2173fr02ATTB

2173fr02ATTB.xls

Reporting Requirements under EPA's Green Power Partnership and Combined Heat and Power Partnership (Renewal)

2173fr02ATTB

OMB: 2060-0578

Document [xlsx]
Download: xlsx | pdf

Overview

B-1
B-2
B-3
B-4
B-5
B-6


Sheet 1: B-1







































Total Hours and Costs























Lgl $ per Hour* Mgr. $ per Hour* Tech. $ per Hour* Cler. $ per Hour* Respon- dent Hours
Capital/ Startup Cost
Number of Respon- dents Frequency of Response
Total Cost/Yr























$114.85 $91.90 $81.44 $38.62 Labor Cost O & M Total Hrs/Yr






















INFORMATION COLLECTION ACTIVITY Cost






















Letter of Intent


































Company and Institutional Partners a


































Review and complete LOI 1.00 1.33 0.67 0.00 3.00 $291.64 $0 $0 32 1 96.0 $9,333






















Submit LOI to EPA and file copy 0.00 0.00 0.00 0.50 0.50 $19.31 $0 $3 32 1 16.0 $714






















SUBTOTAL









112 $10,046






















CHP Project Reporting Forms


































Review form and instructions and complete form (new partners) b 0.00 0.50 0.00 0.00 0.50 $45.95 $0 $0 28 1 14.0 $1,287






















Verify and update spreadsheet (existing partners) c 0.00 1.61 1.33 0.00 2.94 $256.27 $0 $0 200 1 588.0 $51,255






















Submit spreadsheet to EPA electronically and file a copy 0.00 0.00 0.50 0.00 0.50 $40.72 $0 $3 228 1 114.0 $9,968






















SUBTOTAL









716.0 $62,510






















Information Updates and Follow-ups


































Submit contact or profile information updates via Web d 0.00 0.00 0.25 0.00 0.25 $20.36 $0 $0 35 1 8.8 $713






















Clarify LOI or project information via email or telephone interview e 0.00 0.00 0.25 0.00 0.25 $20.36 $0 $0 65 1 16.3 $1,323






















SUBTOTAL









25.0 $2,036






















TOTAL







232f
853.0 $74,592


























































*Labor rates for the company and institutional respondent tables are derived from national hourly labor rates from Bureau of Labor Statistics and consultations with three current CHP partners. Each partner offered a base hourly wage rate for legal, managerial, technical, and clerical occupations. These consultations did not include benefits or overhead. A loaded labor rate to reflect benefits and overhead for the respondent organizations was calculated by applying a 110% factor to the average of the base rates received from the consultations.










































































a Assumed 32 new company/institutional partners in the year 2009, spread evenly among project developers, end-users, consulting engineers, equipment manufacturers, and utilities.


































b Assumed all new end-users, project developers, consulting engineers, and equipment manufacturers (6 each of end users and equip. man.; and 7 each of project developers and consulting engineers) who join in 2009 will fill out a project form. Assumed 33% of the 6 utility partners who join in 2009 (i.e. 2 utilities) will fill out a project form.

















































c All Project developers, end users, ESCOs, consulting engineers, and equipment manufacturers, and 33% of utilities review their project information and provide updates annually. Of the estimated 260 partners at the end of 2008, 200 partners belong to these categories. They will receive a spreadsheet already populated with their project data once a year and will verify and update their project information on this spreadsheet in 2009.

















































d Assumed 15% of new and existing company/institutional partners in the year 2009 (232 projected total partners), will update their information over the CHP website sometime during the calendar year.


































e Assumed 25% of the 32 new company/institutional partners completing their LOI (i.e. 8 partners) will require follow-up. Additionally, 25% of the 228 partners completing CHP project forms or spreadsheets (i.e. 57 partners) will require follow-up in order to correctly complete the form.

















































f The total number of unique respondents submitting information in 2009 is 232, including 200 existing partners who are expected to complete project reporting spreadsheets, 28 new company and institutional partners who will fill out both a LOI and project reporting form, and 4 new company and institutional partners who will fill out only a LOI.


























Sheet 2: B-2
















Total Hours and Costs

Lgl $ per Hour* Mgr. $ per Hour* Tech. $ per Hour* Cler. $ per Hour* Respon- dent Hours
Capital/ Startup Cost
Number of Respon- dents Frequency of Response
Total Cost/Yr

$114.85 $91.90 $81.44 $38.62 Labor Cost O & M Total Hrs/Yr
INFORMATION COLLECTION ACTIVITY Cost
Letter of Intent











Company and Institutional Partners a











Review and complete LOI 1.00 1.33 0.67 0.00 3.00 $291.64 $0 $0 32 1 96.0 $9,333
Submit LOI to EPA and file copy 0.00 0.00 0.00 0.50 0.50 $19.31 $0 $3 32 1 16.0 $714
SUBTOTAL









112 $10,046
CHP Project Reporting Forms











Review form and instructions and complete form (new partners) b 0.00 0.50 0.00 0.00 0.50 $45.95 $0 $0 28 1 14.0 $1,287
Verify and update spreadsheet (existing partners) c 0.00 1.61 1.33 0.00 2.94 $256.27 $0 $0 228 1 670.3 $58,431
Submit spreadsheet to EPA electronically and file a copy 0.00 0.00 0.50 0.00 0.50 $40.72 $0 $3 256 1 128.0 $11,192
SUBTOTAL









812.3 $70,909
Information Updates and Follow-ups











Submit contact or profile information updates via Web d 0.00 0.00 0.25 0.00 0.25 $20.36 $0 $0 40 1 10.0 $814
Clarify LOI or project information via email or telephone interview e 0.00 0.00 0.25 0.00 0.25 $20.36 $0 $0 72 1 18.0 $1,466
SUBTOTAL









28.0 $2,280
TOTAL







260f
952.3 $83,236













*Labor rates for the company and institutional respondent tables are derived from national hourly labor rates from Bureau of Labor Statistics and consultations with three current CHP partners. Each partner offered a base hourly wage rate for legal, managerial, technical, and clerical occupations. These consultations did not include benefits or overhead. A loaded labor rate to reflect benefits and overhead for the respondent organizations was calculated by applying a 110% factor to the average of the base rates received from the consultations.





a Assumed 32 new company/institutional partners in the year 2010, spread evenly among project developers, end-users, consulting engineers, equipment manufacturers, and utilities.











b Assumed all new end-users, project developers, consulting engineers, and equipment manufacturers (6 each of end users and equip. man.; and 7 each of project developers and consulting engineers) who join in 2010 will fill out a project form. Assumed 33% of the 6 utility partners who join in 2010 (i.e. 2 utilities) will fill out a project form.



c All Project developers, end users, ESCOs, consulting engineers, and equipment manufacturers, and 33% of utilities review their project information and provide updates annually. Of the estimated 294 partners at the end of 2009, 228 partners belong to these categories. They will receive a spreadsheet already populated with their project data once a year and will verify and update their project information on this spreadsheet in 2010.



d Assumed 15% of new and existing company/institutional partners in the year 2010 (264 projected total partners), will update their information over the CHP website sometime during the calendar year.











e Assumed 25% of the 32 new company/institutional partners completing their LOI (i.e. 8 partners) will require follow-up. Additionally, 25% of the 256 partners completing CHP project forms or spreadsheets (i.e. 64 partners) will require follow-up in order to correctly complete the form.



f The total number of unique respondents submitting information in 2010 is 260, including 228 existing partners who are expected to complete project reporting spreadsheets, 28 new company and institutional partners who will fill out both a LOI and project reporting form, and 4 new company and institutional partners who will fill out only a LOI.






Sheet 3: B-3
















Total Hours and Costs

Lgl $ per Hour* Mgr. $ per Hour* Tech. $ per Hour* Cler. $ per Hour* Respon- dent Hours
Capital/ Startup Cost
Number of Respon- dents Frequency of Response
Total Cost/Yr

$114.85 $91.90 $81.44 $38.62 Labor Cost O & M Total Hrs/Yr
INFORMATION COLLECTION ACTIVITY Cost
Letter of Intent











Company and Institutional Partners a











Review and complete LOI 1.00 1.33 0.67 0.00 3.00 $291.64 $0 $0 32 1 96.0 $9,333
Submit LOI to EPA and file copy 0.00 0.00 0.00 0.50 0.50 $19.31 $0 $3 32 1 16.0 $714
SUBTOTAL









112 $10,046
CHP Project Reporting Forms











Review form and instructions and complete form (new partners) b 0.00 0.50 0.00 0.00 0.50 $45.95 $0 $0 28 1 14.0 $1,287
Verify and update spreadsheet (existing partners) c 0.00 1.61 1.33 0.00 2.94 $256.27 $0 $0 256 1 752.6 $65,606
Submit spreadsheet to EPA electronically and file a copy 0.00 0.00 0.50 0.00 0.50 $40.72 $0 $3 284 1 142.0 $12,416
SUBTOTAL









908.6 $79,309
Information Updates and Follow-ups











Submit contact or profile information updates via Web d 0.00 0.00 0.25 0.00 0.25 $20.36 $0 $0 45 1 11.3 $916
Clarify LOI or project information via email or telephone interview e 0.00 0.00 0.25 0.00 0.25 $20.36 $0 $0 79 1 19.8 $1,608
SUBTOTAL









31.0 $2,525
TOTAL







288f
1,051.6 $91,880













*Labor rates for the company and institutional respondent tables are derived from national hourly labor rates from Bureau of Labor Statistics and consultations with three current CHP partners. Each partner offered a base hourly wage rate for legal, managerial, technical, and clerical occupations. These consultations did not include benefits or overhead. A loaded labor rate to reflect benefits and overhead for the respondent organizations was calculated by applying a 110% factor to the average of the base rates received from the consultations.





a Assumed 32 new company/institutional partners in the year 2011, spread evenly among project developers, end-users, consulting engineers, equipment manufacturers, and utilities.











b Assumed all new end-users, project developers, consulting engineers, and equipment manufacturers (6 each of end users and equip. man.; and 7 each of project developers and consulting engineers) who join in 2011 will fill out a project form. Assumed 33% of the 6 utility partners who join in 2011 (i.e. 2 utilities) will fill out a project form.



c All Project developers, end users, ESCOs, consulting engineers, and equipment manufacturers, and 33% of utilities review their project information and provide updates annually. Of the estimated 328 partners at the end of 2010, 256 partners belong to these categories. They will receive a spreadsheet already populated with their project data once a year and will verify and update their project information on this spreadsheet in 2010.



d Assumed 15% of new and existing company/institutional partners in the year 2011 (296 projected total partners), will update their information over the CHP website sometime during the calendar year.











e Assumed 25% of the 32 new company/institutional partners completing their LOI (i.e. 8 partners) will require follow-up. Additionally, 25% of the 284 partners completing CHP project forms or spreadsheets (i.e. 64 partners) will require follow-up in order to correctly complete the form.



f The total number of unique respondents submitting information in 2010 is 288, including 256 existing partners who are expected to complete project reporting spreadsheets, 28 new company and institutional partners who will fill out both a LOI and project reporting form, and 4 new company and institutional partners who will fill out only a LOI.






Sheet 4: B-4



Total Hours and Costs

Mgr. $ per Hour* Tech. $ per Hour* Cler. $ per Hour* Respon- dent Hours
Capital/ Startup Cost
Number of Respon- dents Frequency of Response
Total Cost/Yr

$82.88 $52.60 $20.13 Labor Cost O & M Cost Total Hrs/Yr
INFORMATION COLLECTION ACTIVITY
Letter of Intent










State/Local/Tribal Partners a










Review and complete LOI 3.00 0.00 0.00 3.00 $248.64 $0 $0 2 1 6.0 $497
Submit LOI to EPA and file copy 0.00 0.00 0.50 0.50 $10.07 $0 $3 2 1 1.0 $26
SUBTOTAL








7 $523
CHP Project Reporting Forms










Review form and instructions and complete form (new partners) b 0.00 0.00 0.00 0.00 $0.00 $0 $0 0 1 0.0 $0
Verify and update spreadsheet (existing partners) c 0.00 0.00 0.00 0.00 $0.00 $0 $0 0 1 0.0 $0
Submit spreadsheet to EPA electronically and file a copy 0.00 0.00 0.00 0.00 $0.00 $0 $3 0 1 0.0 $0
SUBTOTAL








0.0 $0
Information Updates and Follow-ups










Submit contact or profile information updates via Web d 0.00 0.25 0.00 0.25 $13.15 $0 $0 3 1 0.8 $39
Clarify LOI or project information via email or telephone interview e 0.00 0.25 0.00 0.25 $13.15 $0 $0 1 1 0.3 $13
SUBTOTAL








1.0 $53
TOTAL






2 f
8.0 $576












* Agency labor rates were taken from the source table: 2008 GS Salary Table of Annual Rates by Grade and Step from the Office of Personnel Management. Manager rates assumed a GS level 15 step 5; technical rates assumed a GS level 13 step 1; clerical rates assumed a GS level 5 step 1. A loaded hourly wage to account for benefits and overhead was calculated from the annual rates given in the table according to the instructions in the ICR Handbook, p A-42. GS Hourly wage = [GS annual salary($)/2080 (hours/year)]*1.6





a Assumed 2 new state partners during each of the three year ICR period.










b State partners are not required to fill out project reporting forms.










c State partners are not required to fill out project reporting forms.










d Assumed 15% of new and existing state partners in the year 2009 (18 projected total partners), will update their information over the CHP website sometime during the calendar year.










e Assumed one of the two new partners completing their LOI will require followup.










f The total number of unique respondents submitting information in 2009 is 2, both of which are state/local/tribal government partners who will complete an LOI.



















































































































































































































































































Sheet 5: B-5



Total Hours and Costs

Mgr. $ per Hour* Tech. $ per Hour* Cler. $ per Hour* Respon- dent Hours
Capital/ Startup Cost
Number of Respon- dents Frequency of Response
Total Cost/Yr

$82.88 $52.60 $20.13 Labor Cost O & M Cost Total Hrs/Yr
INFORMATION COLLECTION ACTIVITY
Letter of Intent










State/Local/Tribal Partners a










Review and complete LOI 3.00 0.00 0.00 3.00 $248.64 $0 $0 2 1 6.0 $497
Submit LOI to EPA and file copy 0.00 0.00 0.50 0.50 $10.07 $0 $3 2 1 1.0 $26
SUBTOTAL








7 $523
CHP Project Reporting Forms










Review form and instructions and complete form (new partners) b 0.00 0.00 0.00 0.00 $0.00 $0 $0 0 1 0.0 $0
Verify and update spreadsheet (existing partners) c 0.00 0.00 0.00 0.00 $0.00 $0 $0 0 1 0.0 $0
Submit spreadsheet to EPA electronically and file a copy 0.00 0.00 0.00 0.00 $0.00 $0 $3 0 1 0.0 $0
SUBTOTAL








0.0 $0
Information Updates and Follow-ups










Submit contact or profile information updates via Web d 0.00 0.25 0.00 0.25 $13.15 $0 $0 3 1 0.8 $39
Clarify LOI or project information via email or telephone interview e 0.00 0.25 0.00 0.25 $13.15 $0 $0 1 1 0.3 $13
SUBTOTAL








1.0 $53
TOTAL






2 f
8.0 $576












* Agency labor rates were taken from the source table: 2008 GS Salary Table of Annual Rates by Grade and Step from the Office of Personnel Management. Manager rates assumed a GS level 15 step 5; technical rates assumed a GS level 13 step 1; clerical rates assumed a GS level 5 step 1. A loaded hourly wage to account for benefits and overhead was calculated from the annual rates given in the table according to the instructions in the ICR Handbook, p A-42. GS Hourly wage = [GS annual salary($)/2080 (hours/year)]*1.6





a Assumed 2 new state partners during each of the three year ICR period.










b State partners are not required to fill out project reporting forms.










c State partners are not required to fill out project reporting forms.










d Assumed 15% of new and existing state partners in the year 2010 (20 projected total partners), will update their information over the CHP website sometime during the calendar year.










e Assumed one of the two new partners completing their LOI will require followup.










f The total number of unique respondents submitting information in 2010 is 2, both of which are state/local/tribal government partners who will complete an LOI.























































































































































































































Sheet 6: B-6



Total Hours and Costs

Mgr. $ per Hour* Tech. $ per Hour* Cler. $ per Hour* Respon- dent Hours
Capital/ Startup Cost
Number of Respon- dents Frequency of Response
Total Cost/Yr

$82.88 $52.60 $20.13 Labor Cost O & M Cost Total Hrs/Yr
INFORMATION COLLECTION ACTIVITY
Letter of Intent










State/Local/Tribal Partners a










Review and complete LOI 3.00 0.00 0.00 3.00 $248.64 $0 $0 2 1 6.0 $497
Submit LOI to EPA and file copy 0.00 0.00 0.50 0.50 $10.07 $0 $3 2 1 1.0 $26
SUBTOTAL








7 $523
CHP Project Reporting Forms










Review form and instructions and complete form (new partners) b 0.00 0.00 0.00 0.00 $0.00 $0 $0 0 1 0.0 $0
Verify and update spreadsheet (existing partners) c 0.00 0.00 0.00 0.00 $0.00 $0 $0 0 1 0.0 $0
Submit spreadsheet to EPA electronically and file a copy 0.00 0.00 0.00 0.00 $0.00 $0 $3 0 1 0.0 $0
SUBTOTAL








0.0 $0
Information Updates and Follow-ups










Submit contact or profile information updates via Web d 0.00 0.25 0.00 0.25 $13.15 $0 $0 4 1 1.0 $53
Clarify LOI or project information via email or telephone interview e 0.00 0.25 0.00 0.25 $13.15 $0 $0 1 1 0.3 $13
SUBTOTAL








1.3 $66
TOTAL






2 f
8.3 $589












* Agency labor rates were taken from the source table: 2008 GS Salary Table of Annual Rates by Grade and Step from the Office of Personnel Management. Manager rates assumed a GS level 15 step 5; technical rates assumed a GS level 13 step 1; clerical rates assumed a GS level 5 step 1. A loaded hourly wage to account for benefits and overhead was calculated from the annual rates given in the table according to the instructions in the ICR Handbook, p A-42. GS Hourly wage = [GS annual salary($)/2080 (hours/year)]*1.6





a Assumed 2 new state partners during each of the three year ICR period.










b State partners are not required to fill out project reporting forms.










c State partners are not required to fill out project reporting forms.










d Assumed 15% of new and existing state partners in the year 2011 (22 projected total partners), will update their information over the CHP website sometime during the calendar year.










e Assumed one of the two new partners completing their LOI will require followup.










f The total number of unique respondents submitting information in 2010 is 2, both of which are state/local/tribal government partners who will complete an LOI.






















































































































































































































File Typeapplication/vnd.ms-excel
AuthorERG - Morrisville
Last Modified ByCPPD OAP
File Modified2009-02-12
File Created2004-12-17

© 2024 OMB.report | Privacy Policy