FERC-505, (Instant Final Rule in RM19-13) Small Hydropower Projects and Conduit Facilities including License/Relicense, Exemption, and Qualifying Conduit Facility Determination
ICR 201902-1902-009
OMB: 1902-0115
Federal Form Document
⚠️ Notice: This information collection may be outdated. More recent filings for OMB 1902-0115 can be found here:
FERC-505, (Instant Final Rule
in RM19-13) Small Hydropower Projects and Conduit Facilities
including License/Relicense, Exemption, and Qualifying Conduit
Facility Determination
In accordance
with 5 CFR 1320, the information collection is approved for three
years.
Inventory as of this Action
Requested
Previously Approved
05/31/2022
36 Months From Approved
02/28/2022
319
0
320
24,435
0
24,465
0
0
0
FERC-505 is an application for a small
hydropower project license or relicense, exemption, or
determination of a qualifying conduit hydropower facility.
Qualifying Conduit Hydropower Facilities The Hydropower Regulatory
Efficiency Act of 2013 amended section 30 of the FPA, which created
a subset of conduit exemptions, called “qualifying conduit
hydropower facilities,” which are not required to be licensed under
Part I of the FPA. Section 30 includes the following criteria to
determine whether a facility qualifies as a qualifying conduit
hydropower facility: • the facility would be constructed, operated,
or maintained for the generation of electric power using only the
hydroelectric potential of a non-federally owned conduit; • the
facility would have a total installed capacity that does not exceed
five megawatts (MW); and • the facility is not licensed under, or
exempted from, the license requirements in Part I of the FPA on or
before the date of enactment of the Hydropower Efficiency Act (i.e.
August 9, 2013). To obtain a determination that a project is a
qualifying conduit hydropower facility, an entity must file with
the Commission a notice of its intent to construct the facility
that demonstrates the facility meets the qualifying criteria. The
notice of intent is used by the Commission to determine whether an
entity meets the criteria of a qualifying conduit hydropower
facility. If the Commission did not collect the data from the
notice, then there would not be a qualifying conduit hydropower
facility program, as the Commission would have no way of
determining whether an entity meets the relevant criteria.
Therefore, an entity that may be eligible as a qualifying conduit
hydropower facility, and thus eligible to operate without
Commission regulation, would have to obtain a license or exemption
from the Commission in order to operate. A separate entity may
contest whether a facility meets the qualifying criteria by filing
with the Commission a comment, within the comment period,
contesting the facility’s qualifying status. A comment in
opposition to the notice of intent provides the public with an
opportunity to contest whether a facility meets the statutory
requirements.
The Commission is conforming
its regulations to the Water Infrastructure Act. The revision
increasing the installed capacity for qualifying conduit hydropower
facilities will cause entities with qualifying conduit applications
to incur less burden than before the Act, because more facilities
may be considered qualifying and thus eligible to operate without a
license or an exemption. Overall, Commission staff estimates a
reduction of one response and 30 hours of burden annually.
$1,405,901
No
No
No
No
No
No
Uncollected
Haley McLoud 202
502-8807
No
On behalf of this Federal agency, I certify that
the collection of information encompassed by this request complies
with 5 CFR 1320.9 and the related provisions of 5 CFR
1320.8(b)(3).
The following is a summary of the topics, regarding
the proposed collection of information, that the certification
covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a
benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control
number;
If you are unable to certify compliance with any of
these provisions, identify the item by leaving the box unchecked
and explain the reason in the Supporting Statement.