OMB Control No. 2060-0637
Expires [PENDING]
RFS2 Engineering Review Template
Executive Summary
Compliance Division
Office of Transportation and Air Quality
U.S. Environmental Protection Agency
"The public reporting and recordkeeping burden for this collection of information is estimated to average 24 hours per response. Send comments on the Agency's need for this information, the accuracy of the provided burden estimates, and any suggested methods for minimizing respondent burden, including through the use of automated collection techniques to the Director, Collection Strategies Division, U.S. Environmental Protection Agency (2822T), 1200 Pennsylvania Ave., NW, Washington, D.C. 20460. Include the OMB control number in any correspondence. Do not send the completed RFS2 Engineering Review to this address."
RFS2 Engineering Review Template
Executive Summary
Facility Name:
Facility Address:
Date of on-site review:
Date of Report:
80.1450(b)(2): An independent third-party engineering review and written report and verification of the information provided pursuant to paragraph (b)(1) of this section. The report and verification shall be based upon a site visit and review of relevant documents and shall separately identify each item required by paragraph (b)(1) of this section, describe how the independent third-party evaluated the accuracy of the information provided, state whether the independent third-party agrees with the information provided, and identify any exceptions between the independent third-party's findings and the information provided.
Summary:
Professional engineer’s affirmation of third-party independence per 80.1450(b)(2):
Name of third-party independent professional engineer:
Professional engineer’s signature and stamp (if applicable):
A description of the types of renewable fuels or ethanol that the producer intends to produce at the facility and that the facility is capable of producing without significant modifications to the existing facility:
A list of all the feedstocks the facility is capable of utilizing without significant modification to the existing facility:
A description of the facility's renewable fuel or ethanol production processes:
The type of co-products produced with each type of renewable fuel or ethanol:
Verification of the attached process heat fuel supply plan (See 1450(b)(1)(A)). A process heat supply plan should include:
( 1 )
Each type of process heat fuel used at the facility.
( 2 )
Name and address of the company supplying each process heat fuel to
the renewable fuel or foreign ethanol facility.
Verification
of attached records supporting the Permitted Capacity, Actual Peak
Capacity, and/or Baseline Volume as defined in 80.1401.
Please note that a baseline volume is only required for
facilities that have registered for the 20% greenhouse gas
exemption. The baseline volume should be based on either permit or
production records that meet the requirements of permitted
capacity/actual peak capacity as defined in 80.1401. To use a
permit for permitted capacity, the allowable volume of renewable
fuel must be listed in the permit. Please supply all pages of the
permit as an attachment and state
in this section the page number of the listed volume.
If no such permit exists, please provide production records for the
years described in the definition of actual peak capacity provided
in 80.1401.
For
all facilities not claiming the 20% exemption, only a permitted
capacity or actual peak capacity is required. If utilizing a permit
to establish this volume, supply all pages as an attachment and state
the page number of the listed volume.
If no permit exists, please supply five years of production records,
including the year being utilized in the registration, in support of
actual peak capacity. If five years of records are not available,
provide as many records as the facility has on file.
Verification
of attached Separated Yard, Food, and Municipal Solid Waste Plans
per 80.1450(b)(1)(vii)
and 80.1450(b)(1)(viii)/
If not applicable, write N/A.
For each of the applicable plans, please provide the
name and address of all waste feedstock providers. Additionally,
the EPA requires a plan for separated food waste and separated yard
waste that documents: 1) how the waste will be collected, 2) how the
waste is kept separate from other waste materials and only consists
of either food or yard waste and 3) (food waste only) how the
cellulosic and non-cellulosic portions of the waste will be
quantified. For Municipal Solid Waste, please refer to the
requirements stated in 80.1450(b)(1)(viii).
(Note: Companies who have
registered with the feedstock of either biogenic waste
oils/fats/greases or non-cellulosic portions of separated food waste
need to submit a separated food waste plan.)
Verification of attached documentation outlined in 80.1450(b)(1)(ix) and 80.1450(b)(1)(x) for facilities using Grain Sorghum, Arundo donax, or Pennisetum purpureum feedstocks. If not applicable, write N/A.
RIN generation information for RIN generating producers (three year updates only. For more information, please review the regulation below). If not applicable, write N/A.
Per 80.1450(d)(iii): In addition to conducting the engineering review and written report and verification required by paragraph (b)(2) of this section, the updated independent third-party engineering review shall include a detailed review of the renewable fuel producer's calculations used to determine VRIN of a representative sample of batches of each type of renewable fuel produced since the last registration. The representative sample shall be selected in accordance with the sample size guidelines set forth at § 80.127.
Outline of attachments:
Copy of CDX OTAQREG generated Company Update Request (CR-####)
Professional Engineer credentials, resume, and experience
Process Heat Fuel Supply Plan
Affidavit from the biogas supplier
Separated Food Waste Plan
Air permits supporting Permitted Capacity
Calculations converting to gallons/year
Production records supporting Actual Peak Capacity
Calculations converting to gallons/year
Three-year engineering review update RIN verification calculations
Any additional documents (e.g., pictures from on-site review)
EPA-420-B-13-044
File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document |
File Title | RFS2 Engineering Review Template: Executive Summary (EPA-420-B-13-044, September 2013) |
Subject | This document is the RFS2 engineering review template addressing an independent third-party engineering review and written repor |
File Modified | 0000-00-00 |
File Created | 2021-01-29 |