When the FERC
resubmits the package upon the final rule's promulgation, it should
identify the costs that are incurred solely due to information
collection, dissemination, or storage, not those associated with
conditions or modifications required by the licensing/relicensing
process. The FERC should also calculated the hour burden by
estimating the proportion of the licensees that would choose each
of the three available processes, and multiplying each proportion
by the respective time each process is estimated to require for
completion.
Inventory as of this Action
Requested
Previously Approved
06/30/2003
07/31/2004
06/30/2003
12
0
12
4,512
0
0
241,000
0
241,000
In RM02-16-000, FERC proposes to
revise its regulations concern- ing the hydroelectric license
process under the Federal Power Act. The proposed revisions would
create a new licensing process in which a potential license
applicant's pre-filing consultation and the FERC's scoping
procedures in accordance with the National Environmental Policy Act
(NEPA) would be conducted concurrently.
On behalf of this Federal agency, I certify that
the collection of information encompassed by this request complies
with 5 CFR 1320.9 and the related provisions of 5 CFR
1320.8(b)(3).
The following is a summary of the topics, regarding
the proposed collection of information, that the certification
covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a
benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control
number;
If you are unable to certify compliance with any of
these provisions, identify the item by leaving the box unchecked
and explain the reason in the Supporting Statement.