Approval is
contingent upon our understanding that the SF 1443 requires a
contractor to either have paid its subcontractor costs or that
payment will be made, by the contractor, when due, in the ordinary
course of business. The date entered in "Section II - Statement of
Costs Under This Contract Through _______" is the date by which
incurred costs have been accumulated for inclusion in the progress
payment request, as explained in the instructions on the reverse of
the form. In cases where such incurred costs are actually paid by
the "Date of Request," they may be included in the request for
progress payment.
Inventory as of this Action
Requested
Previously Approved
08/31/1990
08/31/1990
08/31/1987
864,000
0
25,920
479,200
0
14,256
0
0
0
FIRMS PERFORMING UNDER FEDERAL
CONTRACTS THAT CALL FOR PROGRESS PAYMENTS, REQUEST SUCH PAYMENTS ON
THE SF 1443 AND PROVIDE FINANCIAL INFORMATION AS
NECESSARY.
On behalf of this Federal agency, I certify that
the collection of information encompassed by this request complies
with 5 CFR 1320.9 and the related provisions of 5 CFR
1320.8(b)(3).
The following is a summary of the topics, regarding
the proposed collection of information, that the certification
covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a
benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control
number;
If you are unable to certify compliance with any of
these provisions, identify the item by leaving the box unchecked