30 CFR § 77.1101 - Escape and Evacuation Plans (Pertains to surface coal mines, surface
facilities and surface work areas of underground coal mines.)
A. Justification
1. Explain the circumstances that make the collection of information necessary. Identify any legal or
administrative requirements that necessitate the collection. Attach a copy of the appropriate section of
each statute and regulation mandating or authorizing the collection of information.

Section 101(a) of the Federal Mine Safety and Health Act of 1977 (Mine Act) as
amended, provides that "the Secretary shall by rule in accordance with procedures set
forth in this section and in accordance with section 553 of Title 5, United States Code,
develop, promulgate, and revise as may be appropriate, improved mandatory health or
safety standards for the protection of life and prevention of life and prevention of
injuries in coal or other mines." 30 U.S.C. § 811(a). Additionally, section 103(h) of the
Mine Act requires mine operators to establish and maintain "such records, make such
reports, and provide such information, as the Secretary . . . may reasonably require from
time to time to enable [her] to perform [her] functions under this Act." 30 U.S.C.
§ 813(h).
30 C.F.R. § 77.1101(a) requires operators of surface coal mines, including surface
facilities, and surface work areas of underground coal mines to establish and keep
current a specific escape and evacuation plan to be followed in the event of a fire.
30 C.F.R. § 77.1101(b) requires that all employees be instructed in current escape and
evacuation plans, fire alarm signals, and applicable procedures to be followed in case of
fire. The training and record keeping requirements associated with this standard are
addressed under OMB No. 1219-0009 (Training Plan Regulations).
30 C.F.R. § 77.1101(c) requires that escape and evacuation plans include the designation
and proper maintenance of adequate means for exiting areas where persons are
required to work or travel including buildings, equipment, and in areas where persons
normally congregate during the work shift.
2. Indicate how, by whom, and for what purpose the information is to be used. Except for new
collections, indicate the actual use the agency has made of the information received from the current
collection.

October 2009
1

1219-0051
The escape and evacuation plan is prepared by the mine operator and is used by mines,
MSHA, and persons involved in rescue and recovery. The plan is used to instruct
employees in the proper methods of exiting structures in the event of a fire. MSHA
inspection personnel use the plan to determine compliance with the standard requiring
a means of escape and evacuation be established and the requirement that employees
be instructed in the procedures to follow should a fire occur.
3. Describe whether, and to what extent, the collection of information involves the use of automated,
electronic, mechanical, or other technological collection techniques or other forms of information
technology, e.g., permitting electronic submission of responses, and the basis for the decision for
adopting this means of collection. Also describe any consideration of using information technology to
reduce burden.

No improved information technology has been identified that would reduce the
burden; however, in order to comply with the Government Paperwork Elimination Act,
Pub. L. No. 105-277 (1998), mine operators may develop Escape and Evacuation plans
using computer generated CAD drawings and retain the records in whatever method
they chose, which may include utilizing computer technology.
4. Describe efforts to identify duplication. Show specifically why any similar information already
available cannot be used or modified for use for the purpose(s) described in Item 2 above.

No similar or duplicate information exists. Escape and evacuation plans are developed
for individual mines and are unique to the mine. Where equipment manufacturers'
recommendations, engineering construction drawings, architectural design drawings
(which reflect building code requirements such as sprinkler systems, exit signs, fire
alarms, firehose stations, restricted occupancy, etc.) or other similar information exists,
such information may become an essential part of the required plan.
5. If the collection of information impacts small businesses or other small entities, describe the
methods used to minimize burden.

This information does not have a significant impact on small businesses or other small
entities. However, MSHA has made available on our web-site various sources of
information, such as “Technical Assistance,” “Best Practices,” and an “Accident
Prevention” site. To assist with compliance, these provide tips and general information
on a number of various topics.
6. Describe the consequence to Federal program or policy activities if the collection is not conducted or
is conducted less frequently, as well as any technical or legal obstacles to reducing burden.

October 2009
2

1219-0051
Persons working at surface installations such as preparation plants, drawoff tunnels,
slopes, and other buildings must be educated on how to safely escape and evacuate
these sites in case of a fire hazard. They must also be familiar with the means of escape.
Reducing the frequency of or eliminating preparation of the mandatory escape and
evacuation plan, prior to commencing operations, or to remove the requirement to
maintain the plan current with mine conditions, would eliminate an essential training
tool and would expose miners to unnecessary confusion and risk of injury or death
should a fire occur in or at their work location. An escape and evacuation plan need be
developed only once for a specific surface coal mine, surface facilities, or surface work
area of an underground coal mine. Therefore a plan, once developed, need only be
revised if new equipment, additional buildings or other significant changes occur.
Changes in mine ownership do not result in a need for developing new surface escape
and evacuation plans except where the new owner makes changes to the mine's surface
facilities or mining equipment.
7. Explain any special circumstances that would cause an information collection to be conducted in a
manner:
!

requiring respondents to report information to the agency more often than quarterly;

!

requiring respondents to prepare a written response to a collection of information in fewer
than 30 days after receipt of it;

!

requiring respondents to submit more than an original and two copies of any document;

!

requiring respondents to retain records, other than health, medical, government contract, grantin-aid, or tax records for more than three years;

!

in connection with a statistical survey, that is not designed to produce valid and reliable results
that can be generalized to the universe of study;

!

requiring the use of a statistical data classification that has not been reviewed and approved by
OMB;

!

that includes a pledge of confidentiality that is not supported by authority established in
statue or regulation, that is not supported by disclosure and data security policies that are
consistent with the pledge, or which unnecessarily impedes sharing of data with other
agencies for compatible confidential use; or

!

requiring respondents to submit proprietary trade secret, or other confidential information
unless the agency can demonstrate that it has instituted procedures to protect the information's
confidentiality to the extent permitted by law.

October 2009
3

1219-0051
While there is no specific regulatory requirement that escape and evacuation plans be
kept for more than three years, 30 C.F.R. § 77.1101 requires coal mine operators to
establish and keep current such plan and to instruct all employees on the current escape
and evacuation plans, fire alarm signals, and applicable procedures to be followed in
case of fire. This collection of information is otherwise consistent with the guidelines in
5 C.F.R. § 1320.5, and does not contain any requirements for respondents to report more
than quarterly.
8. If applicable, provide a copy and identify the date and page number of publication in the Federal
Register of the agency's notice, required by 5 CFR 1320.8(d), soliciting comments on the information
collection prior to submission to OMB. Summarize public comments received in response to that
notice and describe actions taken by the agency in response to the comments. Specifically address
comments received on cost and hour burden.
Describe efforts to consult with persons outside the agency to obtain their views on the availability of
data, frequency of collection, the clarity of instructions and recordkeeping, disclosure, or reporting
format (if any), and on the data elements to be recorded, disclosed, or reported.
Consultation with representatives of those from whom information is to be obtained or those who
must compile records should occur at least once every 3 years -- even if the collection of information
activity is the same as in prior periods. There may be circumstances that may preclude consultation in
a specific situation. These circumstances should be explained.

MSHA published a 60-day preclearance Federal Register notice on August 12, 2009
(Volume 74, Number 154, pages 40611-40612), soliciting public comments regarding the
extension of this information collection. One favorable comment from the United Mine
Workers of America supporting MSHA’s safety standards was received.
9. Explain any decision to provide any payment or gift to respondents, other than remuneration of
contractors or grantees.

MSHA does not provide payments or gifts to respondents identified by this collection.
10. Describe any assurance of confidentiality provided to respondents and the basis for the assurance
in statute, regulation, or agency policy.

There is no assurance of confidentiality provided to respondents.
11. Provide additional justification for any questions of a sensitive nature, such as sexual behavior and
attitudes, religious beliefs, and other matters that are commonly considered private. This justification
should include the reasons why the agency considers the questions necessary, the specific uses to be
made of the information, the explanation to be given to persons from whom the information is
requested, and any steps to be taken to obtain their consent.

October 2009
4

1219-0051
There are no questions of a sensitive nature.
12. Provide estimates of the hour burden of the collection of information. The statement should:
!

Indicate the number of respondents, frequency of response, annual hour burden, and an
explanation of how the burden was estimated. Unless directed to do so, agencies should not
conduct special surveys to obtain information on which to base hour burden estimates.
Consultation with a sample (fewer than 10) of potential respondents is desirable. If the hour
burden on respondents is expected to vary widely because of differences in activity, size, or
complexity, show the range of estimated hour burden, and explain the reasons for the variance.
Generally, estimates should not include burden hours for customary and usual business
practices.

!

If this request for approval covers more than one form, provide separate hour burden estimates
for each form and aggregate the hour burdens in Item 13 of OMB Form 83-I.

!

Provide estimates of annualized cost to respondents for the hour burdens for collections of
information, identifying and using appropriate wage rate categories. The cost of contracting
out or paying outside parties for information collection activities should not be included here.
Instead, this cost should be included in Item 14.

Salaries used for this response were taken from the U.S. Coal Mine Salaries, Wages, &
Benefits - FY 2007 Survey Results.
In FY 2008, there were approximately 2,379 surface coal mines, surface facilities, and
surface work areas of underground mines affected by this standard. MSHA estimates
that there were approximately 327 new surface coal mines, surface coal facilities, and
surface work areas of underground mines opened during FY 2008. MSHA also
estimates that approximately 1% of existing surface coal mines, surface coal facilities,
and surface work areas of underground mines (24) will need to submit revised plans
during the next three years.
MSHA estimates that it will take a coal mine supervisor earning $64.88 per hour
approximately 4 hours to prepare a new escape and evacuation plan and approximately
2 hours to revise an existing plan.
Hour Burden
327 new plans x 4 hours per plan
24 revised plans x 2 hours per plan
Total Hour Burden

=
=
=

October 2009
5

1,308 hours
48 hours
1,356 hours

1219-0051
Hour Burden Cost
1,356 hours x $64.88 per hour

=

$87,977

MSHA estimates that it will take a clerical person earning $ 22.62 per hour
approximately 1 hour to type and file a new escape and evacuation plan, and
approximately one-half hour (0.5 hour) to type and file a revised plan.
Hour Burden
327 new plans x 1 hour per plan
24 revised plans x 0.5 hour per plan
Total Hour Burden

=
=
=

327 hours
12 hours
339 hours

339 hours x $22.62 per hour

=

$7,668

Total Hour Burden
Total Hour Burden Cost

=
=

1,695 hours
$ 95,645

Hour Burden Cost

13. Provide an estimate of the total annual cost burden to respondents or recordkeepers resulting from
the collection of information. (Do not include the cost of any hour burden shown in Items 12 and 14).
!

The cost estimate should be split into two components: (a) a total capital and start-up cost
component (annualized over its expected useful life); and (b) a total operation and
maintenance and purchase of services component. The estimates should take into account
costs associated with generating, maintaining, and disclosing or providing the information.
Include descriptions of methods used to estimate major cost factors including system and
technology acquisition, expected useful life of capital equipment, the discount rate(s), and the
time period over which costs will be incurred. Capital and start-up costs include, among other
items, preparations for collecting information such as purchasing computers and software;
monitoring, sampling, drilling and testing equipment; and record storage facilities.

!

If cost estimates are expected to vary widely, agencies should present ranges of cost burdens
and explain the reasons for the variance. The cost of purchasing or contracting out information
collection services should be a part of this cost burden estimate. In developing cost burden
estimates, agencies may consult with a sample of respondents (fewer than 10), utilize the 60day pre-OMB submission public comment process and use existing economic or regulatory
impact analysis associated with the rulemaking containing the information collection, as
appropriate.

October 2009
6

1219-0051
!

Generally, estimates should not include purchases of equipment or services, or portions
thereof, made: (1) prior to October 1, 1995, (2) to achieve regulatory compliance with
requirements not associated with the information collection, (3) for reasons other than to
provide information or keep records for the government, or (4) as part of customary and usual
business or private practices.

MSHA does not anticipate that mine operators will incur any costs other than those
described in Item 12.
14. Provide estimates of annualized cost to the Federal government. Also, provide a description of the
method used to estimate cost, which should include quantification of hours, operational expenses
(such as equipment, overhead, printing, and support staff), and any other expense that would not have
been incurred without this collection of information. Agencies also may aggregate cost estimates from
Items 12, 13, and 14 in a single table.

Because the review of escape and evacuation plans is just one aspect of the inspections
required under Section 103(a) of the Mine Act, MSHA believes that this burden is
minimal and has assigned no federal cost burden for this specific information collection.
15. Explain the reasons for any program changes or adjustments reported in Items 13 or 14 of the OMB
Form 83-I.

Respondents: There has been an increase of 3 Respondents (348 to 351). The rise in
Respondents is the result of an increase in the number of new surface coal mines,
surface facilities, and surface work areas of underground mines even though the total
number of such operations declined from 2,407 to 2,379.
Responses: There has been an increase of 3 Responses (348 to 351). This increase is due
to the number of new mines submitting Escape and Evacuation Plans with the
submittal of revised plans remaining unchanged .
Hours: There has been in increase of 15 burden hours (1,680 to 1,695). The hour burden
has remained constant from the last submission to this submission; therefore, the
increase is due to the increase in the number of responses.
Cost: There has been no change in the cost ($0)
16. For collections of information whose results are planned to be published, outline plans for
tabulation and publication. Address any complex analytical techniques that will be used. Provide the
time schedule for the entire project, including beginning and ending dates of the collection of
information, completion of report, publication dates, and other actions. MSHA has no plans to publish
the information obtained through this information collection.

October 2009
7

1219-0051

MSHA has no plans to publish the information obtained through this information
collection.
17. If seeking approval to not display the expiration date for OMB approval of the information
collection, explain the reasons that display would be inappropriate.

MSHA is not seeking approval to either display or not display the expiration date for
OMB approval of this information collection. There are no forms associated with this
collection.
18. Explain each exception to the certification statement identified in Item 19, "Certification for
Paperwork Reduction Act Submissions," of OMB Form 83-I.

There are no certification exceptions identified with this information collection.

October 2009
8

1219-0051
B.

Collection of Information Employing Statistical Methods

The agency should be prepared to justify its decision not to use statistical methods in any case where
such methods might reduce burden or improve accuracy of results. When Item 17 on the Form OMB
83-I is checked "Yes," the following documentation should be included in the Supporting Statement to
the extent that it applies to the methods proposed:
1.
Describe (including a numerical estimate) the potential respondent universe and any sampling
or other respondent selection methods to be used. Data on the number of entities (e.g., establishments,
State and local government units, households, or persons) in the universe covered by the collection
and in the corresponding sample are to be provided in tabular form for the universe as a whole and for
each of the strata in the proposed sample. Indicate expected response rates for the collection as a
whole. If the collection had been conducted previously, include the actual response rate achieved
during the last collection.
2.

Describe the procedures for the collection of information including:
!

Statistical methodology for stratification and sample selection,

!

Estimation procedure,

!

Degree of accuracy needed for the purpose described in the justification,

!

Unusual problems requiring specialized sampling procedures, and

!

Any use of periodic (less frequently than annual) data collection cycles to reduce
burden.

3.
Describe methods to maximize response rates and to deal with issues of non-response. The
accuracy and reliability of information collected must be shown to be adequate for intended uses. For
collections based on sampling, a special justification must be provided for any collection that will not
yield "reliable" data that can be generalized to the universe studied.
4.
Describe any tests of procedures or methods to be undertaken. Testing is encouraged as an
effective means of refining collections of information to minimize burden and improve utility. Tests
must be approved if they call for answers to identical questions from 10 or more respondents. A
proposed test or set of tests may be submitted for approval separately or in combination with the main
collection of information.
5.
Provide the name and telephone number of individuals consulted on statistical aspects of the
design and the name of the agency unit, contractor(s), grantee(s), or other person(s) who will actually
collect and/or analyze the information for the agency.

As statistical analysis is not required by the regulation, questions 1 through 5 do not
apply.

October 2009
9


File Typeapplication/pdf
Authortarr-jane
File Modified2009-10-27
File Created2009-10-27

© 2024 OMB.report | Privacy Policy