Transmittal Handbook No.: 7417.1 REV-1 CHG-12
R Issued: December 21, 1992
CHAPTER 3. DEVELOPMENT REQUIREMENTS
Section 1. General
3-16. Architects. Project planning, design, and administration of
construction contracts require the services of an architect or
other professional registered to provide the necessary services in
the State in which the project will be located. The PHA shall
determine the services required and shall select a qualified
individual in compliance with the program requirements.
_______________________________________________________________________
12/92 3-10
________________________________________________________________________
a. Scope of Services. The extent of architectural services
will vary depending on the development method selected by
the PHA.
(1) Conventional Method: Under the conventional method, the
architect provides all required professional services
for project planning, design, and administration of the
construction contract. This includes the development of
design concepts, preparation of design and construction
documents, rehabilitation work write-ups, and project
cost estimates; evaluation of construction bids;
inspection of materials and workmanship during
construction; notifying the contractor and the PHA of
problems observed; and certification that construction
is performed in accordance with the construction
contract.
(2) Turnkey Method: Under the turnkey method, the architect
is generally responsible only for performing construction
inspections and certifying that construction is
performed in accordance with the contract of sale.
(3) Acquisition Method: Under the acquisition method, an
architect usually is not necessary due to the limited
scope of repair work. However, the PHA may employ an
architect for project planning and administration of
the repair contract, if appropriate.
b. Selection. The PHA shall select an architect on the basis
of professional and technical competence, experience,
knowledge of local building codes, and capability to provide
professional services in a timely manner. Every effort
should be made to retain an architect prior to the project
planning conference (Chapter 6).
c. Area Office Approval. The PHA, upon selecting an architect,
shall prepare and submit the PHA architect's contract to
the Area Office for approval prior to execution by the PHA.
The Agreement Between Owner and Architect (Form HUD 51915)
is used for projects being developed under the conventional
and acquisition methods. The Contract for Inspection
Services (Form HUD 5084) is used for projects being developed
under the turnkey method.
________________________________________________________________________
3-11 10/80
________________________________________________________________________
d. Compensation. At the time the contract for architectural
services is prepared the PHA and the architect, subject to
Area Office approval, shall agree upon the compensation to
be specified in the contract. Architectural fees shall be
consistent with those which prevail for similar projects
and services in the area. The amount of compensation is
usually stated as a percent of the estimated construction
cost for the project, an hourly rate, per sheet fee or
lump sum amount. In determining fees, consideration
should be given to the following:
(1) scope of basic services;
(2) type of project, size, and complexity of design;
(3) extent that previously completed architectural drawings
are being used;
(4) extent that prefabricated or modular components are
being used;
(5) extent that a project consists of repetitive basic
structures;
(6) the number of construction contracts - prime and separate
trades contracts - to be administered; and
(7) anticipated complexity of the Turnkey Developer's Packet
and developer response.