FERC-725A, Mandatory
Reliability Standards for the Bulk-Power System (Final Rule in
Docket No.RM20-16-000)
Revision of a currently approved collection
No
Regular
03/03/2022
Requested
Previously Approved
36 Months From Approved
11/30/2024
4,158
3,420
1,474,398
1,456,686
156,953
156,953
This is a Final Rule in Docket No.
RM20-16-000 (RIN 1902-AF84). Due to ROCIS restrictions the
information on the NOPR is provided below in the 60 day notice
metadata fields and information on the Final Rule is provided in
the 30 day notice metadata fields. On December 16, 2021 the
Commission issued the final rule RM20-16-000 (Managing Transmission
Line Ratings). The portions of the final rule that pertain to
FERC-725A affect the estimated burdens ― but not the Requirements
themselves ― for Requirements 2, 3, and 6 of Reliability Standard
FAC-008-05 (Facility Ratings) developed by the North American
Electric Reliability Corporation (NERC), and most recently revised
by Letter Order issued on April 7, 2021 in Docket No. RD21-4-000.
Reliability Standard FAC-008-5 sets forth requirements to ensure
that transmission line ratings used in operations are determined on
a technically sound basis. The final rule clarifies that
transmission owners, not transmission providers, are responsible
for calculating transmission line ratings. This responsibility is
codified in the NERC Reliability Standards, as well as in
foundational documents for RTOs and ISOs. Nothing in the final rule
changes that responsibility. The final rule will result in
increased, one-time information collection burdens by requiring:
(1) review and update of facility ratings methodology under
Requirements 2 and 3 of Reliability Standard FAC-008-5; and (2)
determination of facility ratings consistent with the updated
methodology in accordance with Requirement 6 of Reliability
Standard FAC-008-5.
There is an increase of burden
due to the Final Rule in Docket No. RM20-16-000. This rule will
require respondents to review and update their facility ratings and
methodology along with determining new transmission line
ratings.
$8,279
No
No
No
No
No
No
No
Jean Sonneman 202 785-6577
jean_sonneman@blm.gov
No
On behalf of this Federal agency, I certify that
the collection of information encompassed by this request complies
with 5 CFR 1320.9 and the related provisions of 5 CFR
1320.8(b)(3).
The following is a summary of the topics, regarding
the proposed collection of information, that the certification
covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a
benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control
number;
If you are unable to certify compliance with any of
these provisions, identify the item by leaving the box unchecked
and explain the reason in the Supporting Statement.