CHAPTER 12. PROJECT CONSTRUCTION AND COMPLETION
Section 6. Contract Settlement
12-71. GENERAL. The PHA, upon receipt of written authorization from the
Area Office, shall notify the contractor to prepare for settlement.
The PHA shall also advise the contractor to submit the
documentation identified in this section for PHA and Area Office
approval prior to settlement.
12-72. SETTLEMENT DOCUMENTS. The contractor is responsible for preparing
and submitting the following to the PHA:
a. Conventional and Turnkey Projects. The following documents
are required for all projects, whether developed under the
conventional or turnkey method.
(1) a certificate of occupancy issued by the responsible
local agency for each building;
(2) two notarized originals of the contractor's release
and certification which indicates:
(a) the work was completed in accordance with the
construction documents (including change orders)
except any minor items identified on the
PHA architect's final inspection report;
(b) the total amount due the contractor and a
separately stated amount for each unsettled
claim against the PHA;
(c) the PHA is released of all claims, other than
those stated in the contractor's release; and
(d) wages paid to laborers or mechanics were
consistent with the wage rate requirements
of the contract, and there are no
outstanding claims for unpaid wages.
(3) an assignment of all guarantees and warranties to the PHA.
b. Conventional Projects. In addition to the documents
identified in paragraph a, the general contractor shall submit
a "final" Periodical Estimate for Partial Payment (Form
HUD 51001).
________________________________________________________________________
12-55 10/80
7417.1 REV-1
________________________________________________________________________
c. Turnkey Projects. In addition to the documents identified
in subparagraph a, the turnkey developer Shall submit the
following:
(1) the as-built drawings (paragraph 12-23);
(2) a copy of the receipt for real property taxes paid by
the developer during the construction period;
(3) the title binder, evidencing that good and marketable
title will be conveyed to the PHA; and
(4) a copy of the proposed deed.
12-73. PHA CONTRACT SETTLEMENT REPORT. The PHA in consultation with
the PHA architect and attorney shall review the contractor's
settlement documents and prepare a report on its findings.
a. PHA Review. The PHA shall review the construction documents,
the PHA records, and completed work, to determine whether
the contractor's statements concerning compliance with the
construction documents (including change orders) and identified
work to be completed are accurate.
b. PHA Report. Upon completing its review, the PHA shall prepare
a contract settlement report indicating PHA agreement
with the contractor's statements. The PHA report shall
also identify:
(1) the current status of any incomplete or seasonal work;
(2) any outstanding disputes or claims;
(3) any PHA exceptions to the contractor's settlement
documents; and
(4) the PHA attorney statement as to the adequacy of the
proposed deed and title information (turnkey projects
only).
c. Certificate of Completion. The PHA or PHA architect shall
prepare the proposed certificate of completion in the form
prescribed by the Area Office.
________________________________________________________________________
10/80 12-56
7417.1 REV-1
________________________________________________________________________
d. PHA Submission The PHA shall submit a copy of the following
to the Area Office for approval:
(1) all settlement documents identified in paragraph 12-72
for the applicable development method;
(2) the PHA contract settlement report; and
(3) the proposed certificate of completion.
12-74. AREA OFFICE REVIEW. The AE Chief is responsible for coordinating
the review and recommending approval of the certificate of
completion.
a. Standard Processing Time. The standard processing time (SPT)
is the number of calendar days from receipt of the settlement
documents and certificate of completion by the PCR Unit and
a decision by the Housing Director. The SPT for Area Office
review and approval (or disapproval) of the certificate of
completion is ten (10) calendar days.
b. AE Branch. The AE Chief in order to recommend approval must
determine that:
(1) all work has been completed in accordance with the
construction documents;
(2) the proposed certificate of completion is acceptable;
and
(3) the amount to be withheld from the contractor is
sufficient to complete any items on the PHA architect's
punch list, including seasonal work.
c. Legal Division. The Area Counsel, in order to recommend
approval, must determine and advise the AE Chief that:
(1) the contractor's release and certification is consistent
with the terms of the contract;
(2) for turnkey projects, the proposed deed and title
information is acceptable and are consistent with
the contract of sale; and
(3) for turnkey projects, the scheduled closing date.
________________________________________________________________________
12-57 10/80
7417.1 REV-1
________________________________________________________________________
d. Labor Relations Staff. The Labor Relations Staff,
in order to recommend approval, must determine and advise
the AE Chief that the contractor's wage certification is
acceptable.
e. PHA Notification. The AE Chief, upon determining that the
contract settlement documents are in order, must sign the
certificate of completion and submit it for the
Housing Director's signature. The original shall be
promptly sent to the PHA. If applicable, the PHA and
turnkey developer shall be advised of the scheduled closing
date.
12-75. PAYMENT OF CONTRACTOR. The PHA upon receipt of the approved
certificate of completion is authorized to make payment to the
contractor of the amounts approved by the Area Office. For
turnkey projects, payment shall be made at the closing of the
sale.
a. Contract Payment. The PHA payment to the contractor shall
be the amount specified in the certificate of completion
approved by the Area Office and shall not include any amount
to be retained for:
(1) warranty retainage or disputed items; and
(2) incomplete work, such as punch list or seasonal
items.
b. Final Payments. The PHA is not authorized to make final
payment of any amounts withheld without prior Area Office
approval. When punch list or seasonal work items are
completed, the PHA shall submit a revised certificate of
completion for Area Office approval.
12-76. TURNKEY CLOSING PROCEDURES. The closing for turnkey projects
shall take place in accordance with the following requirements:
a. Title Insurance. The PHA must obtain a title insurance
policy, or other title guarantee acceptable to the Area
Office, at closing. The title policy shall guarantee
that title is good and marketable and is free of any
mortgage, lease, lien or other encumbrances, such as use
or building restrictions, zoning ordinances, easements
or rights-of way which would affect the value or proposed
use of the site. In those instances where several
contiguous parcels are being acquired, a blanket title
insurance policy should be obtained for the entire site.
________________________________________________________________________
10/80 12-58
7417.1 REV-1
________________________________________________________________________
b. Curing Title Defects. The PHA attorney shall ensure that
any outstanding mortgages, leases, or liens have been cleared.
c. Settlement Record. The closing details for each transaction
shall be recorded in triplicate on the Real Estate Settlement
Record (Form HUD 51975) or a similar locally used and accepted
settlement record.
d. Deed Recordation. The PHA shall ensure that the deed is
promptly recorded by its attorney.
e. Declaration of Trust. The PHA shall execute and record the
Declaration of Trust (Form HUD 52190) prepared by the Area
Counsel. A copy of the executed Declaration of Trust shall
be returned to the Area Office as soon as it has been
recorded.