FERC-725N, (Final Rule in RM15-11) Mandatory Reliability Standards: Reliability Standard TPL Reliability Standards

ICR 201609-1902-007

OMB: 1902-0264

Federal Form Document

Forms and Documents
Document
Name
Status
Supplementary Document
2016-10-06
Supporting Statement A
2016-10-05
Supplementary Document
2016-10-05
Supplementary Document
2016-10-05
Supplementary Document
2016-10-05
Supplementary Document
2016-10-03
Supplementary Document
2016-10-03
ICR Details
1902-0264 201609-1902-007
Historical Active 201310-1902-001
FERC FERC-725N
FERC-725N, (Final Rule in RM15-11) Mandatory Reliability Standards: Reliability Standard TPL Reliability Standards
Revision of a currently approved collection   No
Regular
Approved without change 11/28/2016
Retrieve Notice of Action (NOA) 10/06/2016
In accordance with 5 CFR 1320, the information collection is approved for three years. Note that FERC included a one-time burden estimate (42,137 hours) associated with the addition of Reliability Standard TPL-007-1 in this collection that was annualized over the three year approval period. FERC will need to remove this burden from this collection and their inventory after year 3. Similarly there are a number of one time responses that will need to be adjusted. Additionally, the previous terms of clearance will need to be addressed by FERC when Reliability Standards TPL-001-0 through TPL-001-004 are revised: "When FERC considers approval of the next versions of Reliability Standards TPL-001 through TPL-004, and TPL-007, they should consider small entity impacts and potential options for reducing their recordkeeping and reporting burden."
  Inventory as of this Action Requested Previously Approved
11/30/2019 36 Months From Approved 01/31/2017
2,205 0 183
45,020 0 15,471
0 0 0

In this Final Rule in Docket RM15-11, FERC approves Reliability Standard TPL-007-1. Reliability Standard TPL-007-1 establishes requirements for certain entities to assess the vulnerability of their transmission systems to geomagnetic disturbance events (GMDs), which occur when the sun ejects charged particles that interact and cause changes in the earth’s magnetic fields. Entities that do not meet certain performance requirements, based on the results of their vulnerability assessments, must develop a plan to achieve the requirements. NERC submitted the Reliability Standard for Commission approval in response to a FERC directive in Order No. 779. In addition, the Commission directs that NERC develop modifications to the benchmark GMD event definition set forth in Attachment 1 of the approved Reliability Standard so that the definition is not based solely on spatially-averaged data.

US Code: 16 USC 824o Name of Law: Energy Policy Act of 2005
  
None

1902-AF04 Final or interim final rulemaking 81 FR 67120 09/30/2016

No

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 2,205 183 0 2,022 0 0
Annual Time Burden (Hours) 45,020 15,471 0 29,549 0 0
Annual Cost Burden (Dollars) 0 0 0 0 0 0
Yes
Miscellaneous Actions
No
The Commission approves Reliability Standard TPL-007-1 and the associated implementation plan, violation severity levels, and violation risk factors, as discussed above. Reliability Standard TPL-007-1 will impose new requirements for transmission planners, planning coordinators, transmission owners, and generator owners. 1. Reliability Standard TPL-007-1, Requirement R1 requires planning coordinators, in conjunction with transmission planner, to identify the responsibilities of the planning coordinator and transmission planner in the planning coordinator’s planning area for maintaining models and performing the study or studies needed to complete GMD Vulnerability Assessments. 2. Requirements R2, R3, R4, R5, and R7 refer to the “responsible entity, as determined by Requirement R1,” when identifying which applicable planning coordinators or transmission planners are responsible for maintaining models and performing the necessary study or studies. 3. Requirement R2 requires that the responsible entities maintain models for performing the studies needed to complete GMD Vulnerability Assessments, as required in Requirement R4. 4. Requirement R3 requires responsible entities to have criteria for acceptable system steady state voltage performance during a benchmark GMD event. 5. Requirement R4 requires responsible entities to complete a GMD Vulnerability Assessment of the near-term transmission planning horizon once every 60 calendar months. 6. Requirement R5 requires responsible entities to provide GIC flow information to transmission owners and generator owners that own an applicable bulk electric system power transformer in the planning area. This information is necessary for applicable transmission owners and generator owners to conduct the thermal impact assessments required by Requirement R6. 7. Requirement R6 requires applicable transmission owners and generator owners to conduct thermal impact assessments where the maximum effective GIC value provided in Requirement R5, Part 5.1 is 75 A/phase or greater. 8. Requirement R7 requires responsible entities to develop a corrective action plan when its GMD Vulnerability Assessment indicates that its system does not meet the performance requirements of Table 1 – Steady State Planning Events. The corrective action plan must address how the performance requirements will be met, must list the specific deficiencies and associated actions that are necessary to achieve performance, and must set forth a timetable for completion.

$5,481
No
No
No
No
No
Uncollected
Regis Binder 301 665-1601 regis.binder@ferc.gov

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
10/06/2016


© 2024 OMB.report | Privacy Policy