NESHAP for Miscellaneous Organic Chemical Manufacturing (40 CFR part 63, subpart FFFF) (Renewal)

ICR 201905-2060-014

OMB: 2060-0533

Federal Form Document

Forms and Documents
Document
Name
Status
Supplementary Document
2019-05-20
Supporting Statement A
2019-05-20
ICR Details
2060-0533 201905-2060-014
Active 201603-2060-007
EPA/OAR 1969.07
NESHAP for Miscellaneous Organic Chemical Manufacturing (40 CFR part 63, subpart FFFF) (Renewal)
Extension without change of a currently approved collection   No
Regular
Approved without change 11/25/2019
Retrieve Notice of Action (NOA) 05/28/2019
In accordance with 5 CFR 1320, the information collection is approved for three years.
  Inventory as of this Action Requested Previously Approved
11/30/2022 36 Months From Approved 11/30/2019
1,281 0 1,711
327,000 0 436,000
4,310,000 0 5,750,000

The National Emission Standards for Hazardous Air Pollutants (NESHAP) for Miscellaneous Organic Chemical Manufacturing (40 CFR Part 63, Subpart FFFF) were proposed on April 4, 2002, and promulgated on July 14, 2006. These regulations apply to both existing facilities and new facilities that manufacture a miscellaneous organic chemical and that are located at, or are part of, major sources of hazardous air pollutant (HAP) emissions. New facilities include those that commenced construction, modification or reconstruction after the date of proposal. This information is being collected to assure compliance with 40 CFR Part 63, Subpart FFFF. In general, all NESHAP standards require initial notifications, performance tests, and periodic reports by the owners/operators of the affected facilities. They are also required to maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. These notifications, reports, and records are essential in determining compliance, and are required of all affected facilities subject to NESHAP.

US Code: 42 USC 7401 et seq Name of Law: Clean Air Act
  
None

Not associated with rulemaking

  83 FR 24785 05/30/2018
84 FR 23789 05/23/2019
No

1
IC Title Form No. Form Name
NESHAP for Miscellaneous Organic Chemical Manufacturing (40 CFR Part 63, subpart FFFF) (Renewal)

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 1,281 1,711 0 0 -430 0
Annual Time Burden (Hours) 327,000 436,000 0 0 -109,000 0
Annual Cost Burden (Dollars) 4,310,000 5,750,000 0 0 -1,440,000 0
No
No
There is an adjustment decrease in the total estimated burden as currently identified in the OMB Inventory of Approved Burdens; this decrease is not due to any program changes. The decrease in burden is due to more accurate estimates of existing sources based on information gathered by EPA and confirmed by industry. The decrease in the number of respondents also results in a decrease in responses and operation and maintenance costs.

$308,000
No
    No
    No
No
No
No
Uncollected
Patrick Yellin 202 564-2970

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
05/28/2019