Approved subject
to the comments on FERC-500 (OMB# 1902-0058) dated 04/29/87. As in
FERC-500, 18 CFR 16.16(d)(1) and the "compile" requirement in
(c)(1) are NOT approved (see FERC-500 comments). The preamble and
justification statement provide little specific justification for
individual requirements contained in the regulation. If FERC
believes there is sufficient justification to require licensee to
inventory (or "complile") information covered by the regulations an
report "unavailable" information, then it could provide its
rational f public comment in future notice and comment rulemakings
that it will b conducting under the Electric Consumers Protection
Act. Such rulemakin should explain to the public what FERC intends
by 16.16(c)(2) - -- "available at the principal place of
business".
Inventory as of this Action
Requested
Previously Approved
10/31/1987
10/31/1987
10/31/1987
230
0
245
29,585
0
29,360
0
0
0
THE INTERIM RULE (RM87-8) REQUIRES THE
COMMISSION TO CARRY OUT THE REQUIREMENTS OF SECTION 8 OF THE
ELECTRIC CONSUMERS PROTECTION ACT OF 1986 (ECPA) CONCERNING THE
LICENSEE MAKING INFORMATION REGARDING CONSTRUCTION AND OPERATION OF
THE LICENSED PROJECT READILY AVAILABLE TO THE PUBLIC.
On behalf of this Federal agency, I certify that
the collection of information encompassed by this request complies
with 5 CFR 1320.9 and the related provisions of 5 CFR
1320.8(b)(3).
The following is a summary of the topics, regarding
the proposed collection of information, that the certification
covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a
benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control
number;
If you are unable to certify compliance with any of
these provisions, identify the item by leaving the box unchecked