IC18-7 30-day Notice

725L_IC18-7_30day_20180411-3026.docx

FERC-725L (Mandatory Reliability Standards for the Bulk-Power System: MOD Reliability Standards)

IC18-7 30-day Notice

OMB: 1902-0261

Document [docx]
Download: docx | pdf

UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION


[Docket No. IC18-7-000]


COMMISSION INFORMATION COLLECTION ACTIVITIES (FERC-725L); COMMENT REQUEST


(April 11, 2018)


AGENCY: Federal Energy Regulatory Commission.

ACTION: Comment request.

SUMMARY: In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is submitting the FERC-725L (Mandatory Reliability Standards for the Bulk-Power System: MOD Reliability Standards) to the Office of Management and Budget (OMB) for review of the information collection requirements. Any interested person may file comments directly with OMB and should address a copy of those comments to the Commission as explained below. The Commission previously issued a Notice in the Federal Register requesting public comments. The Commission received no comments on the FERC-725L and is making this notation in its submittal to OMB.

DATES: Comments on the collection of information are due by [INSERT DAte 30 days after DATE OF publication IN THE Federal Register].

ADDRESSES: Comments filed with OMB, identified by the OMB Control No. 1902-0261, should be sent via email to the Office of Information and Regulatory Affairs: oira_submission@omb.gov. Attention: Federal Energy Regulatory Commission Desk Officer. The Desk Officer may also be reached via telephone at 202-395-8528.

A copy of the comments should also be sent to the Commission, in Docket No. IC18-7-000, by either of the following methods:

  • eFiling at Commission’s Web Site: http://www.ferc.gov/docs-filing/efiling.asp.

  • Mail/Hand Delivery/Courier: Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street, NE, Washington, DC 20426.

Instructions: All submissions must be formatted and filed in accordance with submission guidelines at: http://www.ferc.gov/help/submission-guide.asp. For user assistance contact FERC Online Support by e-mail at ferconlinesupport@ferc.gov, or by phone at: (866) 208-3676 (toll-free), or (202) 502-8659 for TTY.

Docket: Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at http://www.ferc.gov/docs-filing/docs-filing.asp.

FOR FURTHER INFORMATION: Ellen Brown may be reached by e-mail at DataClearance@FERC.gov, by telephone at (202) 502-8663, and by fax at (202) 273-0873.

SUPPLEMENTARY INFORMATION:

Title: FERC-725L, Mandatory Reliability Standards for the Bulk-Power System: MOD Reliability Standards

OMB Control No.: 1902-0261

Type of Request: Three-year extension of the FERC-725L information collection requirements with no changes to the reporting requirements.

Abstract: MOD Reliability Standards ensure that generators remain in operation during specified voltage and frequency excursions, properly coordinate protective relays and generator voltage regulator controls, and ensure that generator models accurately reflect the generator’s capabilities and equipment performance.

On 5/30/2013, NERC filed a petition explaining that the reliability of the Bulk-Power System benefits from “good quality simulation models of power system equipment1,” and that “model validation ensures the proper performance of the control systems and validates the computer models used for stability analysis.” NERC further stated that the Reliability Standards will enhance reliability because the tests performed to obtain model data may reveal latent defects that could cause “inappropriate unit response during system disturbances1”. Subsequently, on 3/20/20141, the Commission approved Reliability Standards MOD-025-2, MOD-026-1, and MOD-027-1. These Standards were intended to address generator verifications needed to support Bulk-Power System reliability that would also ensure that accurate data is verified and made available for planning simulations.2

On 5/1/20143, the Commission approved Reliability Standards MOD-032-1 and MOD-033-2. These Standards were to address “system-level modeling data and validation requirements necessary for developing planning models and the Interconnection-wide cases that are integral to analyzing the reliability of the Bulk-Power System”.

MOD-025-2, MOD-026-1, MOD-027-1, MOD-032-1 and MOD-033-2 are all currently approved within the FERC-725L information collection. The reporting requirements associated with each standard will not change as a result of this extension request.

Type of Respondents: NERC-registered entities including generator owners, transmission planners, planning authorities, balancing authorities, resource planners, transmission service providers, reliability coordinators, and transmission operators4.

Estimate of Annual Burden5: The Commission estimates the annual public reporting burden6 and cost for the information collection as:

MOD-025-2 (Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability)


Number of Respondents
(1)

Annual Number of Responses per Respondent

(2)

Total Number of Responses (1)*(2)=(3)

Average Burden & Cost Per Response

(4)

Total Annual Burden Hours & Total Annual Cost

(3)*(4)=(5)

Cost per Respondent

($)

(5)÷(1)

Attachment 2

933

(GO)


1

933

6 hrs.;

$448.927

5,598 hrs.;

$418,842

$448.92


Evidence Retention

933

(GO)

1

933

1 hr.;

$32.748

933 hrs.;

$30,546

$32.74

TOTAL


6,531 hrs.;

$449,388



MOD-026-1 (Verification of Models and Data for Generator Excitation Control System or Plant Volt/Variance Control Functions)


Number of Respondents
(1)

Annual Number of Responses per Respondent

(2)

Total Number of Responses (1)*(2)=(3)

Average Burden & Cost Per Response

(4)

Total Annual Burden Hours & Total Annual Cost

(3)*(4)=(5)

Cost per Respondent

($)

(5)÷(1)

Instructions for obtaining excitation control system or plant voltage/variance control function model

185

(TP)

1

185

8 hrs.;

$598.565

1,480 hrs.;

$110,734

$598.56

Documentation on generator verification

466

(GO)


1

466

8 hrs.;

$598.565

3,728 hrs.;

$278,929

$598.56


Evidence Retention

651

(GO and TOP)

1

651

1 hr.;

$32.746

651 hrs.;

$21,314

$32.74

TOTAL


5,859 hrs.;

$410,977



MOD-027-1 (Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions)


Number of Respondents
(1)

Annual Number of Responses per Respondent

(2)

Total Number of Responses (1)*(2)=(3)

Average Burden & Cost Per Response

(4)

Total Annual Burden Hours & Total Annual Cost

(3)*(4)=(5)

Cost per Respondent

($)

(5)÷(1)

Instructions for obtaining excitation control system or plant voltage/variance control function model

185

(TP)

1

185

8 hrs.;

$598.565

1,480 hrs.;

$110,734

$598.56

Documentation on generator verification

466

(GO)


1

466

8 hrs.;

$598.565

3,728 hrs.;

$278,929

$598.56


Evidence Retention

651

(GO and TP)

1

651

1 hr.;

$32.746

651 hrs.;

$21,314

$32.74

TOTAL


5,859 hrs.;

$410,977



MOD-032-1 (Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions)


Number of Respondents
(1)

Annual Number of Responses per Respondent

(2)

Total Number of Responses (1)*(2)=(3)

Average Burden & Cost Per Response

(4)

Total Annual Burden Hours & Total Annual Cost

(3)*(4)=(5)

Cost per Respondent

($)

(5)÷(1)

Data Submittal

1,197

(BA, GO, PA, RP, TO, TP, and TSP)


1

1,197

8 hrs.;

$544.969

9,576 hrs.;

$652,317

$544.96


Evidence Retention

1,197

(BA, GO, PA, RP, TO, TP, and TSP)


1

1,197

1 hr.;

$32.746

1,197 hrs.;

$39,190

$32.74

TOTAL


10,773 hrs.;

$691,507



MOD-033-1 (Steady-State and Dynamics System Model Validation)


Number of Respondents
(1)

Annual Number of Responses per Respondent

(2)

Total Number of Responses (1)*(2)=(3)

Average Burden & Cost Per Response

(4)

Total Annual Burden Hours & Total Annual Cost

(3)*(4)=(5)

Cost per Respondent

($)

(5)÷(1)

Data Submittal

188

(RC and TOP)


1

188

8 hrs.;

$544.967

1,504 hrs.;

$102,452

$544.96


Evidence Retention

194

(PA, RC, and TOP)

1

194

1 hr.;

$32.746

194 hrs.;

$6,352

$32.74

TOTAL


1,698 hrs.;

$108,804



The total annual estimated burden and cost for the FERC-725L information collection is 30,720 hours and $2,071,653 respectively.

Comments: Comments are invited on: (1) whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency's estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology.





Kimberly D. Bose,

Secretary.


1 Final Rule in Docket No. RM13-16-000

2 NERC Petition for Approval of Five Proposed Reliability Standards MOD-025-2, MOD-026-1, MOD-027-1, PRC-019-1, and PRC-024-1 submitted to FERC on 5/30/2013.

3 Order in Docket No. RD14-5-000

4 In subsequent portions of this notice, the following acronyms will be used:

PA = Planning Authority, GO = Generator Owner, TP = Transmission Planner, BA = Balancing Authority, RP = Resource Planner, TSP = Transmission Service Provider, RC = Reliability Coordinator, TOP = Transmission Operator.

5 “Burden” is defined as the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information to or for a Federal agency. For further explanation of what is included in the information collection burden, reference 5 Code of Federal Regulations 1320.3.

6 Each of the five MOD standards in the FERC-725L information collection previously contained “one-time” components to their respondent burden. These one-time burden categories consisted primarily of activities related to establishing industry practices and developing data validation procedures tailored toward these reliability standards and their reporting requirements. None of the one-time burdens apply any longer, so they are being removed from the FERC-725L information collection.

7 This wage figure uses the average hourly wage (plus benefits) for electrical engineers (Occupation Code: 17-2071, $68.12/hour) and managers (Occupation Code: 11-0000, $81.52/hour) obtained from the Bureau of Labor Statistics (BLS). The average used the following calculation: [$68.12/hour + $81.52/hour] ÷ 2 = $74.82/hour.

8 The estimate uses the hourly average wage (plus benefits) for file clerks obtained from the Bureau of Labor Statistics: $32.74/hour (BLS Occupation Code: 43-4071).

9 This uses the hourly average wage (plus benefits) for electrical engineers obtained from the Bureau of Labor Statistics: $68.12/hour (BLS Occupation Code: 17-2071).

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
AuthorSYSTEM
File Modified0000-00-00
File Created2021-01-21

© 2024 OMB.report | Privacy Policy