $849,802 | NA | $883,794 | $883,794 | NA | $901,470 | $901,470 | $878,355 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 180 | 393 | 380 | 127 | 13 | 1,093 | NA | 142,483 | 154,943 | NA | 143,808 | 154,680 | NA | 140,418 | 154,196 | 112,589 | NA | ||
Costs | $0 | $4,344 | $9,913 | $10,483 | $3,978 | $491 | $30,159 | NA | 26,346,605 | $16,374,717 | NA | 26,091,276 | $15,751,201 | NA | 26,580,244 | $16,070,255 | $13,839,759 | $1,342,405 | $1,970,414 | |
Data Entry for | PAMSVOC | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | 39 | ||||||||||||||||||
0.00% | Report Org | Auto GC Sites | 43 | Report Org | Sites | 43 | Report Org | Sites | 43 | Sites | 43 | |||||||||
Overall Comment | 39 | Canister Sites | 0 | 39 | Canister Sites | 0 | 39 | Canister Sites | 0 | Canister Sites | 0 | |||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 5 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 5 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $100,000 | 2019 | $120,892 | $5,198,342 | $1,039,668 | $125,727 | $5,406,275 | $1,081,255 | $128,242 | $5,514,401 | $1,102,880 | NA | NA | $1,074,601 | ||||||
Canister sampling system | $16,000 | 2019 | $19,343 | $0 | $0 | $20,116 | $865,004 | $173,001 | $20,519 | $882,304 | $176,461 | $116,487 | ||||||||
Gas cleaning system | $5,667 | 2019 | $6,851 | $294,590 | $58,918 | $7,125 | $306,374 | $61,275 | $7,267 | $312,501 | $62,500 | NA | NA | $60,898 | ||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 8 | 0 | 0 | 8 | NA | 344 | 69 | NA | 344 | 69 | NA | 344 | 69 | 69 | NA | NA | |
Cost per site | 0 | 0 | 0 | 221 | 0 | 0 | $221 | $473 | $20,329 | $4,066 | $492 | $21,142 | $4,228 | $502 | $21,565 | $4,313 | $4,202 | NA | NA | |
Installation Hours per site | 0 | 0 | 0 | 10 | 5 | 0 | 15 | NA | 645 | 129 | NA | 645 | 129 | NA | 645 | 129 | 129 | NA | NA | |
Cost per site | 0 | 0 | 0 | 276 | 157 | 0 | $433 | $926 | $39,830 | $7,966 | $963 | $41,424 | $8,285 | $983 | $42,252 | $8,450 | $8,234 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 18 | 5 | 0 | 23 | NA | 989 | 198 | NA | 989 | 198 | NA | 989 | 198 | 198 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $497 | $157 | $0 | $654 | $1,399 | 60,160 | $1,110,618 | $1,455 | 62,566 | $1,328,044 | $1,484 | 63,817 | $1,354,605 | $12,436 | NA | $1,251,986 | |
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$16,000 | 2019 | $19,343 | $831,735 | $831,735 | $20,116 | $865,004 | $865,004 | $20,519 | $882,304 | $882,304 | NA | $859,681 | NA | |||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 88 | 0 | 0 | 88 | NA | 3,784 | 3,784 | NA | 3,784 | 3,784 | NA | 3,784 | 3,784 | 3,784 | NA | NA | |
Cost per site | 0 | 0 | 0 | 2426 | 0 | 0 | $2,426 | $5,190 | $223,161 | $223,161 | $5,397 | $232,088 | $232,088 | $5,505 | $236,729 | $236,729 | $230,659 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 88 | 0 | 0 | 88 | NA | 3,784 | 3,784 | NA | 3,784 | 3,784 | NA | 3,784 | 3,784 | 3,784 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $2,426 | $0 | $0 | $18,426 | $24,532 | $1,054,896 | $1,054,896 | $25,514 | $1,097,092 | $1,097,092 | $26,024 | $1,119,033 | $1,119,033 | $1,090,340 | $859,681 | NA | |
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$3,000 | 2019 | $3,627 | $155,950 | $155,950 | $3,772 | $162,188 | $162,188 | $3,847 | $165,432 | $165,432 | NA | $161,190 | NA | |||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 24 | 8 | 0 | 32 | NA | 1,376 | 1,376 | NA | 1,376 | 1,376 | NA | 1,376 | 1,376 | 1,376 | NA | NA | |
Cost per site | 0 | 0 | 0 | 662 | 250 | 0 | $912 | $1,951 | $83,892 | $83,892 | $2,029 | $87,248 | $87,248 | $2,070 | $88,993 | $88,993 | $86,711 | NA | NA | |
Routine Maint. Hours per site | 0 | 0 | 0 | 48 | 16 | 0 | 64 | NA | 2,752 | 2,752 | NA | 2,752 | 2,752 | NA | 2,752 | 2,752 | 2,752 | NA | NA | |
Cost per site | 0 | 0 | 0 | 1323 | 501 | 0 | $1,824 | $3,902 | $167,785 | $167,785 | $4,058 | $174,496 | $174,496 | $4,139 | $177,986 | $177,986 | $173,422 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 72 | 24 | 0 | 96 | NA | 4,128 | 4,128 | NA | 4,128 | 4,128 | NA | 4,128 | 4,128 | 4,128 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $1,985 | $751 | $0 | $5,736 | $9,480 | $407,627 | $407,627 | $9,859 | $423,933 | $423,933 | $10,056 | $432,411 | $432,411 | $260,134 | $161,190 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 24 | 0 | 0 | 24 | NA | 1,032 | 1,032 | NA | 1,032 | 1,032 | NA | 1,032 | 1,032 | 1,032 | NA | NA | |
Cost per site | 0 | 0 | 0 | 662 | 0 | 0 | $662 | $1,416 | $60,896 | $60,896 | $1,473 | $63,331 | $63,331 | $1,502 | $64,598 | $64,598 | $62,942 | NA | NA | |
Data reporting Hours per site | 0 | 0 | 0 | 8 | 1 | 1 | 10 | NA | 430 | 430 | NA | 430 | 430 | NA | 430 | 430 | 430 | NA | NA | |
Cost per site | 0 | 0 | 0 | 221 | 31 | 38 | $290 | $620 | $26,676 | $26,676 | $645 | $27,743 | $27,743 | $658 | $28,298 | $28,298 | $27,573 | NA | NA | |
Data validation Hours per site | 0 | 0 | 0 | 32 | 8 | 0 | 40 | NA | 1,720 | 1,720 | NA | 1,720 | 1,720 | NA | 1,720 | 1,720 | 1,720 | NA | NA | |
Cost per site | 0 | 0 | 0 | 882 | 250 | 0 | $1,132 | $2,422 | $104,130 | $104,130 | $2,518 | $108,295 | $108,295 | $2,569 | $110,461 | $110,461 | $107,628 | NA | NA | |
Data distribution Hours per site | 0 | 0 | 0 | 70 | 30 | 10 | 110 | NA | 4,730 | 4,730 | NA | 4,730 | 4,730 | NA | 4,730 | 4,730 | 4,730 | NA | NA | |
Cost per site | 0 | 0 | 0 | 1930 | 939 | 378 | $3,247 | $6,946 | $298,683 | $298,683 | $7,224 | $310,630 | $310,630 | $7,368 | $316,843 | $316,843 | $308,718 | NA | NA | |
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | 0.25 | 11 | 11 | 0.25 | 11 | 11 | 0.25 | 11 | 11 | 11 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $138 | $138 | $13 | $144 | $144 | $14 | $146 | $146 | $143 | NA | NA | |
Sub Total - Hours | 0 | 0.25 | 0 | 134 | 39 | 11 | 184.25 | NA | 7,923 | 7,923 | NA | 7,923 | 7,923 | NA | 7,923 | 7,923 | 7,923 | NA | NA | |
Sub Total - Costs | $0 | $6 | $0 | $3,695 | $1,220 | $416 | $5,337 | $11,417 | $490,522 | $490,522 | $11,874 | $510,143 | $510,143 | $12,111 | $520,346 | $520,346 | $507,004 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 8 | 8 | 0 | 16 | NA | 688 | 688 | NA | 688 | 688 | NA | 688 | 688 | 688 | NA | NA | |
Cost per site | 0 | 0 | 0 | 221 | 250 | 0 | $471 | $1,008 | $43,326 | $43,326 | $1,048 | $45,059 | $45,059 | $1,069 | $45,960 | $45,960 | $44,782 | NA | NA | |
Routine Calibrations Hours per site | 0 | 0 | 0 | 16 | 0 | 0 | 16 | NA | 688 | 688 | NA | 688 | 688 | NA | 688 | 688 | 688 | NA | NA | |
Cost per site | 0 | 0 | 0 | 441 | 0 | 0 | $441 | $943 | $40,566 | $40,566 | $981 | $42,189 | $42,189 | $1,001 | $43,033 | $43,033 | $41,929 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 4 | 5 | 0 | 9 | NA | 387 | 387 | NA | 387 | 387 | NA | 387 | 387 | 387 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 157 | 0 | $267 | $571 | $24,561 | $24,561 | $594 | $25,543 | $25,543 | $606 | $26,054 | $26,054 | $25,386 | NA | NA | |
Training Hours per site | 0 | 0 | 0 | 0 | 20 | 0 | 20 | NA | 860 | 860 | NA | 860 | 860 | NA | 860 | 860 | 860 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 626 | 0 | $626 | $1,339 | $57,584 | $57,584 | $1,393 | $59,887 | $59,887 | $1,421 | $61,085 | $61,085 | $59,519 | NA | NA | |
Reporting Hours per site | 0 | 0 | 0 | 6 | 2 | 0 | 8 | NA | 344 | 344 | NA | 344 | 344 | NA | 344 | 344 | 344 | NA | NA | |
Cost per site | 0 | 0 | 0 | 165 | 63 | 0 | $228 | $488 | $20,973 | $20,973 | $507 | $21,812 | $21,812 | $517 | $22,248 | $22,248 | $21,678 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 0 | 0 | 10 | 5 | 15 | NA | 585 | 117 | NA | 585 | 117 | NA | 585 | 117 | 117 | NA | NA | |
Cost per RO | 0 | 0 | 0 | 0 | 313 | 189 | $502 | $1,074 | $41,882 | $8,376 | $1,117 | $43,557 | $8,711 | $1,139 | $44,428 | $8,886 | $8,658 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 34 | 45 | 5 | 84 | NA | NA | 3,084 | NA | NA | 3,084 | NA | NA | 3,084 | 3,084 | |||
Sub Total - Costs | $0 | $0 | $0 | $937 | $1,409 | $189 | $2,535 | $5,423 | NA | $195,387 | $5,640 | NA | $203,202 | $5,753 | NA | $207,266 | $201,952 | |||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 20 | 0 | 20 | NA | 860 | 860 | NA | 860 | 860 | NA | 860 | 860 | 860 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 626 | 0 | $626 | $1,339 | $57,584 | $57,584 | $1,393 | $59,887 | $59,887 | $1,421 | $61,085 | $61,085 | $59,519 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 0 | 0 | 16 | 8 | 24 | NA | 1,032 | 1,032 | NA | 1,032 | 1,032 | NA | 1,032 | 1,032 | 1,032 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 501 | 303 | $804 | $1,720 | $73,958 | $73,958 | $1,789 | $76,916 | $76,916 | $1,825 | $78,454 | $78,454 | $76,443 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 36 | 8 | 44 | NA | 1892 | 1892 | NA | 1892 | 1892 | NA | 1892 | 1,892 | 1,892 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $1,127 | $303 | $1,430 | $3,059 | $131,542 | $131,542 | $3,181 | $136,803 | $136,803 | $3,245 | $139,540 | $139,540 | $135,962 | NA | NA | |
Summary by Element | PAMSVOC | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | |||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
2 - Site Installation Hours | 0 | 0 | 0 | 18 | 5 | 0 | 23 | NA | 989 | 198 | NA | 989 | 198 | NA | 989 | 198 | 198 | |||
Costs | $0 | $0 | $0 | $497 | $157 | $0 | $654 | $1,399 | $60,160 | $1,110,618 | $1,455 | $62,566 | $1,328,044 | $1,484 | $63,817 | $1,354,605 | $12,436 | NA | $1,251,986 | |
3 - Supplies & site visits Hours | 0 | 0 | 0 | 88 | 0 | 0 | 88 | NA | 3784 | 3784 | NA | 3784 | 3784 | NA | 3784 | 3784 | 3784 | NA | NA | |
Costs | $0 | $0 | $0 | $2,426 | $0 | $0 | $18,426 | $24,532 | $1,054,896 | $1,054,896 | $25,514 | $1,097,092 | $1,097,092 | $26,024 | $1,119,033 | $1,119,033 | $1,090,340 | $859,681 | NA | |
4 - Maintenance Hours | 0 | 0 | 0 | 72 | 24 | 0 | 96 | NA | 4128 | 4128 | NA | 4128 | 4128 | NA | 4128 | 4128 | 4128 | |||
Costs | $0 | $0 | $0 | $1,985 | $751 | $0 | $5,736 | $9,480 | $407,627 | $407,627 | $9,859 | $423,933 | $423,933 | $10,056 | $432,411 | $432,411 | $260,134 | $161,190 | NA | |
5 - Data Managment Hours | 0 | 0.25 | 0 | 134 | 39 | 11 | 184.25 | NA | 7922.75 | 7922.75 | NA | 7922.75 | 7922.75 | NA | 7922.75 | 7922.75 | 7922.75 | NA | NA | |
Costs | $0 | $6 | $0 | $3,695 | $1,220 | $416 | $5,337 | $11,417 | $490,522 | $490,522 | $11,874 | $510,143 | $510,143 | $12,111 | $520,346 | $520,346 | $507,004 | NA | NA | |
6 - Quality Assurance Hours | 0 | 0 | 0 | 34 | 45 | 5 | 84 | NA | NA | 3084 | NA | NA | 3084 | NA | NA | 3084 | 3084 | NA | NA | |
Costs | $0 | $0 | $0 | $937 | $1,409 | $189 | $2,535 | $5,423 | NA | $195,387 | $5,640 | NA | $203,202 | $5,753 | NA | $207,266 | $201,952 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 0 | 0 | 36 | 8 | 44 | NA | 1892 | 1892 | NA | 1892 | 1892 | NA | 1892 | 1892 | 1892 | NA | NA | |
Costs | $0 | $0 | $0 | $0 | $1,127 | $303 | $1,430 | $3,059 | $131,542 | $131,542 | $3,181 | $136,803 | $136,803 | $3,245 | $139,540 | $139,540 | $135,962 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 0 | 0 | 346 | 149 | 24 | 519 | NA | 18,716 | 21,009 | NA | 18,716 | 21,009 | NA | 18,716 | 21,009 | 21,009 | NA | ||
Costs | $0 | $6 | $0 | $9,540 | $4,664 | $908 | $34,118 | $55,310 | 2,144,747 | $3,390,592 | $57,523 | 2,230,537 | $3,699,216 | $58,673 | 2,275,147 | $3,773,201 | $2,207,827 | $1,020,871 | $1,251,986 |
Data Entry for | PAMSNOx | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | 39 | ||||||||||||||||||
0.00% | Report Org | Precursor NOy | 43 | Report Org | Precursor NOy | 43 | Report Org | Precursor NOy | 43 | Precursor NOy | 43 | |||||||||
Other | 0 | Other | 0 | Other | 0 | Other | 0 | |||||||||||||
Overall Comment | 39 | Spares | 0 | 39 | Spares | 0 | 39 | Spares | 0 | Spares | 0 | |||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design (1) | Years Amoritized | 5 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Element 2 - Site Installation (1) | Years Amoritized | 5 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $20,500 | 2019 | $24,783 | $1,065,660 | $213,132 | $25,774 | $1,108,286 | $221,657 | $26,290 | $1,130,452 | $226,090 | NA | NA | $220,293 | ||||||
Spare Analyzers | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | $0 | |||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Installation Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $213,132 | $0 | $221,657 | $0 | $226,090 | $0 | NA | $220,293 | ||||
Element 3 - Supplies and Site Visits (1) | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$800 | 2019 | $967 | $41,587 | $41,587 | $1,006 | $43,250 | $43,250 | $1,026 | $44,115 | $44,115 | NA | $42,984 | NA | |||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $967 | $41,587 | $41,587 | $1,006 | $43,250 | $43,250 | $1,026 | $44,115 | $44,115 | $42,984 | $42,984 | NA | |
Element 4 - Maintenance (1) | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$1,000 | 2019 | $1,209 | $51,983 | $51,983 | $1,257 | $54,063 | $54,063 | $1,282 | $55,144 | $55,144 | NA | $53,730 | NA | |||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Routine Maint. Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | 0 | $1,209 | $51,983 | $51,983 | $1,257 | $54,063 | $54,063 | $1,282 | $55,144 | $55,144 | $0 | $53,730 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Data reporting Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Data validation Hours per site | 0 | 0 | 5 | 10 | 0 | 0 | 15 | NA | 645 | 645 | NA | 645 | 645 | NA | 645 | 645 | 645 | NA | NA | |
Cost per site | 0 | 0 | 126 | 276 | 0 | 0 | $402 | $860 | $36,979 | $36,979 | $894 | $38,458 | $38,458 | $912 | $39,227 | $39,227 | $38,221 | NA | NA | |
Data distribution Hours per site | 0 | 0 | 2 | 3 | 0 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | NA | NA | |
Cost per site | 0 | 0 | 50 | 83 | 0 | 0 | $133 | $285 | $12,234 | $12,234 | $296 | $12,724 | $12,724 | $302 | $12,978 | $12,978 | $12,645 | NA | NA | |
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | 0.25 | 11 | 11 | 0.25 | 11 | 11 | 0.25 | 11 | 11 | 11 | NA | NA | |
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $138 | $138 | $13 | $144 | $144 | $14 | $146 | $146 | $143 | NA | NA | |
Sub Total - Hours | 0 | 0.25 | 7 | 13 | 0 | 0 | 20.25 | NA | 871 | 871 | NA | 871 | 871 | NA | 871 | 871 | 871 | NA | NA | |
Sub Total - Costs | $0 | $6 | $176 | $359 | $0 | $0 | $541 | $1,157 | $49,351 | $49,351 | $1,204 | $51,325 | $51,325 | $1,228 | $52,352 | $52,352 | $51,009 | NA | NA | |
Element 6 - Quality Assurance (1) | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 36 | 36 | 0 | 0 | 72 | NA | 3,096 | 3,096 | NA | 3,096 | 3,096 | NA | 3,096 | 3,096 | 3,096 | NA | NA | |
Cost per site | 0 | 0 | 908 | 992 | 0 | 0 | $1,900 | $4,065 | $174,776 | $174,776 | $4,227 | $181,767 | $181,767 | $4,312 | $185,402 | $185,402 | $180,648 | NA | NA | |
Routine Calibrations Hours per site | 0 | 24 | 24 | 0 | 0 | 0 | 48 | NA | 2,064 | 2,064 | NA | 2,064 | 2,064 | NA | 2,064 | 2,064 | 2,064 | NA | NA | |
Cost per site | 0 | 581 | 605 | 0 | 0 | 0 | $1,186 | $2,537 | $109,097 | $109,097 | $2,639 | $113,461 | $113,461 | $2,691 | $115,730 | $115,730 | $112,763 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 2 | 2 | 0 | 4 | NA | 172 | 172 | NA | 172 | 172 | NA | 172 | 172 | 172 | NA | NA | |
Cost per site | 0 | 0 | 0 | 55 | 63 | 0 | $118 | $252 | $10,854 | $10,854 | $263 | $11,289 | $11,289 | $268 | $11,514 | $11,514 | $11,219 | NA | NA | |
Training Hours per site | 0 | 1 | 1 | 2 | 1 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 31 | 0 | $135 | $289 | $12,418 | $12,418 | $300 | $12,915 | $12,915 | $306 | $13,173 | $13,173 | $12,836 | NA | NA | |
Reporting Hours per site | 0 | 0 | 3 | 3 | 0 | 0 | 6 | NA | 258 | 258 | NA | 258 | 258 | NA | 258 | 258 | 258 | NA | NA | |
Cost per site | 0 | 0 | 76 | 83 | 0 | 0 | $159 | $340 | $14,626 | $14,626 | $354 | $15,211 | $15,211 | $361 | $15,515 | $15,515 | $15,117 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 5 | 5 | 5 | 0 | 15 | NA | 585 | 117 | NA | 585 | 117 | NA | 585 | 117 | 117 | NA | NA | |
Cost per RO | 0 | 0 | 126 | 138 | 157 | 0 | $421 | $901 | $35,124 | $7,025 | $937 | $36,529 | $7,306 | $955 | $37,260 | $7,452 | $7,261 | NA | NA | |
Sub Total - Hours | 0 | 25 | 69 | 48 | 8 | 0 | 150 | NA | NA | 5,922 | NA | NA | 5,922 | NA | NA | 5,922 | 5,922 | |||
Sub Total - Costs | $0 | $605 | $1,740 | $1,323 | $251 | $0 | $3,919 | $8,384 | NA | $328,796 | $8,719 | NA | $341,948 | $8,893 | NA | $348,787 | $339,844 | |||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 8 | 4 | 12 | NA | 516 | 516 | NA | 516 | 516 | NA | 516 | 516 | 516 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 250 | 151 | $401 | $858 | $36,887 | $36,887 | $892 | $38,362 | $38,362 | $910 | $39,130 | $39,130 | $38,126 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 16 | 8 | 4 | 2 | 30 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | 1,290 | NA | NA | |
Cost per site | 0 | 0 | 404 | 221 | 125 | 76 | $826 | $1,767 | $75,981 | $75,981 | $1,838 | $79,021 | $79,021 | $1,874 | $80,601 | $80,601 | $78,534 | NA | NA | |
Sub Total - Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 1806 | 1806 | NA | 1806 | 1806 | NA | 1806 | 1,806 | 1,806 | NA | NA | |
Sub Total - Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $112,868 | $112,868 | $2,730 | $117,383 | $117,383 | $2,784 | $119,731 | $119,731 | $116,661 | NA | NA | |
Summary by Element | PAMSNOx | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | |||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
2 - Site Installation Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | |||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $213,132 | $0 | $0 | $221,657 | $0 | $0 | $226,090 | $0 | NA | $220,293 | |
3 - Supplies & site visits Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $967 | $41,587 | $41,587 | $1,006 | $43,250 | $43,250 | $1,026 | $44,115 | $44,115 | $42,984 | $42,984 | NA | |
4 - Maintenance Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | |||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $1,209 | $51,983 | $51,983 | $1,257 | $54,063 | $54,063 | $1,282 | $55,144 | $55,144 | $0 | $53,730 | NA | |
5 - Data Managment Hours | 0 | 0.25 | 7 | 13 | 0 | 0 | 20.25 | NA | 870.75 | 870.75 | NA | 870.75 | 870.75 | NA | 870.75 | 870.75 | 870.75 | NA | NA | |
Costs | $0 | $6 | $176 | $359 | $0 | $0 | $541 | $1,157 | $49,351 | $49,351 | $1,204 | $51,325 | $51,325 | $1,228 | $52,352 | $52,352 | $51,009 | NA | NA | |
6 - Quality Assurance Hours | 0 | 25 | 69 | 48 | 8 | 0 | 150 | NA | NA | 5922 | NA | NA | 5922 | NA | NA | 5922 | 5922 | NA | NA | |
Costs | $0 | $605 | $1,740 | $1,323 | $251 | $0 | $3,919 | $8,384 | NA | $328,796 | $8,719 | NA | $341,948 | $8,893 | NA | $348,787 | $339,844 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 1806 | 1806 | NA | 1806 | 1806 | NA | 1806 | 1806 | 1806 | NA | NA | |
Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $112,868 | $112,868 | $2,730 | $117,383 | $117,383 | $2,784 | $119,731 | $119,731 | $116,661 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 25 | 92 | 69 | 20 | 6 | 212 | NA | 2,677 | 8,599 | NA | 2,677 | 8,599 | NA | 2,677 | 8,599 | 8,599 | NA | ||
Costs | $0 | $611 | $2,320 | $1,903 | $626 | $227 | $5,687 | $14,342 | 255,790 | $797,718 | $14,916 | 266,021 | $829,627 | $15,214 | 271,342 | $846,219 | $550,498 | $96,714 | $220,293 | |
1) includes costs for Precursor NOy analyzers only, NO2 analyzers are covered in NO2 network costs (see seperate spreadsheet) |
Data Entry for | PAMSSurfMet | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | 39 | ||||||||||||||||||
5.00% | Report Org | Sites | 43 | Report Org | Sites | 43 | Report Org | Sites | 43 | Sites | 43 | |||||||||
Overall Comment | 39 | Spares | 2 | 39 | Spares | 2 | 39 | Spares | 2 | Spares | 2 | |||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 5 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
Network Design and Site Selection | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 5 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Analyzers | $17,285 | 2019 | $20,896 | $898,533 | $179,707 | $21,732 | $934,475 | $186,895 | $22,167 | $953,164 | $190,633 | NA | NA | $185,745 | ||||||
Spare Analyzers | $44,927 | $8,985 | $46,724 | $9,345 | $47,658 | $9,532 | NA | NA | $9,287 | |||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 4 | 4 | 0 | 8 | NA | 361 | 72 | NA | 361 | 72 | NA | 361 | 72 | 72 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 125 | 0 | $235 | $503 | $22,698 | $4,540 | $523 | $22,482 | $4,496 | $533 | $22,931 | $4,586 | $4,541 | NA | NA | |
Installation Hours per site | 0 | 8 | 8 | 0 | 0 | 0 | 16 | NA | 688 | 138 | NA | 688 | 138 | NA | 688 | 138 | 138 | NA | NA | |
Cost per site | 0 | 194 | 202 | 0 | 0 | 0 | $396 | $847 | $36,427 | $7,285 | $881 | $37,884 | $7,577 | $899 | $38,642 | $7,728 | $7,530 | NA | NA | |
Sub Total - Hours | 0 | 8 | 8 | 4 | 4 | 0 | 24 | NA | 1,049 | 210 | NA | 1,049 | 210 | NA | 1,049 | 210 | 210 | NA | NA | |
Sub Total - Costs | $0 | $194 | $202 | $110 | $125 | $0 | $631 | $1,350 | $200,517 | $1,404 | $208,313 | $1,432 | $212,479 | $12,071 | NA | $195,032 | ||||
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$750 | 2019 | $907 | $38,988 | $38,988 | $943 | $40,547 | $40,547 | $962 | $41,358 | $41,358 | NA | $40,298 | NA | |||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 5,160 | 5,160 | NA | 5,160 | 5,160 | NA | 5,160 | 5,160 | 5,160 | NA | NA | |
Cost per site | 0 | 1452 | 1513 | 0 | 0 | 0 | $2,965 | $6,343 | $272,742 | $272,742 | $6,597 | $283,652 | $283,652 | $6,728 | $289,325 | $289,325 | $281,906 | NA | NA | |
Sub Total - Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 5,160 | 5,160 | NA | 5,160 | 5,160 | NA | 5,160 | 5,160 | 5,160 | NA | NA | |
Sub Total - Costs | $0 | $1,452 | $1,513 | $0 | $0 | $0 | $3,715 | $7,250 | $311,730 | $311,730 | $7,540 | $324,199 | $324,199 | $7,690 | $330,683 | $330,683 | $322,204 | $40,298 | NA | |
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$2,000 | 2019 | $2,418 | $103,967 | $103,967 | $2,515 | $108,126 | $108,126 | $2,565 | $110,288 | $110,288 | NA | $107,460 | NA | |||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 8 | 8 | 0 | 0 | 16 | NA | 688 | 688 | NA | 688 | 688 | NA | 688 | 688 | 688 | NA | NA | |
Cost per site | 0 | 0 | 202 | 221 | 0 | 0 | $423 | $905 | $38,911 | $38,911 | $941 | $40,467 | $40,467 | $960 | $41,276 | $41,276 | $40,218 | NA | NA | |
Routine Maint. Hours per site | 0 | 0 | 30 | 40 | 0 | 0 | 70 | NA | 3,010 | 3,010 | NA | 3,010 | 3,010 | NA | 3,010 | 3,010 | 3,010 | NA | NA | |
Cost per site | 0 | 0 | 757 | 1103 | 0 | 0 | $1,860 | $3,979 | $171,096 | $171,096 | $4,138 | $177,940 | $177,940 | $4,221 | $181,499 | $181,499 | $176,845 | NA | NA | |
Sub Total - Hours | 0 | 0 | 38 | 48 | 0 | 0 | 86 | NA | 3,698 | 3,698 | NA | 3,698 | 3,698 | NA | 3,698 | 3,698 | 3,698 | NA | NA | |
Sub Total - Costs | $0 | $0 | $959 | $1,324 | $0 | $0 | $4,283 | $7,302 | $313,974 | $313,974 | $7,594 | $326,533 | $326,533 | $7,746 | $333,063 | $333,063 | $217,063 | $107,460 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 8 | 8 | 4 | 0 | 20 | NA | 860 | 860 | NA | 860 | 860 | NA | 860 | 860 | 860 | NA | NA | |
Cost per site | 0 | 0 | 202 | 221 | 125 | 0 | $548 | $1,172 | $50,409 | $50,409 | $1,219 | $52,425 | $52,425 | $1,244 | $53,474 | $53,474 | $52,103 | NA | NA | |
Data reporting Hours per site | 0 | 0 | 3 | 4 | 3 | 0 | 10 | NA | 430 | 430 | NA | 430 | 430 | NA | 430 | 430 | 430 | NA | NA | |
Cost per site | 0 | 0 | 76 | 110 | 94 | 0 | $280 | $599 | $25,756 | $25,756 | $623 | $26,787 | $26,787 | $635 | $27,322 | $27,322 | $26,622 | NA | NA | |
Data validation Hours per site | 0 | 0 | 5 | 10 | 0 | 0 | 15 | NA | 645 | 645 | NA | 645 | 645 | NA | 645 | 645 | 645 | NA | NA | |
Cost per site | 0 | 0 | 126 | 276 | 0 | 0 | $402 | $860 | $36,979 | $36,979 | $894 | $38,458 | $38,458 | $912 | $39,227 | $39,227 | $38,221 | NA | NA | |
Data distribution Hours per site | 0 | 0 | 2 | 3 | 0 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | NA | NA | |
Cost per site | 0 | 0 | 50 | 83 | 0 | 0 | $133 | $285 | $12,234 | $12,234 | $296 | $12,724 | $12,724 | $302 | $12,978 | $12,978 | $12,645 | NA | NA | |
Asset Management Hours per Site | 0 | 0.5 | 0 | 0 | 0 | 0 | 0.5 | 0.5 | 22 | 22 | 0.5 | 22 | 22 | 0.5 | 22 | 22 | 22 | NA | NA | |
Cost per site | 0 | 11 | 0 | 0 | 0 | 0 | $11 | $24 | $506 | $506 | $24 | $526 | $526 | $25 | $537 | $537 | $523 | NA | NA | |
Sub Total - Hours | 0 | 0.5 | 18 | 25 | 7 | 0 | 50.5 | NA | 2,172 | 2,172 | NA | 2,172 | 2,172 | NA | 2,172 | 2,172 | 2,172 | NA | NA | |
Sub Total - Costs | $0 | $11 | $454 | $690 | $219 | $0 | $1,374 | $2,939 | $125,885 | $125,885 | $3,057 | $130,920 | $130,920 | $3,118 | $133,538 | $133,538 | $130,114 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 36 | 36 | 0 | 72 | NA | 3,096 | 3,096 | NA | 3,096 | 3,096 | NA | 3,096 | 3,096 | 3,096 | NA | NA | |
Cost per site | 0 | 0 | 0 | 992 | 1127 | 0 | $2,119 | $4,533 | $194,921 | $194,921 | $4,714 | $202,718 | $202,718 | $4,809 | $206,772 | $206,772 | $201,470 | NA | NA | |
Routine Calibrations Hours per site | 0 | 24 | 24 | 0 | 0 | 0 | 48 | NA | 2,064 | 2,064 | NA | 2,064 | 2,064 | NA | 2,064 | 2,064 | 2,064 | NA | NA | |
Cost per site | 0 | 581 | 605 | 0 | 0 | 0 | $1,186 | $2,537 | $109,097 | $109,097 | $2,639 | $113,461 | $113,461 | $2,691 | $115,730 | $115,730 | $112,763 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 2 | 2 | 0 | 4 | NA | 172 | 172 | NA | 172 | 172 | NA | 172 | 172 | 172 | NA | NA | |
Cost per site | 0 | 0 | 0 | 55 | 63 | 0 | $118 | $252 | $10,854 | $10,854 | $263 | $11,289 | $11,289 | $268 | $11,514 | $11,514 | $11,219 | NA | NA | |
Training Hours per site | 0 | 1 | 1 | 2 | 1 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | NA | NA | |
Cost per site | 0 | 24 | 25 | 55 | 31 | 0 | $135 | $289 | $12,418 | $12,418 | $300 | $12,915 | $12,915 | $306 | $13,173 | $13,173 | $12,836 | NA | NA | |
Reporting Hours per site | 0 | 0 | 0 | 3 | 3 | 0 | 6 | NA | 258 | 258 | NA | 258 | 258 | NA | 258 | 258 | 258 | NA | NA | |
Cost per site | 0 | 0 | 0 | 83 | 94 | 0 | $177 | $379 | $16,282 | $16,282 | $394 | $16,933 | $16,933 | $402 | $17,272 | $17,272 | $16,829 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0.2 | 0.3 | 0 | 0 | 0.5 | NA | 20 | 20 | NA | 20 | 20 | NA | 20 | 20 | 20 | NA | NA | |
Cost | 0 | 0 | 5 | 8 | 0 | 0 | $13 | $28 | $1,085 | $1,085 | $29 | $1,128 | $1,128 | $30 | $1,151 | $1,151 | $1,121 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 0 | 5 | 5 | 5 | 15 | NA | 585 | 117 | NA | 585 | 117 | NA | 585 | 117 | 117 | NA | NA | |
Cost per RO | 0 | 0 | 0 | 138 | 157 | 189 | $484 | $1,035 | $40,380 | $8,076 | $1,077 | $41,995 | $8,399 | $1,098 | $42,835 | $8,567 | $8,347 | NA | NA | |
Sub Total - Hours | 0 | 25 | 25 | 48 | 47 | 5 | 151 | NA | NA | 5,942 | NA | NA | 5,942 | NA | NA | 5,942 | 5,942 | |||
Sub Total - Costs | $0 | $605 | $635 | $1,331 | $1,472 | $189 | $4,232 | $9,053 | NA | $352,733 | $9,415 | NA | $366,842 | $9,604 | NA | $374,179 | $364,585 | |||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 8 | 4 | 12 | NA | 516 | 516 | NA | 516 | 516 | NA | 516 | 516 | 516 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 250 | 151 | $401 | $858 | $36,887 | $36,887 | $892 | $38,362 | $38,362 | $910 | $39,130 | $39,130 | $38,126 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 16 | 8 | 4 | 2 | 30 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | 1,290 | NA | NA | |
Cost per site | 0 | 0 | 404 | 221 | 125 | 76 | $826 | $1,767 | $75,981 | $75,981 | $1,838 | $79,021 | $79,021 | $1,874 | $80,601 | $80,601 | $78,534 | NA | NA | |
Sub Total - Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 1806 | 1806 | NA | 1806 | 1806 | NA | 1806 | 1,806 | 1,806 | NA | NA | |
Sub Total - Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $112,868 | $112,868 | $2,730 | $117,383 | $117,383 | $2,784 | $119,731 | $119,731 | $116,661 | NA | NA | |
Summary by Element | PAMSSurfMet | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | |||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
2 - Site Installation Hours | 0 | 8 | 8 | 4 | 4 | 0 | 24 | NA | 1,049 | 210 | NA | 1,049 | 210 | NA | 1,049 | 210 | 210 | |||
Costs | $0 | $194 | $202 | $110 | $125 | $0 | $631 | $1,350 | $0 | $200,517 | $1,404 | $0 | $208,313 | $1,432 | $0 | $212,479 | $12,071 | NA | $195,032 | |
3 - Supplies & site visits Hours | 0 | 60 | 60 | 0 | 0 | 0 | 120 | NA | 5160 | 5160 | NA | 5160 | 5160 | NA | 5160 | 5160 | 5160 | NA | NA | |
Costs | $0 | $1,452 | $1,513 | $0 | $0 | $0 | $3,715 | $7,250 | $311,730 | $311,730 | $7,540 | $324,199 | $324,199 | $7,690 | $330,683 | $330,683 | $322,204 | $40,298 | NA | |
4 - Maintenance Hours | 0 | 0 | 38 | 48 | 0 | 0 | 86 | NA | 3698 | 3698 | NA | 3698 | 3698 | NA | 3698 | 3698 | 3698 | |||
Costs | $0 | $0 | $959 | $1,324 | $0 | $0 | $4,283 | $7,302 | $313,974 | $313,974 | $7,594 | $326,533 | $326,533 | $7,746 | $333,063 | $333,063 | $217,063 | $107,460 | NA | |
5 - Data Managment Hours | 0 | 0.5 | 18 | 25 | 7 | 0 | 50.5 | NA | 2171.5 | 2171.5 | NA | 2171.5 | 2171.5 | NA | 2171.5 | 2171.5 | 2171.5 | NA | NA | |
Costs | $0 | $11 | $454 | $690 | $219 | $0 | $1,374 | $2,939 | $125,885 | $125,885 | $3,057 | $130,920 | $130,920 | $3,118 | $133,538 | $133,538 | $130,114 | NA | NA | |
6 - Quality Assurance Hours | 0 | 25 | 25 | 48 | 47 | 5 | 151 | NA | NA | 5942 | NA | NA | 5942 | NA | NA | 5942 | 5942 | NA | NA | |
Costs | $0 | $605 | $635 | $1,331 | $1,472 | $189 | $4,232 | $9,053 | NA | $352,733 | $9,415 | NA | $366,842 | $9,604 | NA | $374,179 | $364,585 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 16 | 8 | 12 | 6 | 42 | NA | 1806 | 1806 | NA | 1806 | 1806 | NA | 1806 | 1806 | 1806 | NA | NA | |
Costs | $0 | $0 | $404 | $221 | $375 | $227 | $1,227 | $2,625 | $112,868 | $112,868 | $2,730 | $117,383 | $117,383 | $2,784 | $119,731 | $119,731 | $116,661 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 94 | 165 | 133 | 70 | 11 | 473 | NA | 13,885 | 18,987 | NA | 13,885 | 18,987 | NA | 13,885 | 18,987 | 18,987 | NA | ||
Costs | $0 | $2,262 | $4,167 | $3,676 | $2,191 | $416 | $15,462 | $30,519 | 864,457 | $1,417,707 | $31,739 | 899,035 | $1,474,190 | $32,374 | 917,015 | $1,503,674 | $1,162,698 | $147,758 | $195,032 |
Data Entry for | PAMSUpperAir | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | ||||||||||
Spare Factor | Report Org | 39 | |||||||||||||||||||
0.00% | Report Org | Sites | 43 | Report Org | Sites | 43 | Report Org | Sites | 43 | Sites | 43 | ||||||||||
Overall Comment | 39 | Spares | 0 | 39 | Spares | 0 | 39 | Spares | 0 | Spares | 0 | ||||||||||
General Costs | Labor | Non Labor O & M |
|||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 5 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | |||||||||||||||
Network Design and Site Selection (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | ||||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | ||
Costs per RO | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | ||
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | ||
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | ||
Element 2 - Site Installation | Years Amoritized | 5 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | |||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Materials | Sites | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Cielometer | $26,500 | 2019 | 43 | $32,036 | $1,377,561 | $275,512 | $33,318 | $1,432,663 | $286,533 | $33,984 | $1,461,316 | $292,263 | NA | NA | $284,769 | ||||||
Radar profiler | $125,000 | 2019 | 0 | $151,115 | $0 | $0 | $157,159 | $0 | $0 | $160,302 | $0 | $0 | NA | NA | $0 | ||||||
Rawindsondes | $45,000 | 2019 | 0 | $54,401 | $0 | $0 | $56,577 | $0 | $0 | $57,709 | $0 | $0 | NA | NA | $0 | ||||||
SODAR | $65,000 | 2019 | 0 | $78,580 | $0 | $0 | $81,723 | $0 | $0 | $83,357 | $0 | $0 | NA | NA | $0 | ||||||
LAP/RASS +NEXRAD | $125,000 | 2019 | 0 | $151,115 | $0 | $0 | $157,159 | $0 | $0 | $160,302 | $0 | $0 | NA | NA | $0 | ||||||
Computer hardware & software | $8,000 | 2019 | $9,671 | $415,867 | $83,173 | $10,058 | $432,502 | $86,500 | $10,259 | $441,152 | $88,230 | NA | NA | $85,968 | |||||||
Total | $1,793,428 | $358,686 | $1,865,165 | $373,033 | $1,902,468 | $380,494 | NA | NA | $370,737 | ||||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Per Site Total | |||||||||||||
Acceptance Testing Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Procurement Hours per site | 0 | 0 | 0 | 8 | 8 | 0 | 0 | 16 | NA | 688 | 138 | NA | 688 | 138 | NA | 688 | 138 | 138 | NA | NA | |
Cost per site | $0 | $0 | $0 | $221 | $250 | $0 | $0 | $471 | $1,008 | $43,326 | $8,665 | $1,048 | $45,059 | $9,012 | $1,069 | $45,960 | $9,192 | $8,956 | NA | NA | |
Installation Hours per site | 0 | 0 | 0 | 12 | 7 | 0 | 0 | 19 | NA | 817 | 163 | NA | 817 | 163 | NA | 817 | 163 | 163 | NA | NA | |
Cost per site | $0 | $0 | $0 | $331 | $219 | $0 | $0 | $550 | $1,177 | $50,593 | $10,119 | $1,224 | $52,617 | $10,523 | $1,248 | $53,669 | $10,734 | $10,459 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 20 | 15 | 0 | 35 | NA | 1,505 | 301 | NA | 1,505 | 301 | NA | 1,505 | 301 | 301 | NA | NA | ||
Sub Total - Costs | $0 | $0 | $0 | $552 | $469 | $0 | $1,021 | $2,184 | $1,887,347 | $377,469 | $392,568 | $400,420 | $19,415 | NA | $370,737 | ||||||
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | |||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||||
$0 | 2019 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | $0 | NA | ||||||||
Routine field service checks | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 16 | 0 | 0 | 16 | NA | 688 | 688 | NA | 688 | 688 | NA | 688 | 688 | 688 | NA | NA | ||
Cost per site | $0 | $0 | $0 | $441 | $0 | $0 | $441 | $943 | $40,566 | $40,566 | $981 | $42,189 | $42,189 | $1,001 | $43,033 | $43,033 | $41,929 | NA | NA | ||
Sub Total - Hours | 0 | 0 | 0 | 16 | 0 | 0 | 16 | NA | 688 | 688 | NA | 688 | 688 | NA | 688 | 688 | 688 | NA | NA | ||
Sub Total - Costs | $0 | $0 | $0 | $16 | $0 | $0 | $441 | $943 | $40,566 | $40,566 | $981 | $42,189 | $42,189 | $1,001 | $43,033 | $43,033 | $41,929 | $0 | NA | ||
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | |||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||||
$2,000 | 2019 | $2,418 | $103,967 | $103,967 | $2,515 | $108,126 | $108,126 | $2,565 | $110,288 | $110,288 | NA | $107,460 | NA | ||||||||
Remedial Field Service | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 5 | 0 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | NA | NA | ||
Cost per site | $0 | $0 | $0 | $138 | $0 | $0 | $138 | $295 | $12,694 | $12,694 | $307 | $13,202 | $13,202 | $313 | $13,466 | $13,466 | $13,121 | NA | NA | ||
Sub Total - Hours | 0 | 0 | 0 | 5 | 0 | 0 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $138 | $0 | $0 | $0 | $138 | $295 | $12,694 | $12,694 | $307 | $13,202 | $13,202 | $313 | $13,466 | $13,466 | $13,121 | $107,460 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | |||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Data aquisition/processing, etc. | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 3 | 3 | 0 | 0 | 6 | NA | 258 | 258 | NA | 258 | 258 | NA | 258 | 258 | 258 | NA | NA | ||
Cost per site | $0 | $0 | $76 | $83 | $0 | $0 | $159 | $340 | $14,626 | $14,626 | $354 | $15,211 | $15,211 | $361 | $15,515 | $15,515 | $15,117 | NA | NA | ||
Data validation Hours per site | 0 | 0 | 0 | 4 | 0 | 0 | 4 | NA | 172 | 172 | NA | 172 | 172 | NA | 172 | 172 | 172 | NA | NA | ||
Cost per site | $0 | $0 | $0 | $110 | $0 | $0 | $110 | $235 | $10,119 | $10,119 | $245 | $10,523 | $10,523 | $250 | $10,734 | $10,734 | $10,459 | NA | NA | ||
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | 0.25 | 11 | 11 | 0.25 | 11 | 11 | 0.25 | 11 | 11 | 11 | NA | NA | ||
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $138 | $138 | $13 | $144 | $144 | $14 | $146 | $146 | $143 | NA | NA | ||
Sub Total - Hours | 0 | 0.25 | 3 | 7 | 0 | 0 | 0 | 10.25 | NA | 441 | 441 | NA | 441 | 441 | NA | 441 | 441 | 441 | NA | NA | |
Sub Total - Costs | $0 | $6 | $76 | $193 | $0 | $0 | $0 | $275 | $588 | $24,883 | $24,883 | $612 | $25,878 | $25,878 | $624 | $26,395 | $26,395 | $25,719 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | ||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 18 | 18 | 0 | 36 | NA | 1,548 | 1,548 | NA | 1,548 | 1,548 | NA | 1,548 | 1,548 | 1,548 | NA | NA | ||
Cost per site | $0 | $0 | $0 | $496 | $564 | $0 | $1,060 | $2,268 | $97,507 | $97,507 | $2,358 | $101,407 | $101,407 | $2,405 | $103,435 | $103,435 | $100,783 | NA | NA | ||
Routine Calibrations Hours per site | 0 | 0 | 18 | 12 | 0 | 0 | 30 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | 1,290 | NA | NA | ||
Cost per site | $0 | $0 | $454 | $331 | $0 | $0 | $785 | $1,679 | $72,210 | $72,210 | $1,746 | $75,098 | $75,098 | $1,781 | $76,600 | $76,600 | $74,636 | NA | NA | ||
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 1 | 1 | 0 | 2 | NA | 86 | 86 | NA | 86 | 86 | NA | 86 | 86 | 86 | NA | NA | ||
Cost per site | $0 | $0 | $0 | $28 | $31 | $0 | $59 | $126 | $5,427 | $5,427 | $131 | $5,644 | $5,644 | $134 | $5,757 | $5,757 | $5,610 | NA | NA | ||
Training Hours per site | 0 | 1 | 1 | 2 | 1 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | NA | NA | ||
Cost per site | $0 | $24 | $25 | $55 | $31 | $0 | $135 | $289 | $12,418 | $12,418 | $300 | $12,915 | $12,915 | $306 | $13,173 | $13,173 | $12,836 | NA | NA | ||
Reporting Hours per site | 0 | 0 | 0 | 3 | 3 | 0 | 6 | NA | 258 | 258 | NA | 258 | 258 | NA | 258 | 258 | 258 | NA | NA | ||
Cost per site | $0 | $0 | $0 | $83 | $94 | $0 | $177 | $379 | $16,282 | $16,282 | $394 | $16,933 | $16,933 | $402 | $17,272 | $17,272 | $16,829 | NA | NA | ||
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0.2 | 0.3 | 0 | 0 | 0.5 | NA | 20 | 20 | NA | 20 | 20 | NA | 20 | 20 | 20 | NA | NA | ||
Cost | $0 | $0 | $5 | $8 | $0 | $0 | $13 | $28 | $1,085 | $1,085 | $29 | $1,128 | $1,128 | $30 | $1,151 | $1,151 | $1,121 | NA | NA | ||
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | ||||||||||||||
Hours per RO | 0 | 0 | 0 | 6 | 18 | 0 | 24 | NA | 936 | 187 | NA | 936 | 187 | NA | 936 | 187 | 187 | NA | NA | ||
Cost per RO | $0 | $0 | $0 | $165 | $564 | $0 | $729 | $1,560 | $60,821 | $12,164 | $1,622 | $63,254 | $12,651 | $1,654 | $64,519 | $12,904 | $12,573 | NA | NA | ||
Sub Total - Hours | 0 | 1 | 19 | 42 | 41 | 0 | 104 | NA | NA | 3,604 | NA | NA | 3,604 | NA | NA | 3,604 | 3,604 | ||||
Sub Total - Costs | $0 | $24 | $484 | $1,166 | $1,284 | $0 | $2,958 | $6,328 | NA | $217,093 | $6,581 | NA | $225,776 | $6,713 | NA | $230,292 | $224,387 | ||||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | |||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Contractor | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 6 | 6 | 12 | NA | 516 | 516 | NA | 516 | 516 | NA | 516 | 516 | 516 | NA | NA | ||
Cost per site | 0 | $0 | $0 | $0 | $188 | $227 | $415 | $888 | $38,175 | $38,175 | $923 | $39,702 | $39,702 | $942 | $40,496 | $40,496 | $39,457 | NA | NA | ||
Supervision/review Hours per site | 0 | 0 | 16 | 8 | 4 | 2 | 30 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | NA | 1,290 | 1,290 | 1,290 | NA | NA | ||
Cost per site | $0 | $0 | $404 | $221 | $125 | $76 | $826 | $1,767 | $75,981 | $75,981 | $1,838 | $79,021 | $79,021 | $1,874 | $80,601 | $80,601 | $78,534 | NA | NA | ||
Sub Total - Hours | 0 | 0 | 16 | 8 | 10 | 8 | 42 | NA | 1806 | 1806 | NA | 1806 | 1806 | NA | 1806 | 1,806 | 1,806 | NA | NA | ||
Sub Total - Costs | $0 | $0 | $404 | $221 | $313 | $303 | $1,241 | $2,655 | $114,156 | $114,156 | $2,761 | $118,722 | $118,722 | $2,816 | $121,097 | $121,097 | $117,992 | NA | NA | ||
Summary by Element | PAMSUpperAir | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||
1 - Network Design Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | ||||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | ||
2 - Site Installation Hours | 0 | 0 | 0 | 20 | 15 | 0 | 35 | NA | 1,505 | 301 | NA | 1,505 | 301 | NA | 1,505 | 301 | 301 | ||||
Costs | $0 | $0 | $0 | $552 | $469 | $0 | $1,021 | $2,184 | $1,887,347 | $377,469 | $0 | $0 | $392,568 | $0 | $0 | $400,420 | $19,415 | NA | $370,737 | ||
3 - Supplies & site visits Hours | 0 | 0 | 0 | 16 | 0 | 0 | 16 | NA | 688 | 688 | NA | 688 | 688 | NA | 688 | 688 | 688 | NA | NA | ||
Costs | $0 | $0 | $0 | $16 | $0 | $0 | $441 | $943 | $40,566 | $40,566 | $981 | $42,189 | $42,189 | $1,001 | $43,033 | $43,033 | $41,929 | $0 | NA | ||
4 - Maintenance Hours | 0 | 0 | 0 | 5 | 0 | 0 | 5 | NA | 215 | 215 | NA | 215 | 215 | NA | 215 | 215 | 215 | ||||
Costs | $0 | $0 | $0 | $138 | $0 | $0 | $138 | $295 | $12,694 | $12,694 | $307 | $13,202 | $13,202 | $313 | $13,466 | $13,466 | $13,121 | $107,460 | NA | ||
5 - Data Managment Hours | 0 | 0.25 | 3 | 7 | 0 | 0 | 10.25 | NA | 440.75 | 440.75 | NA | 440.75 | 440.75 | NA | 440.75 | 440.75 | 440.75 | NA | NA | ||
Costs | $0 | $6 | $76 | $193 | $0 | $0 | $275 | $588 | $24,883 | $24,883 | $612 | $25,878 | $25,878 | $624 | $26,395 | $26,395 | $25,719 | NA | NA | ||
6 - Quality Assurance Hours | 0 | 1 | 19 | 42 | 41 | 0 | 104 | NA | NA | 3604 | NA | NA | 3604 | NA | NA | 3604 | 3604 | NA | NA | ||
Costs | $0 | $24 | $484 | $1,166 | $1,284 | $0 | $2,958 | $6,328 | NA | $217,093 | $6,581 | NA | $225,776 | $6,713 | NA | $230,292 | $224,387 | $0 | NA | ||
7 - Supervision Hours | 0 | 0 | 16 | 8 | 10 | 8 | 42 | NA | 1806 | 1806 | NA | 1806 | 1806 | NA | 1806 | 1806 | 1806 | NA | NA | ||
Costs | $0 | $0 | $404 | $221 | $313 | $303 | $1,241 | $2,655 | $114,156 | $114,156 | $2,761 | $118,722 | $118,722 | $2,816 | $121,097 | $121,097 | $117,992 | NA | NA | ||
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Hours | 0 | 1 | 38 | 98 | 66 | 8 | 212 | NA | 4,655 | 7,054 | NA | 4,655 | 7,054 | NA | 4,655 | 7,054 | 7,054 | NA | |||
Costs | $0 | $30 | $964 | $2,286 | $2,066 | $303 | $6,074 | $12,994 | 2,079,646 | $786,861 | $11,242 | 199,991 | $818,336 | $11,467 | 203,991 | $834,702 | $442,562 | $107,460 | $370,737 |
Data Entry for | NATTS | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | ||||||||||
Spare Factor | Report Org | 22 | |||||||||||||||||||
0.00% | Report Org | Sites | 27 | Report Org | Sites | 27 | Report Org | Sites | 27 | Sites | 27 | ||||||||||
Overall Comment | 22 | Spares | 0 | 22 | Spares | 0 | 22 | Spares | 0 | Spares | 0 | ||||||||||
General Costs | Labor | Non Labor O & M |
|||||||||||||||||||
Element 1 - Network Design | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | |||||||||||||||||
Costs included with other pollutants | |||||||||||||||||||||
Sub Total - Hours | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Sub Total - Costs | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Element 2 - Site Installation | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | |||||||||||||||||
Costs included with other pollutants | |||||||||||||||||||||
Sub Total - Hours | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Sub Total - Costs | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | |||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||||
Analysis (grant to RO) | $129,385 | 2019 | $156,416 | $3,441,145 | $3,441,145 | $162,672 | $3,578,791 | $3,578,791 | $165,926 | $3,650,367 | $3,650,367 | NA | NA | $3,556,768 | |||||||
Sub Total - Hours | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Sub Total - Costs | $156,416 | $3,441,145 | $3,441,145 | $162,672 | $3,578,791 | $3,578,791 | $165,926 | $3,650,367 | $3,650,367 | NA | NA | 3,556,768 | |||||||||
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | |||||||||||||||||
Costs included with other pollutants | |||||||||||||||||||||
Sub Total - Hours | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Sub Total - Costs | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | |||||||||||||||||
Costs included with other pollutants | |||||||||||||||||||||
Sub Total - Hours | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Sub Total - Costs | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | ||||||||||||||
Costs included with other pollutants | |||||||||||||||||||||
Sub Total - Hours | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Sub Total - Costs | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | |||||||||||||||||
Costs included with other pollutants | |||||||||||||||||||||
Sub Total - Hours | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Sub Total - Costs | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | |||||||||
Summary by Element | NATTS | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||
1 - Network Design Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
2 - Site Installation Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
3 - Supplies & site visits Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $156,416 | $3,441,145 | $3,441,145 | $162,672 | $3,578,791 | $3,578,791 | $165,926 | $3,650,367 | $3,650,367 | NA | NA | 3,556,768 | ||
4 - Maintenance Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
5 - Data Managment Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
6 - Quality Assurance Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
7 - Supervision Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $156,416 | $3,441,145 | $3,441,145 | $162,672 | $3,578,791 | $3,578,791 | $165,926 | $3,650,367 | $3,650,367 | NA | NA | $3,556,768 |
Data Entry for | Generic Network | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | ||||||||||
Report Org | 168 | ||||||||||||||||||||
Small Shelter Sites | 1,789 | Small Shelter Sites | 1,789 | Small Shelter Sites | 1,789 | Sites | 1789 | ||||||||||||||
Large Shelter Sites | 444 | Large Shelter Sites | 444 | Large Shelter Sites | 444 | ||||||||||||||||
Total Shelter Sites | 2,233 | Total Shelter Sites | 2,233 | Total Shelter Sites | 2,233 | ||||||||||||||||
Other Sites | 0 | Other Sites | 0 | Other Sites | 0 | ||||||||||||||||
Total Sites | 2,233 | Total Sites | 2,233 | Total Sites | 2,233 | ||||||||||||||||
Report Org | QA Orgs | Report Org | QA Orgs | Report Org | QA Orgs | ||||||||||||||||
Overall Comment | 168 | 156 | 168 | 156 | 168 | 156 | |||||||||||||||
General Costs | Labor | Non Labor O & M |
|||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 7 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | |||||||||||||||
a) Network Design (see individual pollutants) | Entire Network | Entire Network | Entire Network | ||||||||||||||||||
b) Site Selection (see individual pollutants) | Base year | 2019 | Adjusted | Adjusted | Adjusted | ||||||||||||||||
c) Travel other than monitoring sites | Hours | 35,000 | 35,000 | 35,000 | 35,000 | 35,000 | NA | NA | |||||||||||||
Costs (not linked to hours) | $1,052,498 | $1,272,382 | $1,323,278 | $1,349,743 | $1,315,134 | NA | NA | ||||||||||||||
d) Saturation studies | Hours | 21,475 | 21,475 | 21,475 | 21,475 | 21,475 | NA | NA | |||||||||||||
Costs (not linked to hours) | $828,343 | $1,001,398 | $1,041,454 | $1,062,283 | $1,035,045 | NA | NA | ||||||||||||||
e) Additional indirect cost adj ($2/hour) | Base year | 2023 | Costs (not linked to hours) | $4,211,427 | $5,091,265 | $5,294,916 | $5,400,814 | NA | $5,262,331 | ||||||||||||
Sub Total - Hours | 56,475 | 56,475 | 56,475 | 56,475 | 56,475 | NA | NA | ||||||||||||||
Sub Total - Costs | $6,092,268 | $5,091,265 | $5,294,916 | $5,400,814 | $2,350,179 | NA | 5,262,331 | ||||||||||||||
Element 2 - Site Installation | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | |||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||||
Materials | Unit cost | Year | Years Amoritized | 7 | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||
Multigas calibrator | $14,000 | 2019 | $16,925 | $37,793,154 | $5,399,022 | $17,602 | $39,304,880 | $5,614,983 | $17,954 | $40,090,978 | $5,727,283 | NA | NA | $5,580,429 | |||||||
Zero air supply | $5,980 | 2019 | $7,229 | $16,143,076 | $2,306,154 | $7,518 | $16,788,799 | $2,398,400 | $7,669 | $17,124,575 | $2,446,368 | NA | NA | $2,383,640 | |||||||
Ambient air intake manifold assembly | $1,500 | 2019 | $1,813 | $4,049,266 | $578,467 | $1,886 | $4,211,237 | $601,605 | $1,924 | $4,295,462 | $613,637 | NA | NA | $597,903 | |||||||
Shelters | Unit cost | Year | Years Amoritized | 10 | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||
Shelter (large, temp controlled) | $30,000 | 2019 | $36,268 | $16,102,770 | $1,610,277 | $37,718 | $16,746,881 | $1,674,688 | $38,473 | $17,081,819 | $1,708,182 | NA | NA | $1,664,382 | |||||||
Shelter (small, temp controlled) | $13,000 | 2019 | $15,716 | $28,115,776 | $2,811,578 | $16,345 | $29,240,407 | $2,924,041 | $16,671 | $29,825,215 | $2,982,521 | NA | NA | $2,906,047 | |||||||
Shelter delivery charges | $1,500 | 2019 | $1,813 | $4,049,266 | $404,927 | $1,886 | $4,211,237 | $421,124 | $1,924 | $4,295,462 | $429,546 | NA | NA | $418,532 | |||||||
Other shelter equipment/accessories | $5,000 | 2019 | $6,045 | $13,497,555 | $1,349,755 | $6,286 | $14,037,457 | $1,403,746 | $6,412 | $14,318,206 | $1,431,821 | NA | NA | $1,395,107 | |||||||
Other | |||||||||||||||||||||
Site preparation | $4,500 | 2019 | $5,440 | $12,147,799 | $1,735,400 | $5,658 | $12,633,711 | $1,804,816 | $5,771 | $12,886,386 | $1,840,912 | NA | NA | $1,793,709 | |||||||
Power drop | $800 | 2019 | $967 | $2,159,609 | $308,516 | $1,006 | $2,245,993 | $320,856 | $1,026 | $2,290,913 | $327,273 | NA | NA | $318,882 | |||||||
Land/Lease | $4,000 | 2019 | $4,836 | $10,798,044 | $10,798,044 | $5,029 | $11,229,966 | $11,229,966 | $5,130 | $11,454,565 | $11,454,565 | NA | NA | $11,160,858 | |||||||
Rent | $284 | 2019 | $343 | $766,256 | $766,256 | $357 | $796,906 | $796,906 | $364 | $812,844 | $812,844 | NA | NA | $792,002 | |||||||
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | |||||||||
Sub Total - Costs | $145,622,572 | $28,068,394 | $151,447,475 | $29,191,130 | $154,476,424 | $29,774,953 | NA | NA | $29,011,492 | ||||||||||||
Element 3 - Sampling and Analysis | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | |||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||||
Utilities | $1,500 | 2019 | $1,813 | $4,049,266 | $4,049,266 | $1,886 | $4,211,237 | $4,211,237 | $1,924 | $4,295,462 | $4,295,462 | NA | $4,185,322 | NA | |||||||
Vehicle | $75,000 | 2019 | $90,669 | $90,669 | $90,669 | $94,296 | $94,296 | $94,296 | $96,181 | $96,181 | $96,181 | NA | $93,715 | NA | |||||||
Subtotal | $76,500 | $92,482 | $4,139,935 | $4,139,935 | $96,181 | $4,305,533 | $4,305,533 | $98,105 | $4,391,643 | $4,391,643 | NA | $4,279,037 | $0 | ||||||||
Open Path Monitoring | Hours | 2,610 | 2,610 | 2,610 | 2,610 | 2,610 | 2,610 | 2,610 | 2,610 | NA | NA | ||||||||||
Costs (not linked to hours) | $108,460 | $232,022 | $232,022 | $241,303 | $241,303 | $246,129 | $246,129 | $239,818 | NA | NA | |||||||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | ||||||||||||||
Hours per site | 0 | 0 | 0 | 0 | 1.6 | 1.6 | 3.2 | 3.2 | 7,146 | 7,146 | 3.2 | 7,146 | 7,146 | 3.2 | 7,146 | 7,146 | 7,146 | NA | NA | ||
Cost per site | 0 | 0 | 0 | 0 | 50 | 61 | $111 | $237 | $530,238 | $530,238 | $247 | $551,448 | $551,448 | $252 | $562,477 | $562,477 | $548,054 | NA | NA | ||
Sub Total - Hours | 0 | 0 | 0 | 0 | 1.6 | 1.6 | 3.2 | 3.2 | 9,756 | 9,756 | 3 | 9,756 | 9,756 | 3 | 9,756 | 9,756 | 9,756 | NA | NA | ||
Sub Total - Costs | $0 | $0 | $0 | $0 | $50 | $61 | $111 | $237 | $762,260 | $762,260 | $247 | $792,750 | $792,750 | $252 | $808,605 | $808,605 | $787,872 | NA | NA | ||
Element 4 - Maintenance - see individual pollutants | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | |||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||||
Sub Total - Hours | $0 | 0 | 0 | $0 | 0 | 0 | $0 | 0 | 0 | 0 | 0 | NA | |||||||||
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | |||||||||
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | |||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Analysis and Trends (Rep. Org.) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Hours per site | 0 | 0 | 1040 | 0 | 0 | 0 | 1040 | 1040 | 174,720 | 174,720 | 1040 | 174,720 | 174,720 | 1040 | 174,720 | 174,720 | 174,720 | NA | NA | ||
Cost per site | 0 | 0 | 26230 | 0 | 0 | 0 | $26,230 | $56,112 | 9,426,855 | $9,426,855 | $58,357 | 9,803,929 | $9,803,929 | $59,524 | 10,000,008 | $10,000,008 | $9,743,597 | NA | NA | ||
Asset Management Hours per Site | 0 | 0.25 | 0 | 0 | 0 | 0 | 0.25 | 0.25 | 558 | 558 | 0.25 | 558 | 558 | 0.25 | 558 | 558 | 558 | NA | NA | ||
Cost per site | 0 | 6 | 0 | 0 | 0 | 0 | $6 | $13 | $7,165 | $7,165 | $13 | $7,452 | $7,452 | $14 | $7,601 | $7,601 | $7,406 | NA | NA | ||
Sub Total - Hours | 0 | 0.25 | 1040 | 0 | 0 | 0 | 1040.25 | 1,040 | 175,278 | 175,278 | 1040.25 | 175278.25 | 175278.25 | 1,040 | 175,278 | 175,278 | 175,278 | NA | NA | ||
Sub Total - Costs | $0 | $6 | $26,230 | $0 | $0 | $0 | $26,236 | $56,125 | $9,434,020 | $9,434,020 | $58,370 | $9,811,381 | $9,811,381 | $59,537 | $10,007,609 | $10,007,609 | $9,751,004 | NA | NA | ||
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | ||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||||
Equipment | Unit cost | Year | Years Amoritized | 7 | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||||
Multigas calibrator | $14,000 | 2019 | $16,925 | $2,640,274 | $377,182 | $17,602 | $2,745,885 | $392,269 | $17,954 | $2,800,803 | $400,115 | NA | NA | $389,855 | |||||||
Zero air supply | $5,980 | 2019 | $7,229 | $1,127,774 | $161,111 | $7,518 | $1,172,885 | $167,555 | $7,669 | $1,196,343 | $170,906 | NA | NA | $166,524 | |||||||
Miscellaneous equipment | $2,500 | 2019 | $3,022 | $471,478 | $67,354 | $3,143 | $490,337 | $70,048 | $3,206 | $500,143 | $71,449 | NA | NA | $69,617 | |||||||
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||||||||||
Sub Total - Costs | $27,176 | $4,239,526 | $605,647 | $28,264 | $4,409,107 | $629,872 | $28,829 | $4,497,289 | $642,470 | $625,996 | |||||||||||
Element 7 - Supervision - see individual pollutants | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | |||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Sub Total - Hours | 0 | $0 | 0 | 0 | $0 | 0 | 0 | $0 | 0 | 0 | 0 | NA | NA | ||||||||
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | ||||||||
Summary by Element | Generic Network | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||||
1 - Network Design Hours | 0 | 0 | 0 | 0 | 0 | 0 | 56,475 | 56,475 | 0 | 0 | 56,475 | 0 | 0 | 56,475 | 56,475 | ||||||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $6,092,268 | $5,091,265 | $0 | $0 | $5,294,916 | $0 | $0 | $5,400,814 | $2,350,179 | NA | 5,262,331 | ||||
2 - Site Installation Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $145,622,572 | $28,068,394 | $0 | $151,447,475 | $29,191,130 | $0 | $154,476,424 | $29,774,953 | NA | NA | $29,011,492 | ||
3 - Sampling and Analysis Hours | 0 | 0 | 0 | 0 | 1.6 | 1.6 | 3.2 | 3.2 | 9,756 | 9,756 | 3.2 | 9,756 | 9,756 | 3.2 | 9,756 | 9,756 | 9755.6 | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $50 | $61 | $111 | $237 | $762,260 | $762,260 | $247 | $792,750 | $792,750 | $252 | $808,605 | $808,605 | $787,872 | $4,279,037 | NA | ||
4 - Maintenance Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | ||
5 - Data Managment Hours | 0 | 0.25 | 1040 | 0 | 0 | 0 | 1040.25 | 1040.25 | 175,278 | 175,278 | 1040.25 | 175,278 | 175,278 | 1040.25 | 175,278 | 175,278 | 175278.25 | NA | NA | ||
Costs | $0 | $6 | $26,230 | $0 | $0 | $0 | $26,236 | $56,125 | $9,434,020 | $9,434,020 | $58,370 | $9,811,381 | $9,811,381 | $59,537 | $10,007,609 | $10,007,609 | $9,751,004 | NA | NA | ||
6 - Quality Assurance Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $27,176 | $4,239,526 | $605,647 | $28,264 | $4,409,107 | $629,872 | $28,829 | $4,497,289 | $642,470 | NA | $0 | 642,470 | ||
7 - Supervision Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | ||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | ||
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Hours | 0 | 0 | 1,040 | 0 | 2 | 2 | 57,518 | NA | 185,034 | 185,034 | NA | 185,034 | 241,509 | NA | 185,034 | 241,509 | 241,509 | NA | |||
Costs | $0 | $6 | $26,230 | $0 | $50 | $61 | $6,118,615 | $5,174,804 | $160,058,378 | $38,870,321 | $86,881 | 162,051,606 | $45,720,050 | $88,618 | 165,292,638 | $46,634,451 | $12,889,055 | $4,279,037 | $35,542,290 |
Data Entry for | SENSORS | Updated on | August 19, 2018 | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | Average Yearly Costs | Equipment | |||||||||
Spare Factor | Report Org | 50 | ||||||||||||||||||
0.00% | Report Org | Sites | 500 | Report Org | Sites | 750 | Report Org | Sites | 1000 | Sites | 750 | |||||||||
Overall Comment | 30 | Spares | 0 | 50 | Spares | 0 | 70 | Spares | 0 | Spares | 0 | |||||||||
General Costs | Labor | Non Labor O & M |
||||||||||||||||||
Element 1 - Network Design | Years Amoritized | 7 | Comment | Element 1 - Network Design | Element 1 - Network Design | Element 1 - Network Design | ||||||||||||||
a) Network Design (by Reporting Organization) | Per RO | Per RO | Entire Network | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Labor Category | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per RO | 0 | 0 | 0 | 5 | 5 | 5 | 15 | NA | 450 | 64 | NA | 750 | 107 | NA | 750 | 107 | 93 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 138 | 157 | 189 | $484 | $1,035 | $31,062 | $4,437 | $1,077 | $32,304 | $4,615 | $1,098 | $32,950 | $4,707 | $4,586 | NA | NA | |
b) Site Selection (Reporting Organization) | ||||||||||||||||||||
Hours per RO | 0 | 0 | 0 | 4 | 4 | 0 | 8 | NA | 240 | 34 | NA | 400 | 57 | NA | 560 | 80 | 57 | NA | NA | |
Costs per RO | 0 | 0 | 0 | 110 | 125 | 0 | $235 | $503 | $15,082 | $2,155 | $523 | $15,685 | $2,241 | $533 | $15,999 | $2,286 | $2,227 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 9 | 9 | 5 | 23 | NA | 690 | 99 | NA | 1150 | 164 | NA | 1,610 | 230 | 164 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $248 | $282 | $189 | $719 | $1,538 | $46,143 | $6,592 | $1,600 | $47,989 | $6,856 | $1,632 | $114,214 | $16,316 | $9,921 | NA | NA | |
Element 2 - Site Installation | Years Amoritized | 7 | Comment | Element 2 - Site Installation | Element 2 - Site Installation | Element 2 - Site Installation | ||||||||||||||
Unit cost | Year | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||
Materials | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||||
Sensors | $1,000 | 2023 | $1,000 | $500,000 | $71,429 | $1,040 | $520,000 | $74,286 | $1,061 | $530,400 | $75,771 | NA | NA | $73,829 | ||||||
Spare Analyzers | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | $0 | |||||||||||
Labor | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Procurement Hours per site | 0 | 0 | 0 | 4 | 0 | 0 | 4 | NA | 2,000 | 286 | NA | 3,000 | 429 | NA | 4,000 | 571 | 429 | NA | NA | |
Cost per site | 0 | 0 | 0 | 110 | 0 | 0 | $110 | $235 | $117,658 | $16,808 | $245 | $122,364 | $17,481 | $250 | $124,812 | $17,830 | $17,373 | NA | NA | |
Installation Hours per site | 0 | 8 | 8 | 0 | 0 | 0 | 16 | NA | 8000 | 1143 | NA | 12,000 | 1714 | NA | 12,000 | 1714 | 1,524 | NA | NA | |
Cost per site | 0 | 194 | 202 | 0 | 0 | 0 | $396 | $847 | $423,569 | $60,510 | $881 | $660,768 | $94,395 | $899 | $898,645 | $128,378 | $94,428 | NA | NA | |
Sub Total - Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 10,000 | 1,429 | NA | 15,000 | 2,143 | NA | 16,000 | 2,286 | 1,952 | NA | NA | |
Sub Total - Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $148,747 | $1,126 | $186,162 | $1,148 | $221,979 | $111,801 | NA | $73,829 | ||||
Element 3 - Supplies and Site Visits | Comment | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | Element 3 - Supplies and Site Visits | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$0 | 2019 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | $0 | NA | |||||||
Routine visits | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | |
Element 4 - Maintenance | Comment | Element 4 - Maintenance | Element 4 - Maintenance | Element 4 - Maintenance | ||||||||||||||||
Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | |||||||||||||||
Spare parts/supplies | Unit cost | Year | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||||
$0 | 2019 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | $0 | NA | |||||||
Remedial Repairs | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Per Site Total | |||||||||||||
Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Routine Maint. Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | |
Element 5 - Data Management | Comment | Element 5 - Data Management | Element 5 - Data Management | Element 5 - Data Management | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Data aquisition/processing | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 6 | 3 | 3 | 2 | 0 | 14 | NA | 7,000 | 7,000 | NA | 10,500 | 10,500 | NA | 14,000 | 14,000 | 10,500 | NA | NA | |
Cost per site | 0 | 145 | 76 | 83 | 63 | 0 | $367 | $785 | $392,550 | $392,550 | $817 | $408,252 | $408,252 | $833 | $832,835 | $832,835 | $544,546 | NA | NA | |
Data reporting Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Data validation Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Data distribution Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Asset Management Hours per Site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 6 | 3 | 3 | 2 | 0 | 14 | NA | 7,000 | 7,000 | NA | 10,500 | 10,500 | NA | 14,000 | 14,000 | 10,500 | NA | NA | |
Sub Total - Costs | $0 | $145 | $76 | $83 | $63 | $0 | $367 | $785 | $392,550 | $392,550 | $817 | $408,252 | $408,252 | $833 | $832,835 | $832,835 | $544,546 | NA | NA | |
Element 6 - Quality Assurance | Comment | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Element 6 - Quality Assurance | Labor | Non Labor O & M |
Equipment | |||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
Audits Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Routine Calibrations Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Coordination/implementation | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||||
Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Training Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Reporting Hours per site | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
QA Plan review (annual) | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Labor per RO | Adjusted per RO | Total | Yearly Cost | Adjusted per RO | Total | Yearly Cost | |||||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
QA Plan preparation | Years Amoritized | 5 | Per RO | Per RO | Entire Network | Per RO | Entire Network | |||||||||||||
Hours per RO | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Cost per RO | 0 | 0 | 0 | 0 | 0 | 0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | NA | |
Sub Total - Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | 0 | NA | NA | 0 | NA | NA | 0 | 0 | |||
Sub Total - Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | $0 | $0 | NA | $0 | $0 | NA | $0 | $0 | |||
Element 7 - Supervision | Comment | Element 7 - Supervision | Element 7 - Supervision | Element 7 - Supervision | ||||||||||||||||
Per Site | Per Site | Entire Network | Per Site | Entire Network | Per Site | Entire Network | ||||||||||||||
Planning/coordination | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours per site | 0 | 0 | 0 | 0 | 5 | 2 | 7 | NA | 3,500 | 3,500 | NA | 5,250 | 5250 | NA | 7,000 | 7,000 | 5,250 | NA | NA | |
Cost per site | 0 | 0 | 0 | 0 | 157 | 76 | $233 | $498 | $249,221 | $249,221 | $518 | $388,785 | $388,785 | $529 | $528,748 | $528,748 | $388,918 | NA | NA | |
Supervision/review Hours per site | 0 | 0 | 5 | 3 | 2 | 1 | 11 | NA | 5,500 | 5,500 | NA | 8,250 | 8,250 | NA | 11,000 | 11,000 | 8,250 | NA | NA | |
Cost per site | 0 | 0 | 126 | 83 | 63 | 38 | $310 | $663 | $331,582 | $331,582 | $690 | $517,268 | $517,268 | $703 | $703,484 | $703,484 | $517,445 | NA | NA | |
Sub Total - Hours | 0 | 0 | 5 | 3 | 7 | 3 | 18 | NA | 9000 | 9000 | NA | 13500 | 13500 | NA | 18000 | 18,000 | 13,500 | NA | NA | |
Sub Total - Costs | $0 | $0 | $126 | $83 | $220 | $114 | $543 | $1,162 | $580,803 | $580,803 | $1,208 | $906,053 | $906,053 | $1,232 | $1,232,232 | $1,232,232 | $906,363 | NA | NA | |
Summary by Element | SENSORS | Year 1 | 2023 | Year 2 | 2024 | Year 3 | 2025 | |||||||||||||
TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | |||||
1 - Network Design Hours | 0 | 0 | 0 | 9 | 9 | 5 | 23 | NA | 690 | 99 | NA | 1,150 | 164 | NA | 1,610 | 230 | 164 | |||
Costs | $0 | $0 | $0 | $248 | $282 | $189 | $719 | $1,538 | $46,143 | $6,592 | $1,600 | $47,989 | $6,856 | $1,632 | $114,214 | $16,316 | $9,921 | NA | NA | |
2 - Site Installation Hours | 0 | 8 | 8 | 4 | 0 | 0 | 20 | NA | 10,000 | 1,429 | NA | 15,000 | 2,143 | NA | 16,000 | 2,286 | 1,952 | |||
Costs | $0 | $194 | $202 | $110 | $0 | $0 | $506 | $1,082 | $0 | $148,747 | $1,126 | $0 | $186,162 | $1,148 | $0 | $221,979 | $111,801 | NA | $73,829 | |
3 - Supplies & site visits Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | NA | NA | |
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | |
4 - Maintenance Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | NA | 0 | 0 | 0 | |||
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | |
5 - Data Managment Hours | 0 | 6 | 3 | 3 | 2 | 0 | 14 | NA | 7000 | 7000 | NA | 10500 | 10500 | NA | 14000 | 14000 | 10500 | NA | NA | |
Costs | $0 | $145 | $76 | $83 | $63 | $0 | $367 | $785 | $392,550 | $392,550 | $817 | $408,252 | $408,252 | $833 | $832,835 | $832,835 | $544,546 | NA | NA | |
6 - Quality Assurance Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NA | NA | 0 | NA | NA | 0 | NA | NA | 0 | 0 | NA | NA | |
Costs | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | NA | $0 | $0 | NA | $0 | $0 | NA | $0 | $0 | $0 | NA | |
7 - Supervision Hours | 0 | 0 | 5 | 3 | 7 | 3 | 18 | NA | 9000 | 9000 | NA | 13500 | 13500 | NA | 18000 | 18000 | 13500 | NA | NA | |
Costs | $0 | $0 | $126 | $83 | $220 | $114 | $543 | $1,162 | $580,803 | $580,803 | $1,208 | $906,053 | $906,053 | $1,232 | $1,232,232 | $1,232,232 | $906,363 | NA | NA | |
Total | TEC1 | TEC2 | PRO1 | PRO2 | PRO3 | PRO4 | Total | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | Adjusted | Total | Yearly Cost | ||||
Hours | 0 | 14 | 16 | 19 | 18 | 8 | 75 | NA | 26,690 | 17,527 | NA | 40,150 | 26,307 | NA | 49,610 | 34,516 | 26,117 | NA | ||
Costs | $0 | $339 | $404 | $524 | $565 | $303 | $2,135 | $4,567 | 1,019,497 | $1,128,692 | $4,750 | 1,362,295 | $1,507,323 | $4,845 | 2,179,281 | $2,303,363 | $1,572,631 | $0 | $73,829 |
Cost Element | Average 2023-2025 SO2 | Average 2023-2025 CO | Average 2023-2025 NO2 | |||||||||||||
Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | ||
1. Network Design | 451 | $31,513 | $31,513 | 385 | $26,957 | $26,957 | 434 | $30,374 | $30,374 | |||||||
2. Site Installation | 1,172 | $65,119 | $760,968 | $826,087 | 695 | $38,655 | $451,707 | $490,362 | 1,261 | $70,606 | $958,313 | $1,028,919 | ||||
3. Sampling & Analysis | 48,720 | $3,067,570 | $405,849 | $3,473,420 | 28,920 | $1,820,898 | $240,911 | $2,061,808 | 52,440 | $3,301,793 | $436,838 | $3,738,631 | ||||
4. Maintenance | 27,608 | $1,593,442 | $507,312 | $2,100,753 | 16,388 | $945,861 | $301,138 | $1,246,999 | 37,582 | $2,205,967 | $546,047 | $2,752,015 | ||||
5. Data Management | 15,936 | $939,008 | $939,008 | 9,459 | $557,392 | $557,392 | 21,959 | $1,324,677 | $1,324,677 | |||||||
6. Quality Assurance | 31,553 | $1,915,224 | $1,915,224 | 18,806 | $1,142,146 | $1,142,146 | 59,275 | $3,628,397 | $3,628,397 | |||||||
7. Supervision | 17,052 | $1,101,495 | $1,101,495 | 10,122 | $653,843 | $653,843 | 18,354 | $1,185,599 | $1,185,599 | |||||||
Totals | 142,490 | $8,713,372 | $913,161 | $760,968 | $10,387,500 | 84,776 | $5,185,750 | $542,049 | $451,707 | $6,179,506 | 191,306 | $11,747,414 | $982,885 | $958,313 | $13,688,612 | |
Cost Element | Average 2023-2025 O3 | Average 2023-2025 PM 10 | Average2023-2025 PM 2.5 | |||||||||||||
Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | ||
1. Network Design | 559 | $39,107 | $39,107 | 484 | $43,439 | $43,439 | 279 | 19,153 | 19,153 | |||||||
2. Site Installation | 3,301 | $180,063 | $2,617,814 | $2,797,878 | 1,192 | $69,744 | 1,970,414 | $2,040,159 | 3,611 | 285,666 | 4,230,670 | 4,516,336 | ||||
3. Sampling & Analysis | 95,900 | $7,283,674 | $1,110,588 | $8,394,262 | 9,547 | $3,594,136 | 757,867 | 38,771 | $4,390,774 | 23,904 | 10,949,498 | 221,918 | 4,332,301 | 15,503,717 | ||
4. Maintenance | 54,343 | $4,360,378 | $1,388,235 | $5,748,613 | 11,200 | $1,904,889 | 577,692 | $2,482,580 | 38,884 | 2,240,673 | 407,518 | 2,648,190 | ||||
5. Data Management | 31,445 | $2,569,553 | $2,569,553 | 59,277 | $5,569,480 | $5,569,480 | 112,991 | 7,048,060 | 7,048,060 | |||||||
6. Quality Assurance | 62,656 | $5,194,377 | $5,194,377 | 17,779 | $1,779,716 | 6,847 | $1,786,562 | 41,282 | 3,300,126 | 3,902 | 3,304,028 | |||||
7. Supervision | 33,565 | $3,014,188 | $3,014,188 | 13,110 | $878,355 | $878,355 | 67,248 | 4,491,296 | 4,491,296 | |||||||
Totals | 281,770 | $22,641,341 | $2,498,823 | $2,617,814 | $27,757,978 | 112,589 | $13,839,759 | $1,335,559 | $2,016,032 | $17,191,350 | 288,199 | 28,334,473 | 629,435 | 8,566,874 | 37,530,781 | |
Cost Element | Average 2023-2025 Pb | Average 2023-2025 NATTS | Average 2023-2025 PAMS | |||||||||||||
Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | ||
1. Network Design | 89 | $5,796 | $5,796 | $0 | 0 | 0 | 0 | |||||||||
2. Site Installation | 256 | $13,302 | $82,469 | $95,771 | $0 | 829 | 431,886 | 2,209,985 | 2,641,871 | |||||||
3. Sampling & Analysis | 10,080 | $554,477 | $41,984 | $225,316 | $821,778 | $3,556,768 | $3,556,768 | 10,664 | 1,498,561 | 1,848,899 | 10,746 | 3,358,206 | ||||
4. Maintenance | 1,792 | $96,086 | $41,984 | $138,071 | $0 | 8,729 | 548,375 | 362,168 | 910,543 | |||||||
5. Data Management | 2,380 | $149,501 | $149,501 | $0 | 11,417 | 714,665 | 714,665 | |||||||||
6. Quality Assurance | 2,313 | $125,023 | $125,023 | $0 | 21,139 | 1,292,794 | 224,387 | 1,517,181 | ||||||||
7. Supervision | 1,120 | $73,055 | $73,055 | $0 | 10,406 | 703,640 | 703,640 | |||||||||
Totals | 18,030 | $1,017,242 | $83,969 | $307,786 | $1,408,997 | 0 | $0 | $0 | $3,556,768 | $3,556,768 | 63,183 | 5,189,922 | 2,435,454 | 2,220,731 | 9,846,107 | |
Cost Element | Average 2023-2025 Sensors | Average 2023-2025 General Network | ||||||||||||||
Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | |||||||
1. Network Design | 164 | $9,921 | $9,921 | 56,475 | 2,350,179 | 5,262,331 | $7,612,511 | |||||||||
2. Site Installation | 1,952 | $111,801 | $73,829 | $185,629 | 29,011,492 | $29,011,492 | ||||||||||
3. Sampling & Analysis | 0 | $0 | $0 | $0 | 9,756 | 787,872 | 4,279,037 | $5,066,909 | ||||||||
4. Maintenance | 0 | $0 | $0 | $0 | $0 | |||||||||||
5. Data Management | 10,500 | $544,546 | $544,546 | 175,278 | 9,751,004 | $9,751,004 | ||||||||||
6. Quality Assurance | 0 | $0 | $0 | 642,470 | $642,470 | |||||||||||
7. Supervision | 13,500 | $906,363 | $906,363 | $0 | ||||||||||||
Totals | 26,117 | $1,572,631 | $0 | $73,829 | $1,646,459 | 241,509 | $12,889,055 | $4,279,037 | $34,916,294 | $52,084,385 | ||||||
Cost Element | Grand Total Average 2023-2025 | |||||||||||||||
Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | ||||||||||||
1. Network Design | 59,321 | 2,556,442 | $0 | $5,262,331 | $7,818,773 | |||||||||||
2. Site Installation | 14,270 | 1,266,843 | $0 | $42,367,662 | $43,634,505 | |||||||||||
3. Sampling & Analysis | 289,930 | 32,858,480 | $9,343,891 | $8,163,902 | $50,366,272 | |||||||||||
4. Maintenance | 196,526 | 13,895,671 | $4,132,094 | $0 | $18,027,765 | |||||||||||
5. Data Management | 450,641 | 29,167,886 | $0 | $0 | $29,167,886 | |||||||||||
6. Quality Assurance | 254,802 | 18,377,803 | $224,387 | $653,219 | $19,255,408 | |||||||||||
7. Supervision | 184,477 | 13,007,834 | $0 | $0 | $13,007,834 | |||||||||||
Totals | 1,449,968 | $111,130,958 | $13,700,371 | $56,447,115 | $181,278,444 | |||||||||||
Table 1. Grand Total Average 2023-2025 Renewal for Labor Hours & Costs | ||||||||
Cost Element | Labor Hours | Labor Costs | Non-labor O & M | Equipment Contract | Total Cost | |||
1. Network Design | 59,321 | $2,556,442 | $0 | $5,262,331 | $7,818,773 | $15,217 | ||
2. Site Installation | 14,270 | $1,266,843 | $0 | $42,367,662 | $43,634,505 | $7,541 | ||
3. Sampling & Analysis | 289,930 | $32,858,480 | $9,343,891 | $8,163,902 | $50,366,272 | $195,586 | ||
4. Maintenance | 196,526 | $13,895,671 | $4,132,094 | $0 | $18,027,765 | $82,712 | ||
5. Data Management | 450,641 | $29,167,886 | $0 | $0 | $29,167,886 | $173,618 | ||
6. Quality Assurance | 254,802 | $18,377,803 | $224,387 | $653,219 | $19,255,408 | $109,392 | ||
7. Supervision | 184,477 | $13,007,834 | $0 | $0 | $13,007,834 | $77,428 | ||
Totals | 1,449,968 | $111,130,958 | $13,700,371 | $56,447,115 | $181,278,444 | $661,494 | 8630.76405684754 |
File Type | application/vnd.openxmlformats-officedocument.spreadsheetml.sheet |